Warehouse Fit Out Cost: What Drives the Price

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 10 min read

Fitted-out warehouse unit with two insulated loading doors, safety bollards, a sink and new internal doors in Hackney

The short answer

A warehouse fit out cost is set by the shell you start from and what you add. On our 2026 rates it is about £9 to £85.50 per sq ft, ex VAT and fees.

  1. Light refurbishment, mostly decoration, lighting and repairs: £9 to £27 per sq ft on our 2026 rates.
  2. Standard fit-out of power, heating, welfare and loading doors: £27 to £58.50. With offices and welfare: £37 to £85.50.
  3. Example: a standard fit-out of a 5,000 sq ft unit is about £135,000 to £292,500, before racking, sprinklers and mezzanines.
  4. One UK contractor's April 2026 guide publishes £10 to £150+ per sq ft. Add fees of 8 to 15 %, a contingency of 10 to 15 % and VAT at 20 %.

A warehouse fit out cost depends on two things: the shell you start from and what you add to it. On our 2026 rates a light refurbishment starts at about £9 per sq ft. A unit with offices and welfare reaches about £85.50, before VAT and fees.

We design and build warehouse fit outs in London and across the UK: offices, racking, mezzanines, power and welfare. This guide is written by warehouse fit out contractors who survey and build these units. Pricing a unit? Book a site visit and we will tell you what it needs before you commit.

Below are our rates and the bands another UK contractor publishes: £10 to £150+ per sq ft in an April 2026 guide. The bottom is a cosmetic refresh, the top a full strip-out and refit. Then we set out what moves a project within the bands and where budgets break.

Warehouse fit out cost per sq ft in 2026

These are our 2026 rates for construction only, ex VAT and fees. They assume a sound shell with enough incoming power. Your fixed figure comes after a survey.

Our 2026 warehouse fit out rates, ex VAT and fees
ScopeWhat it coversPer sq ftPer m²
Light refurbishmentDecoration, LED lighting, floor repairs, small electrical and fire alarm work£9 to £27£97 to £291
Standard fit-outPower, heating and ventilation upgrades, designed lighting, WCs and welfare, loading doors£27 to £58.50£291 to £630
Fit-out with offices and welfareOffices, kitchen, changing rooms and full services inside the unit£37 to £85.50£400 to £920

Take a 5,000 sq ft unit. A standard fit-out comes to about £135,000 to £292,500 on these rates. Racking, sprinklers and mezzanines are priced on top. A mezzanine floor is £72 to £180 per m² of deck, with stairs and balustrades extra.

One real project for scale: our Banbury warehouse cost £350K for the whole 2,500 m² building. That is about £140 per m², delivered in eight weeks.

What other published guides say

The clearest public figures come from Warehouse Construction Contractors, who published four bands on 23 April 2026. They are per sq ft, before fees, contingency and VAT.

Warehouse refurbishment and fit out cost per sq ft, UK, April 2026 (Warehouse Construction Contractors)
ScopeWhat it coversPer sq ft
Light refurbishmentDecoration, lighting, minor repairs and basic compliance; structure and services left in place£10 to £30
Mid-range refurbishmentServices, doors, loading and welfare; roof and cladding work at the upper end£30 to £65
Cat A+ refurbishmentA solid Cat A base plus offices, EV charging, solar PV and a strong EPC target£60 to £95
Full strip-out and refitExisting fit-out and services removed, new M&E and loading docks; complex mezzanines at the upper end£85 to £150+

The same guide gives worked examples. A 10,000 sq ft unit at the lower end of a light refurbishment costs roughly £100,000 to £150,000. A 20,000 sq ft unit at £35 per sq ft, in the mid-range band, comes to about £700,000.

On top of the build, the guide adds professional fees of 8 to 15 % and a contingency of 10 to 15 %. VAT at 20 % applies unless the project qualifies for a reduced or zero rate.

What drives warehouse fit out costs

Most of the spread inside a band comes from a handful of items. These are the ones to check before you budget.

  1. The shell. A sound unit with a good slab costs far less than one that needs floor, roof and cladding work.
  2. Roof and cladding. The guide puts a full single-ply roof on 20,000 sq ft at £150,000 to £250,000 alone.
  3. Power supply. Modern M&E can outgrow an older site's supply. A new supply or substation costs £50,000 to £200,000 or more, on the DNO's timescale.
  4. Asbestos. From a few thousand pounds for isolated items to £100,000 or more where boards or coatings are widespread.
  5. Offices and welfare. Small in area, but the most expensive part per square metre.
  6. Mezzanines and racking. Often the biggest single items; the slab must be rated for both.
  7. Working around operations. Phased, night and weekend work keeps the site trading but costs more per day.

Each of these shows up in a survey, not on a drawing. That is why a price given before anyone has looked at the slab, the roof and the supply rarely holds.

Check these are in the price you compare

Two quotes for the same unit can differ only because one leaves items out. Ask each contractor to show these lines.

  • Racking and shelving
  • Sprinklers and fire detection
  • Mezzanine stairs and balustrades
  • Line marking and safety barriers
  • A power supply upgrade
  • Fees, contingency and VAT

What a warehouse fit-out includes

The scope depends on the building and the operation. These are the items most warehouse fit-outs include.

Warehouse unit during works, with new electrical installation, equipment, scissor lift and materials on the floor in Hackney
Hackney: engineering systems installed and tested before handover.
Typical warehouse fit-out scope
ItemWhat it covers
FloorRepairs, levelling and a finish that suits forklifts and cleaning
Power and lightingNew distribution, sockets where the work happens, LED lighting by zone
Heating and ventilationHeating, cooling or extraction, depending on people and processes
Plumbing and welfareWCs, washbasins, a kitchen, changing rooms and lockers
OfficesPartitions, meeting rooms, data and an office for supervisors
StoragePallet racking, shelving and bulk floor zones
SafetyBarriers, marked walkways, fire detection, signage and exits
ExtrasMezzanines, loading doors, cold rooms or workshops

Racking and storage are often called the heart of a fit-out. But the floor and power come first. Racking can't go on a floor that isn't ready, and machines can't run without the right supply.

Craftex carried out a warehouse fit-out for us, and I couldn’t be happier with the outcome. The space has been completely transformed into a highly organized and efficient environment that makes our daily operations much smoother. The team was professional but also very approachable — I always felt comfortable asking questions or giving feedback. They came up with smart, practical solutions that worked perfectly for our setup, and everything was explained clearly along the way. The best part was how they stuck to the agreed timeline, finishing on schedule without cutting corners. It’s rare to get both quality and reliability, but Craftex delivered both.

Roma Shchukin, Google reviewSee all reviews on Google

Fit-out, refurbishment and renovation

People use these words loosely, so it helps to separate them.

  1. Fit-out equips a building for a specific operation: racking, offices, services and safety.
  2. Refurbishment is usually a smaller update: repainting, repairs, new lighting.
  3. Renovation repairs or upgrades the building itself, such as roofs, walls or wiring.

In practice they overlap. You may repair the floor before the racking goes in. Our guide to warehouse fit-out vs renovation compares the two routes in detail.

For an existing unit, our warehouse refurbishment and fit-out team surveys the shell first, then prices the scope. Building new rather than fitting out? That is warehouse and logistics hub construction.

Warehouse fit-out projects we have delivered

Three projects show how far the scope, and so the cost, can vary.

Aerial view of two black-clad industrial units beside a railway line and a flyover, with housing and trees around them
120 m²Hackney, 4 weeks
2,500 m²Banbury, 8 weeks
500 m²Drake's, 8 weeks

Hackney: every engineering system redesigned

At our Hackney warehouse fit-out, the 120 m² unit has 6 m ceilings. The client gave us an initial electrical layout. We improved it and installed it as part of a full redesign of the engineering systems. New electric heating spreads heat evenly. Bespoke lighting covers every work zone.

There was no natural drainage outlet for a new sink and an emergency shower. So we designed a pump system to carry the wastewater to a remote point. Every system was connected, inspected and tested. The work took four weeks.

Drake's: a railway arch fitted out without a single fixing

At Drake's, the client moved from a warehouse that was too big and too costly. The new space was a 500 m² railway arch. Nothing could be drilled into the structure.

So we built freestanding partitions and independent service frames, with a complete M&E design. Heating and cooling have zonal control, so energy is used only where it's needed. The five-year tenancy shaped every choice of material. The smaller, better-planned space cut rent, utilities and running costs.

Banbury: a fit-out inside a live warehouse

At our Banbury warehouse, we refitted the whole 2,500 m² building in eight weeks, adding 148 m² of welfare and storage space inside it. The warehouse kept operating throughout. The team got a changing room with lockers, and a storage room with pallet racking and safety barriers.

How long a warehouse fit out takes

Time on site depends on the scope and on whether the operation keeps running. Our own projects show the range.

Time on site for three Craftex warehouse projects
ProjectWhat we didSizeTime on site
HackneyEvery engineering system redesigned and installed120 m²4 weeks
Drake'sRailway arch fitted out with freestanding partitions and full M&E500 m²8 weeks
BanburyWhole warehouse refitted while it kept operating2,500 m²8 weeks

Design, approvals and ordering come before the start on site. Three things can add time.

  1. A power supply upgrade. It runs on the network operator's timescale, not the builder's.
  2. Long-lead items. Racking, doors and electrical gear can take longer than the build.
  3. A live operation. The work is done in phases, at night or at weekends, so the site keeps trading.

With a fixed move-in date, the order of work is set around it at the start.

How to plan a warehouse fit-out budget

A practical fit-out follows the same order every time, and the budget follows it too.

  1. Fix the operation. What you store, how it moves and how many people work each shift.
  2. Plan the layout. Place the zones and routes. Our guide to warehouse layout design and planning explains how.
  3. Survey the building. Floor condition, clear height, roof, doors, drainage, asbestos and incoming power.
  4. Check approvals. Building control for partitions, WCs and services. Planning only for external changes or a new use.
  5. Order long-lead items. Racking, doors and electrical gear can take longer than the build.
  6. Build in the right order. Floor and services first, then racking, offices and finishes.

What a warehouse fit out survey checks

A real price starts with a survey. We walk the unit with you and check the things that move the cost.

  1. Floor slab. Condition, level and the load it can take for racking, mezzanines and machines.
  2. Roof and cladding. Leaks, rooflights and insulation.
  3. Incoming power. The size of the supply against what your operation will draw.
  4. Doors and loading. The number, size and condition of the loading doors.
  5. Drainage and water. Where new WCs, sinks and wash-down points can connect.
  6. Asbestos. Whether a register exists and what it shows.
  7. Height and fire safety. Clear height for racking, plus detection, exits and any sprinklers.

After the visit you get a written scope, priced line by line. That is the figure to compare with any other quote.

Rules a warehouse fit-out must meet

Works that affect only the interior of a building are not development under planning law. So most fit-outs need no planning permission. Most do need building control, because new partitions, WCs and services are building work.

Storage and distribution is Use Class B8. If your operation is general industrial, that is B2. Moving between them can need permission.

HSE guidance says roadways and footpaths should be separate whenever possible. Plan barriers and crossing points into the fit-out, not after it. Size welfare to your headcount: HSE's table asks for two toilets for 6 to 25 people.

Adding a floor inside the warehouse? Read our guide to warehouse mezzanine floor regulations first.

Factory and industrial unit fit out

A factory fit out or industrial fit out follows the same order as a warehouse. The difference is the process inside the building.

  1. Power for machines. The machines set the size of the supply and where the distribution goes.
  2. Extraction and ventilation. Fumes, dust and heat from a process need their own extract.
  3. Floors for plant. Machine bases, load points and finishes that stand up to oils or chemicals.
  4. People and vehicles. Marked walkways and barriers between staff, forklifts and plant.
  5. Use class. General industrial use is B2. Storage and distribution is B8.

Our Hackney project was an industrial unit of this kind. It needed fume extraction, an emergency safety shower and new heating. We work as industrial fit out contractors for factories, workshops and production units as well as warehouses.

One team from shell to handover

A fit-out touches design, M&E, racking, building control and your own move-in plan. Every gap between them is where weeks and money go missing.

We design and build warehouses as one team. That covers storage and distribution space, from industrial storage facilities and distribution centres to new-build warehouse and logistics hubs. If the warehouse has offices, our guide to office design and fit-out costs helps with that part. Need offices to match? We also deliver office fit-outs in London.

Have a unit and a start date? Book a site visit and we'll tell you what the fit-out needs and what drives its cost. We reply within one hour, Monday to Saturday, 8am to 6pm.

What to have ready for a price

  • What you store and how it moves: pallets, cartons, long goods or machines
  • How many people work on each shift
  • The storage you want: pallet racking, shelving or bulk floor space
  • Whether you need a mezzanine now or later
  • Whether you need a picking and packing area
  • Your move-in date, and whether the site must keep working during the works
  • Drawings of the unit, the lease and the EPC, if you have them

Frequently asked questions

How much does a warehouse fit out cost per sq ft?

On our 2026 rates a light refurbishment is £9 to £27 per sq ft. A standard fit-out is £27 to £58.50 and one with offices and welfare £37 to £85.50, ex VAT and fees. Warehouse Construction Contractors' April 2026 guide gives £10 to £30 per sq ft for a light refurbishment and £30 to £65 for mid-range work. It gives £60 to £95 for Cat A+ and £85 to £150+ for a full strip-out and refit. Fees, contingency and VAT come on top.

What is included in a warehouse fit-out?

Usually floor preparation and finishes, power and lighting, heating and ventilation, plumbing and welfare, offices and partitions, racking and storage, safety barriers and fire safety. Larger fit-outs add mezzanines, loading doors and specialist areas such as cold storage.

What pushes a warehouse fit out to the top of its band?

A roof or cladding replacement, a power supply upgrade, asbestos removal, offices and welfare, and work phased around a live operation. The same guide puts a supply upgrade or new substation at £50,000 to £200,000 or more.

How long does a warehouse fit-out take?

It depends on the scope and how much of the operation must keep running. Our Hackney fit-out of 120 m² took four weeks, Banbury's 2,500 m² warehouse and Drake's 500 m² railway arch took eight each. Design, approvals and ordering come before that.

Can operations continue during a warehouse fit-out?

Often, yes, if the works are phased. At Banbury we refitted a 2,500 m² warehouse in eight weeks while it kept operating, with 148 m² of new welfare and storage space inside it.

Do I need planning permission for a warehouse fit-out?

Works that affect only the interior of a building are not development under planning law. Most fit-out items, such as partitions, WCs and new services, need building control instead. External changes, extra floor space or a change of use may need permission.

Do you fit racking and mezzanine floors as part of a warehouse fit out?

Yes. We deliver the fit-out as one contract: floor, power, lighting, welfare, offices, racking and mezzanine floors. At Banbury we installed the pallet racking and steel safety barriers. On our 2026 rates a mezzanine costs £72 to £180 per m² of deck. Stairs and balustrades are extra.

What does a factory or industrial fit out involve?

The same steps as a warehouse fit out, shaped by the process inside. Plan power for the machines, extraction and ventilation, floors that take plant, and marked routes that keep people apart from vehicles. General industrial use is Class B2.

What happens at a site visit for a warehouse fit out?

We walk the unit with you and check the floor slab, roof, incoming power, doors, drainage and fire safety. Then we send a written scope, priced line by line. We reply within one hour, Monday to Saturday, 8am to 6pm.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Need a warehouse fit out cost you can rely on?