For businesses moving office
Office Relocation & Fit-Out Checklist for UK Businesses
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 10 min read
The short answer
An office relocation checklist works backwards from your lease end: team and brief first, then the property, then the fit-out, then IT and the move.
- 12 to 18 months out: project team, brief, budget and lease dates.
- 9 to 12 months out: find the building and survey it before you sign.
- 3 to 9 months out: design, landlord consent, fit-out contract, orders and IT.
- Last 3 months: snagging, the old office, testing and the move itself.
An office relocation checklist works backwards from the date your lease ends. The deadline that matters is not the removal van. It's that date minus the time the new office needs to be ready.
This checklist covers the team, the property, the office relocation fit-out, the legal checks, IT and the move itself, for London and UK businesses. It's written from the contractor's side, because the fit-out is where most moves slip. Got a floor plan and a move date? Get a fixed figure and we will price the new floor.
Why an office relocation checklist starts early
Rushed moves cost money. Decisions get made without prices, the fit-out runs into the lease end and staff arrive to an office that isn't working.
Starting early lets you:
- compare buildings and survey them before you sign;
- get the landlord's consent in time;
- plan the IT so systems work on day one;
- meet the rules on fire safety, workspace and access.
Our guide to construction project planning explains the same method for any building project.
Office relocation project plan at a glance
Most moves run in five phases. Each one has an owner and something it must produce before the next one starts. The numbered checklist below gives the steps inside each phase.
| Phase | When | Owner | Done when |
|---|---|---|---|
| Team, brief and budget | 12 to 18 months before | Project lead and finance | Brief, budget and lease dates signed off |
| Find and check the building | 9 to 12 months before | Project lead and agent | Surveys done, heads of terms agreed |
| Design and fit-out partner | 6 to 9 months before | Project lead and contractor | Layout fixed, fixed figure agreed |
| Consents, contracts and orders | 3 to 6 months before | Contractor and solicitor | Landlord consent, contract and orders placed |
| Handover and the move | Last 3 months | Project lead, IT and removals | Snagging closed, staff moved, systems tested |
Review the plan every week once the fit-out starts. When one phase slips, the move date only holds if a later phase gets shorter.
12 to 18 months before: team, brief and budget
1. Form a relocation team. Appoint one project lead with authority to decide. Include IT, HR, finance and facilities.
2. Write the brief. Audit what works in your current office and what doesn't. Plan for your headcount over the next three to five years. Decide how much open-plan, meeting and quiet space you need. Our guide to office layout types helps here.
Could the current office work after a refit? Compare it with office refurbishment cost before you commit to a move.
3. Set the budget. Include rent, deposits and fees on the new space. Add what you owe on the old one, the fit-out, furniture, IT and the move. Our office fit-out cost guide covers the new floor. For every other line of the move, see what an office move costs.
4. Check your lease dates. Note the lease end or break date and its notice. If the 1954 Act protects your tenancy, notice to leave at a fixed term's end is due at least three months before. Some leases exclude that protection. A break clause has its own terms. Ask your solicitor which applies.
5. Ask what the new landlord will offer. Incentives come as a rent-free period, a capital contribution or landlord's works. Agree them in the heads of terms. Our guide to a landlord fit-out contribution explains how each works.
Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody
9 to 12 months before: find and check the building
6. Shortlist buildings. Look at transport links, commute times, access for visitors and local amenities. Check business rates too.
7. Survey before you sign. A building survey shows defects. In older buildings, HSE says you should find out whether there is asbestos before any work starts. That's especially true where the building was built or refurbished before 2000.
8. Check the fit-out you're taking on. Is the space shell, Cat A or a previous tenant's Cat B? Our guide to Cat A, Cat A+ and Cat B fit-out explains the difference.
9. Check the energy rating. Privately rented non-domestic property must meet EPC band E. Since April 2023 that applies to existing tenancies too.
10. Size the space. HSE's code of practice sets at least 11 cubic metres per person in a workroom. Welfare is sized by headcount: two toilets for 6 to 25 people, three for 26 to 50.
London checks
London buildings add their own questions. Ask them before you sign the lease.
- Does the lease need the landlord's licence for alterations? Our guide to a licence for alterations shows what to expect.
- Does the building limit noisy work, deliveries or loading-bay use to set hours? Ask the building manager.
- Will the site need a delivery and waste plan? Our guide to a construction logistics plan explains when.
- Is the office in a listed building? Works that would affect its character need listed building consent. Check the listing first.
6 to 9 months before: design and fit-out partner
11. Choose your fit-out contractor. Ask for similar past projects, proof of insurance and an itemised price after a site visit. Ask how they would handle your programme. Our guide to choosing a fit-out company lists the questions. Our commercial fit-out team works to the same checks.
12. Design the workspace. Balance collaboration, focus and wellbeing. Good office design and space planning starts from how your teams actually work. Read why commercial space planning matters before you fix the layout.
13. Pick the fit-out type. Our guide to the different types of office fit-out covers Cat A, Cat B and refurbishment.
14. Plan for access. Under the Equality Act 2010, employers must make reasonable adjustments where a physical feature puts a disabled person at a substantial disadvantage. Design it in now, not after the move.
15. Get a range for the new floor. Run our office fit-out cost calculator with your headcount. Then ask for a fixed figure after a survey. A fixed figure is a price for a defined scope.
3 to 6 months before: consents, contracts and orders
16. Get the landlord's consent. Your lease says whether alterations need the landlord's written consent. Where a lease bars improvements without consent, the law says consent can't be unreasonably withheld. The landlord can still ask for its costs and a sum for any damage. Their surveyor reviews your drawings on their own timetable, so start early.
17. Check building control. Where the fit-out is building work, the Building Regulations need a building notice or a full plans application. In a building the Fire Safety Order covers, it must be full plans. Ask your contractor who applies and when.
18. Sign a clear contract. It should include drawings, a specification and a programme with milestones. Tie payments to progress. Set out insurance, defects and how changes are priced.
19. Order long-lead items. Bespoke furniture, joinery and IT equipment can take longer than the build.
20. Monitor progress. Hold weekly meetings to check programme, quality and safety. Keep a log of issues so they're fixed quickly.
21. Keep people informed. Tell staff, clients and suppliers the date and what will change.
IT and telecoms move
The IT move is a project inside the project. Treat it that way from the start.
- Ask providers for connectivity lead times at the start and order early. Don't leave it until handover.
- Agree where the comms room goes, with the power and cooling it needs.
- Put the data cabling in the fit-out scope, so it's installed before the finishes.
- Test the network and phones with a small group before move week.
1 to 3 months before: handover, testing and the old office
22. Snag the work. Walk the space with your contractor and list anything unfinished. Get it fixed before you sign off.
23. Collect the documents. Ask for operation and maintenance manuals, warranties and as-built drawings.
24. Plan the fire safety. The responsible person must carry out and regularly review a fire risk assessment, and keep a written record. Do it for the new office before people move in.
25. Plan the move. Give the removal team floor plans showing where every team and workstation goes.
26. Plan the old office. Your lease may set the condition you must return it in. The Dilapidations Protocol expects the landlord's schedule within about 56 days of the lease ending, and your response about 56 days after their demand. It's expected conduct, not law. Our guide to what a schedule of dilapidations costs shows how to price it.
27. Clear out responsibly. Archive records in line with your retention policy. Old IT is waste with a duty of care: pass it only to an authorised person, with a written description of the waste.
Office move checklist: the last eight weeks
The final two months are about logistics. Run them as a weekly list, so nothing lands in move week by surprise.
- Eight weeks out. Book the removal company and agree the date, the lift and loading-bay times at both buildings.
- Six weeks out. Confirm the new internet lines and phone numbers are live or booked. Order crates and labels.
- Four weeks out. Tell clients and suppliers the new address. Print new stationery and order signage.
- Three weeks out. Issue a seating plan and a floor plan to every team. Name one move contact per team.
- Two weeks out. Clear desks and archive files. Book the disposal of old furniture and IT with an authorised carrier.
- One week out. Back up the data, label every crate by team and destination, and brief the removal crew on site.
Allow one spare week in this list. Late deliveries and lift bookings are the usual reasons a move week slips.
Move week and the first weeks after
28. The day before. Back up all company data. Pack and label every box by team and destination.
29. Moving day. Have your project lead at both sites. Move IT last from the old office, but set it up first in the new one.
30. Test everything. Networks, phones, heating and cooling, lighting, fire alarms and meeting-room AV.
31. Induct staff and collect feedback. Show people the new spaces and systems. After a few weeks, ask what works and adjust desks, lighting or acoustics.
Who to tell when you move office
A new address has to reach the right registers and the right people. Some of it is a legal duty with a deadline.
- Companies House. If your registered office is moving, tell Companies House. The new address must be in the same part of the UK the company was registered in. It only changes once Companies House has registered it.
- HMRC. Tell HMRC about a new trading address. If you are VAT registered, report a change of main business address within 30 days, or you may face a penalty.
- Your bank and insurer. The insurer needs the new premises before you move in, not after.
- Clients and suppliers. Update invoices, email signatures and delivery addresses.
- Your website and listings. Change the address on the website, Google Business Profile and directories on moving day.
How Beaumont House moved 150 staff in five weeks
At Beaumont House in High Street Kensington, the client had five weeks before their lease expired. They had more than 150 staff to relocate. Other contractors quoted at least 12 weeks.
We were on site two weeks after the first conversation. We turned 750 m² of rundown office into an open-plan workplace in three weeks, with zero snags. The work included new lighting and wiring, CCTV, access control and under-floor data cabling to every desk. We also moved the furniture and equipment, so the relocation caused no disruption.
One team for the fit-out and the move
A relocation touches property, design, construction, IT and people. Every gap between them is where a week disappears. With design and construction under one contract, one team owns the programme from survey to handover. See our commercial fit-out and refurbishment service and how commercial refurbishment works.
Moving into an older or repurposed building? Read our lessons from commercial property redevelopment. We take on construction projects from £100,000. Got a move date? Get a fixed figure for the new floor. We reply within one hour, Monday to Saturday, 8am to 6pm, and tell you if the fit-out can be ready in time.
Office relocation checklist on one page
- Appoint one project lead and write the brief.
- Note the lease end or break date, and the notice it needs.
- Set the budget, then see what an office move costs.
- Survey the new building before you sign, including asbestos for older buildings.
- Check EPC band E, space per person and welfare numbers.
- Get the landlord's consent and agree incentives in the heads of terms.
- Check building control, and listed building consent if it applies.
- Choose the fit-out contractor and agree a fixed price and programme.
- Order long-lead furniture, joinery and IT early.
- Plan connectivity, the comms room and data cabling.
- Snag, collect the manuals and complete the fire risk assessment.
- Plan the old office, then move, test and collect feedback.