On-Time & On-Budget: Project Management in London Construction Projects
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
Construction projects finish on time and on budget when the scope is fixed before the price, the programme is built around long-lead items, and every change is priced before it is built.
- Survey the building and freeze the design before you sign a price.
- Order long-lead items before work starts on site.
- Hold a named contingency for what the survey can't see.
- Agree every change in writing, with its cost and time, before anyone builds it.
A renovation booked for three months runs for a year. A fit-out priced at one figure ends at another. In London every week late costs rent, lost trading or a missed lease date. Yet most delays and overspends start before anyone arrives on site.
This guide shows how construction projects stay on time and on budget. It covers why they slip, the five controls that stop it, and three of our own projects. We run project management for £5M+ schemes on these controls. Got a deadline and a budget to protect? Book a site visit and we'll test both on site.
Where projects lose time and money: the management causes
Overruns are normal, not rare. In KPMG's 2015 survey of 109 senior project owners, only 31% of projects came within 10% of budget. Only 25% came within 10% of their original deadline. The survey is global and dated, but builders still see the same pattern.
The management causes repeat on almost every job:
- Scope not fixed. Rooms, layouts and specifications change after the price is agreed.
- Optimistic time and cost. Approvals, lead times and site access were guessed, not checked.
- Loose communication. A missed instruction leads to work that has to be taken out again.
- Unmanaged risk. Hidden defects and supply delays arrive with no contingency to absorb them.
- Weak coordination. Trades arrive out of order and materials land before the area is ready.
Every one of these can be controlled. The five controls below are how we do it. For the cost side, from the first budget to the final account, see our guide to why construction projects go over budget.
Fix the scope before you fix the price
A price is only as firm as the scope behind it. If the drawings are vague, the price is a guess. The guess becomes variations later.
So survey first. Measure the building, open up where you can and check the services. Then freeze the layout before you ask for a firm price. Moving desks, rooms or the office layout once work has started is the most common "small change" that isn't small.
In a leased building, add the landlord's consent to the scope. Their surveyor reviews your drawings on their own timetable. Start that review as soon as the layout is agreed.
Build a programme around the critical path
A programme is not a list of dates. It shows which tasks depend on which. The chain with no spare time is the critical path. Any delay on it moves the finish date.
In London the critical path usually runs through things outside the site:
- Long-lead items, such as bespoke joinery, glazed partitions, plant and imported finishes
- Approvals from the landlord, building control and sometimes the council
- Deliveries, parking and access in a busy street
- Supply upgrades by the network operator
Order long-lead items before work starts. Keep a little float before the handover date. Our construction project planning guide shows how to build the programme step by step.
The law expects realistic time too. Under the CDM Regulations 2015, a client must make suitable arrangements for managing a project. That includes "the allocation of sufficient time and other resources".
At Slingsby Place in Covent Garden, the logistics were planned before demolition started. The works were led by Martin Hickey, now our Preconstruction Director, as Project Director. Crane lifts and road closures were agreed with the local authority in advance.
Price risk openly instead of hiding it
Every project has unknowns. Old buildings hide defects. Suppliers miss dates. The question is whether the budget admits it.
Good practice is to show risk as named lines:
- Contingency. A sum held for what the survey can't see, released only with the client's agreement.
- Provisional sums. Allowances for work that can't be fully defined yet, replaced by real prices once it can.
- Exclusions. What the price does not cover, written down so nobody assumes it does.
A budget with no contingency isn't cheaper. It just moves the surprise to the middle of the job.
Fixed price: fact or fiction?
Fixed-price contracts are real. The contractor commits to a defined scope for an agreed price. It then carries the risk of managing labour, procurement and sequencing within that price.
But a fixed price only holds for the scope it covers. Anything added later is a variation with its own cost and time. That's why fixed price works best after a thorough pre-construction stage. Our guide to design and build vs traditional procurement compares the routes.
We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.
Control every change in writing
Changes are not the enemy. Unpriced changes are. One extra socket is nothing. Twenty, plus a moved wall and a new finish, can cost a week.
Use one simple rule. No change is built until its cost and time effect are written down and agreed. Then it goes into the programme like any other task.
Report weekly and decide quickly
Projects drift when decisions wait. A weekly report should fit on one page and answer four questions:
- Where are we against the programme?
- What changed this week, and what did it cost?
- Which decisions do we need from the client, and by when?
- What risk is coming in the next two weeks?
Short reports read on a phone get answers the same day. Long reports get filed. Clear reporting removes most of the confusion that causes rework.
Three Craftex projects that finished on programme
These projects kept their dates because the hard decisions came before the build.
Beaumont House: a lease deadline met with time to spare
The client had five weeks before their lease expired. Other contractors quoted at least 12 weeks. We were on site two weeks after the first contact. We refurbished 750 sq m of offices in three weeks, with zero snags. Read the Beaumont House case study.
Banbury gym: on time and on budget in four weeks
In 2018, as Focus Internal Ltd (now Craftex Ltd), we designed and built a gym in Banbury in four weeks. The work finished on time and on budget. We then helped arrange delivery of the gym equipment and installed it, so the client could open.
Portsoken House: seven months around an occupied building
At Portsoken House in Aldgate, we designed and built 1,550 sq m of offices over two floors, with a full M&E package. The rest of the building was leased and working. Our team planned deliveries with the supply chain so materials arrived quickly without disrupting the tenants. The offices were finished on time.
Medusa: the design brought back to the budget
Medusa came to us at RIBA Stage 2, with concept designs only. Budget was the main challenge. As one design and build team, we priced the concept and offered cheaper ways to build the same look. The design was adapted to the client's budget and delivered across four floors in 17 weeks.
Choose a team that can keep its promises
Controls only work if someone owns them. Ask any contractor who will run your programme, who prices changes and how often you'll hear from them. Our guide on how to choose the right commercial contractor lists the questions to ask.
Craftex started in 2016 as a carpentry and joinery company. Around 60% of our labour is still in-house, so fewer packages depend on outside firms. Every project we have delivered has finished ahead of programme and on budget. We take on construction projects from £100,000.
See how we run projects on our construction project management services page. If you have a date to hit, book a site visit and we'll tell you honestly whether it's achievable.
Before you sign a construction price
- The building has been surveyed, not just viewed.
- The layout and specification are frozen.
- Long-lead items have order dates in the programme.
- Contingency, provisional sums and exclusions are written as separate lines.
- Changes need a written price and time effect before they're built.
- You know who sends the weekly report and what it contains.