Restaurant Kitchen Fit-Out in London: Extraction, Gas, Consents and Programme

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read

Back-of-house commercial kitchen with stainless steel worktops, refrigeration, racking and an extraction canopy

The short answer

A restaurant kitchen fit-out is the cooking line, extraction, gas, drainage, power and hygienic finishes, designed as one system. In London the extract route and the consents behind it usually set the opening date.

  1. Confirm the extract route to roof level before you sign the lease.
  2. Check the gas and power supply against your equipment list at the survey.
  3. Plan grease management and drainage for the final layout.
  4. Register the food business with the council at least 28 days before trading.

The kitchen decides whether a restaurant opens on time. Guests see the dining room. The environmental health officer, building control and your landlord look at the extract, the gas, the drains and the paperwork.

In London most restaurants open in existing buildings, with neighbours above and beside them. That makes the kitchen the critical path. Got a unit in mind? Book a site visit and we will check the extract route and services with you.

This guide explains what a restaurant kitchen fit-out includes, which consents to plan for, how long it takes and what drives the cost. It also covers what a hotel kitchen contractor should deliver. It is written from the contractor's side of a commercial kitchen and restaurant fit out.

What a restaurant kitchen fit-out includes

A commercial kitchen is a set of systems designed together. Add a charcoal grill and the extraction, fire protection, gas and power all change with it.

Commercial kitchen wash-up area with stainless steel dishwashing equipment, canopy and shelving
  1. Layout and equipment plan. The cooking line, pass, prep, wash-up and storage, plus the routes for food, waste and staff. Agree it with your chef before anything is ordered. Our Aunties design in Seven Sisters fitted service, work and guest zones into 83.35 m².
  2. Extraction and ventilation. Canopies, ductwork, fans, filters and odour control. Make-up air replaces what the extract removes.
  3. Gas. Supply, meter size, pipework and the interlock that stops the gas if the fans are off.
  4. Drainage. Floor gullies, grease management and connections sized for the equipment.
  5. Power and lighting. Dedicated circuits, emergency lighting and light levels fit for food preparation.
  6. Hygienic finishes. Washable walls and ceilings, slip-resistant floors with coved edges, stainless steel where needed.
  7. Fire safety. Fire separation of the kitchen and duct route, suppression over the cooking line where specified, detection and alarms.

Extraction and odour control set the programme

Most London restaurant units sit under offices or flats. So the extract route comes first. It affects planning, the landlord's consent and the neighbours.

Settle these points at the survey:

  1. Where the duct can run. Ideally to high level above the roof. If it can't, the system needs more filtration and odour control, and the council will want it justified.
  2. What you cook. Odour and grease loads differ between a café, a pizza oven and a grill. Councils often assess proposals against the EMAQ update of the government's kitchen exhaust guidance.
  3. Noise. Fans and roof plant cause many complaints. An acoustic report often goes with the planning application.
  4. Cleaning access. Kitchen ventilation is usually specified to BESA DW/172. The ductwork needs access panels so it can be cleaned to TR19 Grease.

External ductwork or roof plant usually needs planning permission. That holds even where the restaurant use is already allowed. In a conservation area or on a listed building, allow more time.

Gas, power and drainage for a commercial kitchen

Gas

All gas work must be done by Gas Safe registered engineers under the Gas Safety (Installation and Use) Regulations 1998. Commercial catering needs an interlock between the gas supply and the extraction. Cooking can't start with the fans off.

Check early whether the meter and supply can carry your equipment list. A supply upgrade from the gas network can take weeks.

Power

Moving to electric or induction cooking removes the gas question. But it can push the unit past its electrical supply. We check the incoming supply against the equipment schedule at the survey, before the design is fixed.

Drainage and grease

Fats, oils and grease poured into drains block sewers. Water companies can act against food businesses that cause blockages. Plan a grease separator or dosing system to suit the unit and the menu. Position floor gullies and equipment drains for the final layout.

Consents for a London restaurant kitchen

A restaurant opening needs several separate approvals. They run in parallel, but each has its own lead time.

The approvals behind a restaurant kitchen
ApprovalWhen it appliesWho decides
Licence for alterationsMost works in a leased unit, especially extraction, plant and openingsYour landlord
Planning permissionExternal ductwork, plant, shopfront; change of use to a pub or barThe borough council
Building regulationsFire safety, ventilation, drainage, access, toiletsBuilding control
Food business registrationAt least 28 days before you start tradingThe local authority
Premises licenceSelling alcohol, or hot food or drink from 11pm to 5amThe licensing authority
Fire risk assessmentBefore you openThe responsible person

Restaurants and cafés sit in Use Class E. A move from shop or office use within Class E generally doesn't need planning permission for the use. Pubs and bars are outside Class E and normally do.

Start the licence for alterations as soon as you have a layout. At lease end the same extraction and plant often have to come out, under restaurant dilapidations. As design and build contractor, we coordinate building control, the fire strategy and the landlord's consent. We also give your planning and licensing advisers the drawings they need.

Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

Pawel Kamionka, Google reviewSee all reviews on Google

Hotel and commercial kitchen contractors

A hotel or commercial kitchen contractor designs and installs the kitchen as one package. That means canopy and extract, the gas interlock, drainage and grease management, fire protection and the hygiene details the council will look at. In a hotel the same kitchen often serves breakfast, banqueting and room service while guests stay in the building.

What a hotel or commercial kitchen contractor should deliver
PackageWhat it coversRule or standard behind it
Canopy and extractCanopy with grease filters, ductwork with cleaning access, fans, make-up air, odour controlHSE CAIS23; BESA DW/172 and TR19 Grease
Gas interlockGas to the cooking line shuts off if the extract fails, with no manual bypassBS 6173, as cited by HSE
Drainage and greaseGullies, grease separator or dosing, drains sized for the equipmentWater Industry Act 1991, s.111
Fire protectionFire-separated duct route; suppression over the cooking line where the fire strategy or insurer asks for itFire risk assessment
Environmental HealthHygienic layout and finishes; food business registration timed for openingFood Standards Agency

HSE guidance says the gas supply to the appliances should shut off if the mechanical ventilation fails. Manual bypasses to the interlock are not permitted. HSE points installers to BS 6173 for new and second-hand gas catering equipment.

BS 6173 is not retrospective, so an older hotel kitchen may have no interlock at all. HSE then expects the risk to be assessed and controlled. A refurbishment is the natural moment to fit one.

Grease is a legal issue as well as a maintenance one. Under section 111 of the Water Industry Act 1991, putting anything into a public sewer that is likely to block its flow is an offence. Fats, oils and grease from a busy kitchen do exactly that.

The Food Standards Agency asks you to register with the local authority at least 28 days before trading. That applies to a new kitchen and to a business you take over. Agree the layout and finishes with your food safety adviser before the build, not after it.

How to choose a hotel kitchen contractor

  1. Ask who designs the extract. The route, odour control and make-up air should be designed by the contractor, not left to the equipment supplier.
  2. Check gas competence. Gas work must be done by Gas Safe registered engineers. Ask how the interlock will be tested and certified.
  3. Ask for the handover pack. Commissioning records for gas, extract, interlock and any suppression system, plus duct cleaning access drawings.
  4. Ask how they phase an occupied hotel. Guests, kitchen staff, deliveries and waste need separate routes and agreed working hours.
  5. Keep the building work in the same contract. Ceilings, fire separation and drainage sit between trades. One contractor closes those gaps.

We deliver kitchens as part of a restaurant and hospitality fit-out. Design with your chef, extract, gas, drainage, finishes and approvals sit under one contract.

How long a restaurant kitchen fit-out takes

The build is rarely the longest part. Design, approvals and ordering usually take 4 to 10 weeks first.

Typical stages of a restaurant kitchen fit-out
StageWhat happensTypical time
Survey and briefMeasured survey, gas, power, drainage and extract route checked1 to 2 weeks
Design and costingKitchen and dining layout, equipment schedule, extraction design, price2 to 6 weeks
Approvals and orderingLandlord, building control, planning if needed, long-lead items2 to 6 weeks
BuildStrip-out, services, extraction, kitchen, joinery, finishes, testing4 to 12 weeks for most London units

Delays usually come from three places. An extract route the landlord or planners won't accept. A gas or power supply that needs upgrading. Or equipment ordered before the layout was fixed.

Settle the layout questions before work starts and the build itself is rarely what holds up the opening.

What drives the cost of a restaurant kitchen fit-out

A kitchen has no single price per square metre. Two units of the same size can need very different work. These are the main cost drivers.

  1. The extract route. A short run to the roof is a different budget from a long internal route with odour control.
  2. The shell. A former restaurant with usable services costs far less than a bare shell or a former shop.
  3. Supply upgrades. Gas, power and water may all need more capacity.
  4. The menu. Grills, solid fuel and wok cooking need more extraction and fire protection than a café.
  5. Working hours. Out-of-hours work to protect neighbours or a trading business costs more.
  6. Reused equipment. It saves money, but it must be checked and certified.

For 2026 bands per m² for a whole restaurant, bar or pub, see our guide to restaurant fit-out cost. We take on construction projects from £100,000. After a site survey, you get a price against a clear scope before you commit. The wider picture, from concept to opening, is in our hospitality fit-out guide.

Fitting out a kitchen in a trading hotel, pub or restaurant

Many London operators can't close for a full refit. Works can be phased so the bar, part of the dining room or a hotel's breakfast service keeps running. Noisy and dusty tasks move out of hours, and a temporary kitchen can cover the gap.

Agree the phasing plan before the build: which areas stay open, how guests and staff are kept apart, and when deliveries and waste can move.

The same approach works in other occupied buildings. Our commercial fit-out and refurbishment team phases work in shops and offices that must stay open.

Restaurant kitchens in central London

In Westminster, the West End, Covent Garden and Soho, restaurant units are often in older or listed buildings. Many sit in conservation areas with residential neighbours above. Extract routes, roof access and delivery times need more planning there. See how we approach building and fit-out work in Westminster.

We check all of these at a survey, before you commit to a design or a budget. If you have a unit in mind, book a site visit before you sign the lease.

Before you sign a lease or order equipment

  • Is there an extract route to roof level, and will the landlord allow a new one?
  • Does the use class allow a restaurant, and are there planning conditions on hours or extraction?
  • Do the gas, power and water supplies match your equipment list?
  • Where will grease management and waste storage go?
  • Will residential neighbours' noise and odour concerns shape the design?
  • Have you allowed 28 days for food business registration, plus time for a premises licence?

Frequently asked questions

Do I need planning permission for a restaurant kitchen extraction system?

Often yes. If the ductwork or plant is visible outside or changes the building's appearance, it usually needs planning permission, and councils normally ask for details of odour control and noise. Internal works alone usually do not.

How long does a restaurant kitchen fit-out take in London?

Most London restaurant builds take 4 to 12 weeks on site, after 4 to 10 weeks of design, approvals and ordering. The extract route, supply upgrades and the landlord's consent have the biggest effect on the overall programme.

What does a commercial kitchen fit-out include?

The layout and equipment plan, extraction and make-up air, gas with a safety interlock, drainage and grease management, dedicated power and lighting, hygienic wall, floor and ceiling finishes, and fire safety over the cooking line.

Can you design the kitchen with our chef?

Yes. We plan the kitchen layout with you and your chef, then install the gas, extraction, ventilation, drainage and hygienic finishes as part of the same contract.

Can a kitchen be refitted while the restaurant or pub keeps trading?

Often, with phasing. Noisy work is done out of hours, trading areas are kept safely separate and a temporary kitchen is set up where needed. A full kitchen rebuild is usually faster with the kitchen closed.

What does a hotel kitchen contractor do?

A hotel or commercial kitchen contractor designs and installs the canopy and extract, the gas supply with its ventilation interlock, drainage and grease management, fire protection over the cooking line and hygienic finishes. A good one also coordinates building control and the paperwork the council's food team will ask for, and phases the work around guests.

How much does a restaurant kitchen fit-out cost?

It depends on the extract route, the condition of the shell, supply upgrades and the menu. Our restaurant fit-out cost guide gives 2026 bands per m² for the whole venue. We take on projects from £100,000 and price the kitchen after a site survey, before you commit.