Schedule of Dilapidations: What It Lists, the Timetable and What the Works Cost

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read

Portland stone office building in the City of London with bronze-framed windows reflecting the buildings opposite

The short answer

A schedule of dilapidations is the landlord's list of the repairs, redecoration and reinstatement it says you owe when the lease ends, with the works and usually a price for each.

  1. It lists breaches, the works to put them right and the landlord's costings, and the Protocol expects it generally within 56 days after the lease ends.
  2. The prices are a surveyor's estimates: in a 2013 court case the first schedule showed about £2.45 million and the tenant's response about £87,000.
  3. A contractor's price built from a survey of the floor gives you a real figure to set against the schedule.

A schedule of dilapidations lists the repairs, redecoration and reinstatement a landlord says you owe when the lease ends. Each line gives the works needed and usually a price, which is a surveyor's estimate, not a contractor's quote.

The Dilapidations Protocol expects the schedule generally within 56 days after the lease ends. This guide explains each column, the timetable and what the works cost on published 2026 rates. It also shows when doing the works beats paying.

We are a dilapidations works contractor in London, so we read the schedule from the builder's side. Holding one now? Send us the schedule for a free costing.

What a schedule of dilapidations lists

The Protocol gives the landlord a standard form, in Annex B or Annex C. Both have the same five columns.

The five columns of the Protocol's schedule of dilapidations
ColumnWhat it holds
Item no.A number for each breach, so you can answer line by line
Clause no.The lease clause the landlord says you have breached
Breach complained ofWhat the landlord says is wrong
Remedial works requiredThe works to put it right
Landlord's costingsThe price, where the landlord gives one

Breaches should be listed in separate categories, such as repair, reinstatement and redecoration. Where the landlord has served notices requiring reinstatement, the schedule should identify them.

Here is how one line reads. Item 14 cites the decoration clause. The breach is walls not redecorated as the lease requires. The works are to prepare and repaint walls and ceilings. The costing is the surveyor's figure for that work.

The schedule is endorsed by the landlord or, if a surveyor prepared it, by the surveyor. The endorsement confirms the works are reasonably required and the costings reasonable. It also confirms the landlord's intentions for the property were taken into account. That last point can remove whole items, as the cost section below explains.

Interim and terminal schedules

A terminal schedule is sent at or after the end of the lease. It is the one most tenants meet. An interim schedule is sent before the lease ends.

If the landlord sent an interim schedule, the Protocol says it should confirm at the end that nothing has changed, or send a further schedule. So an interim schedule is a warning with time to act.

In Sunlife Europe Properties v Tiger Aspect, a terminal claim decided in 2013, the landlord had an interim schedule prepared in October 2006. The tenant left in November 2008. Two years is long enough to price works and plan them.

Our dilapidations works contractor team prices a schedule of either kind. It is not legal or valuation advice: your solicitor and building surveyor handle the claim itself.

Step 1 of 1

The timetable after you receive it

The Protocol sets the conduct a court would normally expect before anyone issues proceedings. It is not a statutory deadline.

  1. Schedule. Sent within a reasonable time, which will generally be within 56 days after the lease ends.
  2. Quantified Demand. The sum claimed, sent in the same timescale, with a date by which you should respond.
  3. Your response. Usually within 56 days after the demand, set out item by item on the landlord's schedule where appropriate.
  4. Meeting. The surveyors should generally meet, without prejudice, within 28 days after your response.
  5. Settlement or ADR. The parties should consider alternative dispute resolution, because the courts see litigation as a last resort.
56 dayslandlord's schedule, generally, after the lease ends
56 daysyour response, usually, after the quantified demand
28 daysmeeting, generally, after your response

The 56 days for your response is the clock that matters. A price for the works takes time, so start before the schedule lands if you can.

What dilapidations cost: the published 2026 rates

The costings in a schedule are the landlord's surveyor's estimates. A contractor's price, built from a survey of the floor, can be higher or lower. The best published benchmark is Knight Frank's Landlord Refurbishment Cost Guide for Spring 2026.

It prices a landlord's refurbishment of office floors in Central London at £110 per sq ft, excluding VAT and fees. That is a refurbishment benchmark, not a dilapidations tariff. Your schedule may cover only some of these lines.

Office floor costs per sq ft, Central London, Spring 2026 (Knight Frank, excluding VAT and fees)
Element£ per sq ft
Strip out existing fit-out£10
Raised access floor (refurbish)£5
Suspended ceiling or soffit treatment£12
Decorations£3
Joinery and window treatment£5
LED lighting, power and fire alarms£25
Air conditioning and mechanical ventilation£50
Total office floors£110
£10per sq ft to strip out the old fit-out
£50per sq ft for air conditioning and ventilation
£110per sq ft for the office floors in total

Contractor preliminaries, overheads, profit and risk are included. VAT, professional fees, section 106, community infrastructure levy, rights of light and utility upgrades are not. The Protocol asks the demand to state whether VAT applies, so check it.

Services move the total most: air conditioning and ventilation is £50 of the £110. Outside Central London the guide takes 10% off the South East and 20% off the Midlands and East Anglia, rising to 30% off Wales.

Our Cat A fit out cost per sq ft guide sets out the same benchmark for landlords, including the common parts and plant.

Why the first figure is rarely the final one

A schedule shows what the landlord would like to recover. Two rules in section 18(1) of the Landlord and Tenant Act 1927 pull the figure down.

The first caps damages for breach of a repairing covenant at the amount the landlord's reversion has fallen in value. The second allows no damages for repairs that would be valueless. That applies where the premises will be pulled down or structurally altered at or shortly after the lease ends.

That is why the endorsement must show the landlord's intentions. The Protocol also says the demand should not include items likely to be superseded by those intentions.

Two surveyors can be a long way apart. In Sunlife v Tiger Aspect, the landlord's costed schedule of August 2009 showed about £2.45 million. The tenant's surveyor's schedule in response showed about £87,000.

After trial the judge assessed the cost of the works at £1,353,254, including validation reports and the cost of preparing the schedule. Neither first figure was the outcome.

The cap did not help that tenant. The judge estimated the building's fall in value at about £1.408 million, more than the cost of the works. So the cap did not limit what the landlord recovered.

Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

Pascal Hunt, Google reviewSee all reviews on Google

Doing the works yourself instead of paying

Before the lease ends you can price the works and set the result against the landlord's figure. Whether you may do them, and when, depends on the lease, any licence for alterations and the landlord's access. Your solicitor confirms.

Office corridor with glass partitions, timber-faced walls, an exposed ceiling with cable tray and black pendant lamps

Doing the works tends to make sense when three things line up:

  1. A clear scope. Taking out your own partitions, kitchen and extra cabling is easy to define.
  2. A lower price. A contractor's price for the real scope sits below the schedule's costings.
  3. Time. The works can finish before the lease end date.

Paying can make sense when the landlord will demolish or refurbish anyway, because the repairs may be valueless. It can also make sense when finishing the works would mean paying rent past the lease end.

A costed dilapidations schedule from a builder gives your surveyor something firm to negotiate with. Costs come back by section of the schedule. We do not prepare or negotiate the claim: your surveyor does.

A licence for alterations often records what you must remove at the end, so read it first. Our licence for alterations guide explains how that works. For the wider picture, see dilapidations explained: meaning and the legal cap.

A fixed end date shapes the whole programme. At Beaumont House, a client with five weeks left on its old lease had 750 sq m refurbished in three weeks. That was a fit-out, not a dilapidations job, but the lesson is the same: count back from the date.

A costed schedule in five steps

A figure you can put in front of the landlord's surveyor needs a survey behind it. These five steps get there.

  1. Send us the papers. The schedule, the floor plans and an extract of the lease.
  2. Walk the floor. We walk it with you or your surveyor and check each item against what is there.
  3. Cost by section. Each section of the schedule is priced for your floor, so the figures sit beside the landlord's.
  4. Fit the programme to the lease date. We count back from the day the keys go back.
  5. Decide. With a price for the works, paying or doing them becomes a choice about numbers.

Send us your schedule for a free costing and we start with the floor, not the estimate.

  • The schedule as served, with every annex
  • Floor plans and the area of each floor
  • The lease clauses on repair, decoration and reinstatement
  • Any licences for alterations and any schedule of condition
  • The lease end date and any break date
  • Whether the landlord plans to refurbish or redevelop
  • Photographs of the floor as it stands today

Frequently asked questions

What is a schedule of dilapidations?

It is the landlord's list of the breaches of the tenant's repairing, redecoration and reinstatement obligations. For each breach it gives the works needed to remedy it and, if relevant, the landlord's costings. The Dilapidations Protocol sets out a standard form with five columns.

How much do dilapidations cost per sq ft?

There is no single rate, because the cost follows the lease, the schedule and the floor. As a published benchmark, Knight Frank's Spring 2026 guide prices stripping out an old fit-out at £10 per sq ft and office floors at £110 per sq ft in Central London, excluding VAT and fees. That prices a landlord's refurbishment, not a dilapidations claim.

What is the difference between an interim and a terminal schedule of dilapidations?

An interim schedule is sent before the lease ends. A terminal schedule is sent at or after the end. If the landlord sent an interim schedule, the Protocol says it should confirm at termination that nothing has changed or send a further schedule.

How long does a landlord have to serve a schedule of dilapidations?

The Protocol says within a reasonable time, which will generally be within 56 days after the lease ends. It sets out the conduct a court would normally expect before proceedings. It is not a statutory deadline, so take advice if your schedule is late.

Can I do the dilapidations works myself instead of paying the landlord?

Often, yes, if the lease and the landlord's access allow it and the works are finished before the lease ends. It tends to suit clear scopes, such as removing your own partitions. Get the works priced first and ask your solicitor to confirm what the lease requires.

Who prepares a schedule of dilapidations?

The landlord, usually through a chartered building surveyor. The Protocol says the schedule should be endorsed by the landlord or, where a surveyor prepared it, by the surveyor. We are not surveyors: we price and carry out the works on the schedule.