Construction Project Planning and the Programme

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read

Full-height scaffold and temporary works holding retained brick façades during structural works in Covent Garden

The short answer

Construction project planning is deciding everything that can be decided before site, so the site only has to build: scope, budget, programme, risks and approvals.

  1. Write the brief, the deadline and the budget before anyone draws.
  2. Survey the building: most surprises are already in it on day one.
  3. Plan backwards from the deadline, including legal notice periods.
  4. Price the scope unit by unit and keep contingency as a visible line.

Construction project planning is deciding everything that can be decided before work starts on site: brief, budget, programme, risks and approvals. Done well, the site only has to build.

An office move shows why. Its deadline never moves: the day the old lease ends. At Beaumont House the client had five weeks left, more than 150 staff to move, and quotes of at least 12 weeks.

We settled the survey, scope and sequence first. We were on site two weeks after the first contact and handed over the 750 m² floor three weeks later, with zero snags.

This guide walks through how our construction project management in London team plans a job and writes the construction programme, in the order it happens. It includes the UK deadlines that decide your start date. Got a deadline? Book a site visit and we'll tell you if it's achievable.

The first step in construction project planning

The first step is writing down what the project must achieve and what it may cost. Do it before anyone draws anything. In practice that's four answers:

  1. What is being built, and why? "New office for 120 people with room for 150" is a brief. "Refresh the office" isn't.
  2. When must it finish? A lease expiry, a school term or an opening date is a hard deadline. Plan backwards from it.
  3. What is the budget, and what's in it? Construction only, or design, fees, furniture, IT and VAT too?
  4. Who decides? One person with authority to sign off design and cost.

Then survey what's there. Most of the surprises that wreck a programme are already in the building on day one.

At Drake's, inside a London railway arch, nothing could be fixed into the structure. So every partition and service frame was designed to stand on its own. Finding that during design cost a drawing revision. Finding it on site would have cost weeks.

Good construction space planning starts from the same survey.

The five stages of construction project planning

The classic stages are initiation, planning, execution, monitoring and control, and closure. To outsiders, construction project management can look chaotic. But every job follows these stages. In the UK they line up with the RIBA Plan of Work 2020.

Project planning stages and the RIBA Plan of Work 2020
StageRIBA Plan of Work 2020What we do at this point
1. Initiation0 Strategic Definition, 1 Preparation and BriefingBrief, survey and Feasibility Study before any planning application
2. Planning2 Concept Design, 3 Spatial Coordination, 4 Technical DesignDesign and consents, then Pre-Construction at RIBA Stage 4
3. Execution5 Manufacturing and ConstructionSite works with our own labour and specialist trades
4. Monitoring and controlRuns through stage 5Weekly programme and cost reviews, change control, inspections
5. Closure6 Handover, 7 UseTesting, commissioning, handover documents, aftercare

Initiation tests the idea before money is committed. For development work, this is where a free site appraisal belongs. It's also where an owner decides who runs the scheme: see development management fees explained. For a fit-out, it's where you brief the contractor.

Planning develops the design until it can be priced unit by unit. Our Pre-Construction stage is RIBA Stage 4 technical design: detailed drawings, priced scope, programme and long-lead orders.

Execution, monitoring and closure follow. Progress and cost are checked every week. Every change gets a price and a time effect before it's approved. Our guide to what construction project management is covers this part in depth.

The UK deadlines that set your start date

A programme isn't just how long the work takes. Several legal and landlord steps have fixed notice periods. They often decide the earliest date you can start.

Crane jib being lifted in on a central London street by operatives in hi-vis, with traffic barriers and period buildings behind
Slingsby Place, Covent Garden (delivered by our team): crane lifts and road closures agreed with the local authority in advance.
Legal and landlord checkpoints to build into the programme
CheckpointWhen it appliesTime to plan for
Planning permissionNew build, extensions, change of useStatutory target of 8 weeks, or 13 weeks for major development
Landlord's licence for alterationsMost leasehold fit-outsSet by the landlord's surveyor; often the slowest item
Party wall noticesWork to a party wall or nearby excavation2 months for party wall work; 1 month for a new boundary wall or excavation; 14 days to respond
Building RegulationsMost structural, fire, services and layout changesApproval before work; dutyholders appointed since October 2023
CDM 2015 notificationOver 30 working days with 20+ workers at once, or over 500 person daysClient notifies HSE before the construction phase
Building Safety RegulatorResidential buildings of 18 m or 7 storeys, with 2+ homesApproval before work starts

Two of these catch out more clients than all the others. One is the landlord's licence on a fit-out. The other is party wall notices on anything structural. Both can be started early.

Not sure which of these apply to your building? Our construction project management team lists the consents, notice periods and lead times for your job, then builds the programme backwards from your deadline.

Work breakdown structure in project planning

A work breakdown structure (WBS) splits the project into packages. Each one is small enough to price, programme and give to one person. Instead of "fit out the office", a WBS might read:

  • Strip-out and enabling works
  • Partitions and ceilings
  • Mechanical services: heating, cooling and ventilation
  • Electrical services, lighting and data
  • Fire alarm and life safety
  • Joinery, kitchen and WCs
  • Floor finishes and decoration
  • Testing, commissioning and handover

A WBS shows the whole scope before it costs you. Each line has an owner, a duration and a cost. It's also the only honest way to compare prices. A quote with one line for "electrical installation" can't be checked against the drawings.

Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

Pawel Kamionka, Google reviewSee all reviews on Google

Budget and programme: the two documents that run the job

The cost plan is built from the WBS and priced unit by unit. Material prices move, so it should say when its rates were checked. Our article on the rising cost of construction materials explains what's driving them. For office budgets, see office design and fit-out costs in the UK.

Contingency should match what is still unknown. Keep it as a separate, visible line, and agree who can spend it.

Design cost comes in early. Medusa in Knightsbridge came to us at RIBA Stage 2 with a concept and a few 3D visuals. The people who finished the design also priced it, so every choice was costed before it reached the wall. The four-floor salon and spa was designed and built in 17 weeks.

The critical path is the chain of activities with no slack. If one slips, the finish date slips. Long-lead items like bespoke joinery, plant and switchgear usually sit on it.

Fixed deadlines leave no float. At Beaumont House the lease date set the programme. Work back from the date. Anything that can't fit becomes a decision for the brief, not a surprise on site.

How to write a construction programme

A construction programme is the build in time order: every activity, how long it takes and what it waits for. A good one tells you the finish date and which activities can move it.

Most programmes are drawn as a Gantt chart: one bar per activity against a calendar. Build it in four passes.

  1. List the activities from the work breakdown structure, at a level the site can manage week by week.
  2. Give each one a duration from the contractor, the supplier or a comparable job, not a guess.
  3. Link them in order. Strip-out before first fix, first fix before plastering, plant on site before commissioning.
  4. Find the critical path and mark long-lead items, consents and notice periods as milestones.
Example programme for a fit-out floor, as a simple Gantt in words
ActivityDepends onTiming
Survey and strip-outAccess to the floorStart
First fix servicesStrip-out completeAfter strip-out
Partitions and ceilingsFirst fix in the wallsOverlaps first fix by area
Second fix and joineryPlastering dryLong-lead joinery ordered at the start
Commissioning and snaggingServices completeBefore the handover date

Update the programme every week against progress on site. The value is not the chart; it is seeing a slip in week three, not week twelve.

Risk: name it, price it, give it an owner

A risk register lists what could go wrong, how likely it is, what it would cost and who prevents it. The risks that hurt London projects are rarely exotic.

Strip-out in progress behind scaffolded façades, with demolition rubble, steelwork and an access stair on a central London site
Slingsby Place, led by Martin Hickey, now our Preconstruction Director, as Project Director.
  1. Hidden conditions in existing buildings. A warehouse unit in Hackney had no natural outflow for waste water. The sink and emergency shower needed a pumped drainage system, planned before installation.
  2. Occupied buildings. At Portsoken House, the other floors stayed let, so we rebuilt the reception at night and at weekends.
  3. Late decisions. Every week a finish stays undecided is a week the programme loses later.
  4. Consents and notices not started early enough.

Space planning tools and the survey behind them

A space planning tool lets architects, high-end interior designers and project managers test a layout digitally. They plan room sizes, furniture, circulation, exits and access for disabled people.

The tool is only as good as the survey behind it. A layout drawn on an inaccurate plan looks perfect until the partitions arrive. We measure first, then plan. Our office fit-out and commercial fit-out teams work from that same survey through to handover.

Plan first, then build

Construction project planning is how office design ideas and building plans turn into something finished on time. The same applies to the redevelopment projects we work on. Around 60% of our labour is in-house. Every project we have delivered has finished ahead of programme and on budget.

Choosing who to plan and build it with? Our guide to choosing the right commercial contractor lists the questions to ask. How we keep London projects on time and on budget shows the method, and our case studies show the results.

Tell us your deadline. Book a site visit and we'll tell you what has to happen, and by when, to hit it.

Frequently asked questions

What is the first step in construction project planning?

Write down what the project must achieve, when it must finish and what it may cost, before anyone draws anything. Then survey the building, because most of the surprises that break a programme are already in it.

What are the 5 stages of project planning?

Initiation, planning, execution, monitoring and control, and closure. In UK construction they are usually mapped to the RIBA Plan of Work 2020, from Stage 0 Strategic Definition to Stage 7 Use.

What is a work breakdown structure in construction?

A work breakdown structure (WBS) splits the project into packages small enough to price, programme and give to one person to deliver, such as strip-out, partitions, mechanical services, electrical services and finishes.

What is the critical path method in construction?

It finds the longest chain of dependent activities in the programme. Those activities have no slack, so any delay to them delays completion. Long-lead items such as bespoke joinery, plant and switchgear often sit on it.

How long does construction project planning take?

It depends on the size of the job and the consents it needs. Beaumont House went from first contact to site in two weeks. Schemes that need planning permission, party wall awards or a landlord's licence can't start until those are in place.

Who is responsible for planning a construction project, the client or the contractor?

Both have legal duties. Under CDM 2015 the client must make suitable arrangements for managing the project, including enough time and resources. The contractor then plans and manages the construction work itself.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Deadline set, plan not written yet?

Our design and build team checks the building and the approvals on site, then gives you a programme and a price before you commit. Book a site visit.

Reply within 1 hour, Mon–Sat 8am–6pm. Urgent? WhatsApp us for a reply straight away, any day.

WhatsApp us