For businesses planning a fit-out or a build
Building Fit-Out Contractor vs. General Contractor: Key Differences
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read
The short answer
Fit-out contractor vs general contractor comes down to scope. A fit-out contractor builds the inside of an existing building; a general (main) contractor runs the whole build, structure included.
- Interior works in a sound building: hire a fit-out contractor.
- New build, extension or structural change: hire a general contractor.
- A conversion needs both skills, so pick one firm that has done both.
- Either way, the firm in control of the work is your principal contractor.
Someone tells you to get a fit-out contractor. Someone else says you need a general contractor. Both sound right, and the quotes will look nothing alike. The difference matters, because hiring the wrong type of firm is how budgets and programmes break.
This guide sets out fit-out contractor vs general contractor in plain terms. It covers what each one does and the UK legal roles behind the names. It also shows how to tell which one your project needs.
We are fit out contractors in London. Shops, gyms, clinics and showrooms designed and built by one team, open on your date, with zero snags. Not sure which side of the line your building sits? Book a site visit and we'll tell you on site.
Fit-out contractor vs general contractor: the short version
The split is about where the work happens and who carries the risk. A fit-out contractor works inside a building that already stands. A general contractor takes charge of the whole construction, from the ground up.
| Point | Fit-out contractor | General contractor |
|---|---|---|
| Main job | Makes the inside of a building usable | Delivers the whole construction project |
| Typical work | Partitions, ceilings, floors, services, joinery, finishes | Structure, envelope, groundworks, then fit-out |
| When it starts | After the shell is built and weathertight | From the first day on site |
| Common projects | Offices, shops, restaurants, clinics, hotels | New builds, extensions, major structural works |
| Design role | Often designs the interior too (design and build) | Usually builds to someone else's design |
| Main risks | Services, landlord consents, live buildings | Ground, structure, weather, long programmes |
The two overlap more than the names suggest. Many general contractors fit out their own buildings. Many fit-out contractors handle structural openings and new floors inside an existing frame.
What a building fit-out contractor does
A fit-out contractor turns an empty or tired space into one people can use. The building is already there. The job is everything inside it.
A typical commercial fit-out includes:
- Strip-out of old partitions, ceilings and finishes
- New internal walls and glazed partitions
- Suspended ceilings, raised floors and floor finishes
- Electrics, lighting, data, heating, cooling and ventilation
- Kitchens, WCs, joinery and decoration
On an office, a fit-out often starts from the landlord's Cat A floor. The tenant's Cat B fit-out then adds the layout, meeting rooms and finishes. Our guide to Cat A, Cat A+ and Cat B explains who usually pays for what.
If you are comparing office fit out companies for that Cat B work, ask each one which trades it employs.
Interior-only works are usually not "development" under planning law. So most fit-outs need no planning permission. They still need Building Regulations approval where it applies, and the landlord's consent if you lease.
What a general contractor does
A general contractor runs the whole construction project. It hires and manages the trades, orders materials, keeps the site safe and keeps the programme moving. It answers to the client for the finished building.
In the UK, "general contractor" and "main contractor" usually mean the same firm. It is the one that signs the main contract with the client. Our full guide explains what a commercial contractor does day to day.
You need general contractor skills when the work touches:
- Foundations, basements or groundworks
- The frame, floors or load-bearing walls
- The roof, façade or windows
- Extensions, new storeys or new buildings
On larger developments, the main contractor often brings in a fit-out specialist once the shell is complete. That handover point is where many disputes start, so it needs a clear scope.
We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.
Step 1 of 1
Principal contractor: the legal role behind both names
"Fit-out contractor" and "general contractor" are trade terms. The law cares about a different word: principal contractor.
Under CDM 2015, a client must appoint a principal contractor on any project with more than one contractor. Its job is to plan, manage and coordinate the construction phase. Since October 2023, the Building Regulations add a matching duty. The client must appoint the principal contractor in writing, before the construction phase begins.
So on a fit-out, your fit-out contractor is usually your principal contractor. On a new build, it is the general contractor. What matters is that the firm can prove it is competent for the role. The client must take reasonable steps to check that before appointing.
Two more checks apply to both types of firm. Employers' liability insurance is a legal requirement, with at least £5 million of cover.
Some projects must also be notified to HSE. That applies if work runs over 30 working days with more than 20 workers at once. It also applies above 500 person days. Our guide to CDM 2015 client duties covers your side of the paperwork.
Which contractor your project needs
Ask one question first: does the work change the structure or the outside of the building? If not, you probably need a fit-out contractor. If yes, you need general contractor skills.
| Project | Usually best served by |
|---|---|
| New office layout on a Cat A floor | Fit-out contractor |
| Restaurant, shop or clinic in an existing unit | Fit-out contractor |
| Refurbishment of an occupied office | Fit-out contractor with live-building experience |
| New storey, extension or basement | General contractor |
| Removing load-bearing walls or new floor openings | General contractor, or a fit-out contractor with structural experience |
| Converting a warehouse or office to a new use | One firm that does both, under one contract |
The last row is where projects go wrong. A conversion is part structure and part fit-out. Split it between two firms and the gap between them becomes your problem.
The choice also depends on how you buy the work. With traditional procurement, you hire designers first and a contractor builds their drawings. With design and build, one firm designs and builds. Our guide to design and build vs traditional procurement compares the two.
Three Craftex projects show where the line falls
These three projects sit at different points between fit-out and general contracting.
Beaumont House: a pure fit-out in three weeks
Beaumont House in High Street Kensington was a £350K office refurbishment of 750 sq m. The client had five weeks before their lease ended. Other contractors had quoted at least 12 weeks.
We were on site two weeks after first contact. We finished in three weeks with zero snags.
Walls came down for an open-plan floor. Frosted glass rooms went in for private meetings. Lighting and wiring were replaced, and data ran under the floor to every desk. The client then hired us for a second refurbishment in the same building, valued at £1.3 million.
Portsoken House: a fit-out that needed both skills
Portsoken House in Aldgate was a £2.2M office fit-out of 1,550 sq m on two floors. It took seven months. The work included structural changes, levelled concrete floors and a new entrance. It also needed a full mechanical and electrical package, new ceilings, kitchens and WCs.
That is general contractor work and fit-out work in one job. The rest of the building was already let, so noisy work ran at nights and weekends. Our in-house team designed it, and design and build sat under one roof.
Drake's: a building inside a building
For Drake's, we turned a 500 sq m railway arch into offices, a photo studio, manufacturing and dispatch in eight weeks. Nothing could be drilled into the arch. So we built a fully self-supported interior: freestanding partitions and independent service frames.
It looks like a fit-out. It was engineered like a small building.
Questions to ask before you hire either type
The right contractor is the one whose experience matches your building, not the one with the right label. These questions sort them quickly.
- Have you delivered projects of this size and type in the last three years?
- Which works will you do with your own people, and which will you subcontract?
- Will you act as principal contractor, and who is your named site manager?
- Can you send current employers' liability and public liability certificates?
- Who handles building control, the landlord's licence and any structural design?
- What is excluded from your price, and what are the provisional sums?
- How will you work around neighbours or occupied floors?
Our tips for choosing the right commercial contractor cover the tender itself. For fit-out firms in particular, read what fit-out companies do and how to choose one. For offices, see choosing an office fit-out company in London. Either way, book a site visit before you compare prices.
One team for fit-out and structure
Most London projects don't sit neatly on one side of the line. A tired office needs a new staircase. A shop needs a new opening in a party wall. A warehouse becomes an office.
Craftex started in 2016 as a carpentry and joinery company. We now deliver commercial fit-out and refurbishment and structural works in London. Around 60% of our labour is in-house. We take on construction projects from £100,000.
With turnkey contracting, design, structure and fit-out sit under one contract and one programme. A good plan still decides the outcome. Our construction project planning guide shows how to set one up before work starts.