What Does a Commercial Contractor Do? Full Guide

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read

Open-plan office floor with rows of desks, slim columns and a new ceiling grid after the internal walls came out

The short answer

A commercial contractor builds, converts, refurbishes or fits out buildings used for business. They price the work, plan the programme, run the site and the trades, and carry the legal health and safety duties until handover.

  1. Before work starts: survey, price, programme and order the long-lead items.
  2. On site: manage every trade, safety, quality, neighbours and changes.
  3. By law: usually acts as principal contractor under CDM 2015.
  4. At the end: test, sign off, hand over and fix defects.

A commercial contractor builds, converts, refurbishes or fits out buildings used for business: offices, shops, restaurants, clinics, schools and warehouses. They survey and price the work, plan the programme, run the trades on site and carry the legal safety duties until handover.

Most people only meet one when something has to be built by a date. A lease ends. A shop must open. A team has to move before the old lease runs out.

This guide explains the job in plain English, stage by stage. It covers the legal roles, the main types of contractor and how the work looks on real projects.

We work as a main contractor in London and as commercial fit out contractors, so it's written from the builder's side. Have a building in mind? Book a site visit and we'll walk it with you.

What a commercial contractor does, in short

A commercial contractor delivers construction work for a business. That means offices, shops, restaurants, clinics, schools and warehouses. The work can be a new build, a conversion, a refurbishment or a fit-out.

The contractor takes your design and your budget and turns them into a finished building. They plan the work, hire and manage the trades and buy the materials. They control safety and quality on site. Then they test everything, hand it over and fix any defects.

On most projects the contractor is also the one legal point of control on site. That's the role the law calls principal contractor. More on that below.

The commercial contractor's job, stage by stage

The work starts long before anyone picks up a tool. This is how the job runs on a typical commercial fit-out or refurbishment.

What a commercial contractor does at each stage
StageWhat the contractor doesWhat you get
SurveyInspects the building, services, structure and accessA list of risks before you commit
PricingPrices the scope, line by line or as a lump sumA written price against a clear scope
ProgrammePlans the sequence and the long-lead itemsDates you can plan a move or opening around
Pre-constructionFinalises design details, orders materials, books tradesA site that starts ready, not waiting
ConstructionRuns the site, the trades, safety and quality every dayProgress you can see and measure
HandoverTests, commissions, cleans and signs offA working building and its manuals
AftercareReturns to fix defects in the agreed periodProblems fixed without a fight

Before work starts: survey, price and programme

The survey is where a good contractor earns its fee. Old buildings hide things. Floors are not level. Services are smaller than the drawings say. A price given before anyone has looked is a guess.

Medusa in Knightsbridge came to us with a design concept and a few visuals. We finished the design, and the people who drew it also priced it, so every choice was costed before it reached the wall. Then we stripped out and refitted four floors in 17 weeks.

On site: trades, safety, quality and neighbours

Once work starts, the contractor runs the site every day. They sequence the trades so nobody waits for anybody. They keep the site safe, check the work and deal with neighbours, tenants and the building manager.

They also manage change. Every project has some. A good contractor prices a change before it is built, so you decide with the cost in front of you.

At the end: testing, sign-off and handover

The last fortnight is busy. Fire alarms, emergency lighting, ventilation and power are tested. Building control signs off the work. You receive the certificates, the manuals and a clean building.

Five types of commercial contractor

Commercial construction isn't handled by one kind of firm. The right type depends on the size and scope of the job. Our guide to what commercial construction covers explains the work types.

  1. General or main contractors. They coordinate the whole project: planning, programme, budget and every trade on site. They oversee the build from start to finish.
  2. Design and build contractors. One company takes on both the design and the construction under one contract. You deal with one team, and design and cost develop together.
  3. Fit-out contractors. They complete the inside of a building. A Cat A fit-out gives you a usable shell with ceilings, lighting and services. A Cat B fit-out adds the layout, finishes, furniture and technology.
  4. Specialist contractors. They focus on one system, such as electrics, ventilation, plumbing, fire protection or roofing. They usually work under the main contractor.
  5. Civil or structural contractors. They build foundations, frames, drainage and the structure itself.

Not sure which one you need? We compare two of them in fit-out contractor vs general contractor. Most mid-size jobs in London, from £100,000 to £10M+, suit a design and build contractor. That's where we work.

Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.

Hainro Eybers, Google reviewSee all reviews on Google

What a commercial contractor does on real projects

Definitions only go so far. Here's what the job looked like on two of our projects, both with a fixed date and people using the building.

Open-plan office with rows of white desks, mesh chairs and a new ceiling grid with panel lights
Beaumont House, High Street Kensington: 750 sq m finished in three weeks.

An office floor, ready before the lease ran out

At Beaumont House in High Street Kensington, the client's old lease had five weeks to run. More than 150 staff had to move. Other contractors quoted at least 12 weeks for the 750 sq m floor.

We were on site two weeks after the first contact and finished in three. Other offices in the building kept working, so we organised noise, waste and deliveries around them. The floor was handed over with zero snags.

A live warehouse that never stopped

Bright warehouse floor with storage racking, a table tennis table and bean bags in a break area
Banbury warehouse: 2,500 sq m refitted in eight weeks.

In 2018, trading as Focus Internal Ltd (now Craftex Ltd), we added new rooms inside a busy Banbury warehouse. The warehouse had to keep working. In eight weeks we refitted the whole 2,500 sq m warehouse. The 148 sq m of new rooms included a changing room with lockers and a storage room with pallet racking.

Repeat work is the clearest sign a contractor did the first job well.

How a commercial contractor keeps a project on time and on budget

Most overruns start before the site opens. These are the habits that stop them.

  1. Survey first. Problems found before pricing cost far less than problems found during strip-out.
  2. Freeze the design early. Changes after work starts cost the most.
  3. Order long-lead items first. Bespoke joinery, glazing and equipment break more programmes than the trades do.
  4. Price every change before it is built. You keep control of the budget.
  5. Report weekly. Progress, risks and the decisions needed from you.

Material and labour prices still move during a project. We explain why in the rising cost of construction labour and materials. Our guide to delivering projects on time and on budget shows how we plan each stage.

What a good commercial contractor does that an average one doesn't

Good and average contractors use the same trades and materials. The difference is in how they run the job.

If you're comparing firms now, our guide to commercial construction companies in London lists the checks to make before you sign.

How Craftex works as your commercial contractor

Craftex started in 2016 as a carpentry and joinery company. Today we design and build commercial projects across London. Around 60% of our labour is in-house, so the joinery and finishes stay under our control.

We hold £10 million public liability and £10 million employers' liability cover. One team runs your project from survey and design to handover.

A contractor's job doesn't end with the build. Good design decisions also cut running costs, as we show in energy efficiency in data centre construction. And a layout that works starts with commercial space planning.

Have a project in mind? Book a site visit. We'll walk the building with you, flag the risks and give you a clear scope and price.

Seven traits of a good commercial contractor

  • Clear communication with you, the designers and the site team.
  • Sound knowledge of Building Regulations, fire safety and access.
  • Calm problem-solving when supplies slip or the building surprises everyone.
  • Careful control of the budget and the materials.
  • A firm grip on health and safety, every day.
  • Attention to detail, checked as the work goes, not just at the end.
  • Honest, regular updates, including bad news early.

Frequently asked questions

What does a commercial contractor do?

A commercial contractor delivers construction work for a business: new builds, conversions, refurbishments and fit-outs. They survey, price and programme the work, buy materials, manage the trades on site, control health and safety and quality, and hand over a finished, tested building.

What is the difference between a commercial contractor and a residential builder?

A commercial client keeps its own legal duties under CDM 2015, while a homeowner's duties normally pass to the contractor. Commercial work also tends to involve landlords, occupied buildings, fixed opening or lease dates and heavier fire, access and building services work.

How much does it cost to hire a commercial contractor in the UK?

It depends on the size, scope and location of the project. A contractor's price covers the work itself, site running costs (preliminaries) and overheads and profit. Ask for a written, itemised price after a site visit, so you can compare like with like.

What insurance should a commercial contractor carry?

Employers' liability insurance is a legal requirement for any employer, with cover of at least £5 million. Expect public liability cover and insurance for the works too, and professional indemnity if the contractor is designing. Ask for the certificates, not just a logo.

Do commercial contractors give warranties after completion?

Most contracts include a defects period after handover, when the contractor must return to fix defects. Manufacturers give separate warranties for equipment and materials. Check both in writing before you sign.

Can a commercial contractor work while my business stays open?

Yes. Works can be phased, with noisy and dusty work done at night or at weekends and the site kept separate from staff and customers. It costs more per day of work, but often far less than closing.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Need one contractor to take the whole job off your hands?

Our design and build team surveys the building, prices the work and runs it from strip-out to handover. Book a site visit.

Reply within 1 hour, Mon–Sat 8am–6pm. Urgent? WhatsApp us for a reply straight away, any day.

WhatsApp us