How Commercial Refurbishment Works?
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 4 min read
The short answer
Commercial refurbishment works in six stages: brief and survey, design and costing, approvals, strip-out and build, services and finishes, then testing and handover. Most problems start in the first two stages, not on site.
- Survey the building, including asbestos, before the design is fixed.
- Price the design before you order anything, so you can still make changes.
- Settle the landlord's licence and building control before the strip-out.
- Plan phasing early if staff or tenants stay in the building.
A commercial refurbishment can look like one big job. In practice it is six smaller ones, done in a fixed order. Skip a step or rush it, and the problem turns up later, usually on site and usually at a cost.
This guide explains how commercial refurbishment works, stage by stage. It covers what happens, who decides what, and where the time and money really go. It uses offices we have refurbished in London as part of our commercial fit out and refurbishment work. Planning one? Book a site visit and we'll walk the space with you.
How commercial refurbishment works, in six stages
| Stage | What happens | What you get |
|---|---|---|
| 1. Brief and survey | Goals, budget, dates; survey of the building | A clear brief and known risks |
| 2. Design and costing | Layout, finishes, services; priced in detail | A design and a price you can sign off |
| 3. Approvals | Landlord's licence, building control, CDM | Consent to start |
| 4. Strip-out and build | Old fit-out removed; walls, ceilings, structure | The new layout in place |
| 5. Services and finishes | Mechanical, electrical, data, floors, decoration | A working, finished space |
| 6. Testing and handover | Commissioning, snagging, certificates | Keys, manuals and warranties |
The rest of this guide takes each stage in turn.
Stage 1: the brief and the survey set the risks
It starts with a conversation about what the space must do. More meeting rooms, better light, room for hybrid working, a stronger brand? Our guide to office workspace design covers the factors to brief on.
Then comes the survey. The team checks the structure, partitions, ceiling height, ventilation, fire routes, floors and services.
Stage 2: design and price before you order anything
The design turns the brief into drawings: layout, finishes, lighting and services. It is then priced in detail, so you can trade items off on paper. Changing a drawing is cheap. Changing a wall that is already built is not.
Prices also move with the market. Our article on the cost of construction materials explains why a fixed design and an early order protect the budget.
The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!
Stage 3: approvals before the strip-out
Three sets of approvals usually apply to a commercial refurbishment.
- The landlord: most leases need written consent for alterations. Allow time for the landlord's surveyor to review drawings.
- Building control: new partitions, services and structural changes are building work under the Building Regulations. Works that only affect the inside are not development, so planning is rarely needed.
- CDM 2015: with more than one contractor, you appoint a principal designer and a principal contractor. A construction phase plan must exist before work starts.
Larger projects must be notified to HSE. That applies when work lasts more than 30 working days with more than 20 workers at once, or exceeds 500 person days.
Stage 4: strip-out and the build
The old carpets, partitions, ceilings and fittings come out first. The space goes back to a clean shell. Then the new layout goes in: partitions, ceilings and any structural changes.
This is where the survey pays off. Hidden defects found now cost time. Defects found at survey were already in the price.
Stage 5: services, then finishes
Modern offices depend on their services. In this stage, engineers install or move:
- heating, cooling and ventilation;
- electrical wiring and lighting;
- data cabling and wireless coverage;
- plumbing for kitchens and WCs;
- fire alarm and emergency lighting.
Then the finishes follow: floors, decoration, doors, joinery and the kitchen. Furniture and IT come last. Landlords should also check the energy rating here. Let commercial property needs an EPC rating of E or better.
Stage 6: testing, snagging and handover
Every system is tested and commissioned before handover. The team walks the space and fixes the small defects, called snags. You then receive the certificates, manuals and warranties.
A good handover has no snag list left. Our aim is a zero-snag handover on every project.
Beaumont House: 750 sq m refurbished in three weeks
At Beaumont House in Kensington, the client had five weeks before their lease ended. They had more than 150 staff to move. Other contractors quoted at least 12 weeks.
We removed walls to open up the floor and built frosted glass meeting rooms. Lighting and wiring were replaced, and data cabling runs under the floor to every desk. CCTV and access control went in. At the end, we moved the furniture and equipment into the new office.
Refurbishing an occupied building takes a different plan
Many businesses can't move out. Then the works are phased by zone, and noisy jobs move to nights and weekends.
At Portsoken House in Aldgate, the other floors were already let. We refurbished 1,550 sq m of offices over seven months around the tenants. The reception was rebuilt overnight in 12 weeks, so tenants were never interrupted.
Phasing costs more per day of work. But it can cost far less than closing the business.
Choose a team that runs all six stages
Most refurbishment problems happen in the gaps: between designer and builder, or between builder and services engineer. A design and build team closes those gaps. One team owns the brief, the price and the programme.
When you compare choosing fit-out companies, ask who does the work. About 60% of our labour is in-house. You can also compare us with other commercial construction companies in London.
Our office refurbishment team works across London, and we take on construction projects from £100,000. Ready to start? Book a site visit and we'll take you through the six stages for your building.