For freeholders, managing agents and leaseholders
Section 20 Notice and Consultation for Major Works
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
A section 20 notice opens the consultation a landlord in England must run before charging any leaseholder more than £250 for major works.
- It applies once any one leaseholder's share of the works is more than £250.
- Two notices each open a 30-day window: the notice of intention, then the estimates.
- Skip it and each leaseholder pays no more than £250, unless the tribunal dispenses.
A section 20 notice starts the consultation a landlord in England must run before charging leaseholders more than £250 each for major works. Consultation means a notice of intention, a statement of at least two estimates, and 30 days for leaseholders to comment after each notice.
This guide is for whoever runs the process: the freeholder, a resident management company director or a managing agent. It also helps the leaseholder who has just received a notice. We are Section 20 works contractors who price the works the process exists for. Running one now? Get a free major works estimate.
When section 20 consultation applies
Section 20 of the Landlord and Tenant Act 1985 limits what a landlord can recover through service charges. Unless the consultation requirements are met, or the First-tier Tribunal dispenses with them, each leaseholder's contribution is capped.
Two triggers matter. Qualifying works are works on a building or any other premises. Consultation applies once any one leaseholder's share of their cost is more than £250. Roof, window and external redecoration schemes often cross that line.
A long-term agreement is one for a term of more than twelve months. Consultation applies to it once any leaseholder's share in an accounting period is more than £100. The steps for those agreements differ from the ones below.
Section 20 consultation timeline: the three notices
For works that do not need a public notice, the steps sit in Part 2 of Schedule 4 to the 2003 regulations. There are two notices with a 30-day window each, then a reasons notice where one is needed.
| Stage | What the landlord sends | Window |
|---|---|---|
| 1. Notice of intention | The works, the reasons, an invitation to comment and to nominate contractors | 30 days |
| 2. Statement of estimates | At least two estimates, a summary of comments and the response, plus where to inspect them | 30 days |
| 3. Reasons notice | Why the contract went to this contractor, within 21 days of the contract | Only if neither a nominee nor the lowest estimate won |
The 30 days run from the date of the notice. The two windows alone take at least 60 days, before you count the time to obtain estimates. Where public notice of the works is required, a different route applies and there is no nomination stage.
Consultation only works if the estimates are credible. Section 20 major works contractors earn their place by pricing one specification, so leaseholders compare like with like.
Step 1 of 1
Stage 1: the notice of intention and nominations
The landlord gives notice in writing to each leaseholder, and to a recognised tenants' association where one represents some of them. The notice must do four things:
- Describe the works in general terms, or say where a description can be inspected.
- State the landlord's reasons for considering the works necessary.
- Invite written observations, with an address, and say they must arrive within 30 days.
- Give the date on which that period ends.
The notice must also invite each leaseholder and the association to propose a firm from which the landlord should try to obtain an estimate. The landlord must have regard to observations made in time. Any place of inspection must be reasonable and the description free to read.
Stage 2: estimates that survive consultation
The landlord obtains estimates and sends a free statement of at least two of them. The statement also summarises any observations received and the landlord's response. All the estimates must be open to inspection.
At least one estimate must come from a person wholly unconnected with the landlord. The regulations treat a company director or manager, or their close relative, as connected. If the landlord obtained an estimate from a nominee, it must be one of those in the statement.
A second notice then says where and when the estimates can be inspected, invites comments and gives the end date of a further 30 days. The landlord must have regard to what comes back.
Leaseholders read these estimates closely, so they need to be comparable. Four things make them so:
- One written specification that every firm prices.
- The same assumptions on scaffold, access and working hours.
- Provisional sums marked as such, with what would change them.
- A programme that shows when residents are affected.
We price from the surveyor's report or a maintenance plan, so you can use the figures in the statement. As major works contractors, we offer a free specification and estimate. Send us the report or photos of the block.
Hired Craftex to do the full design and fit out of my gym in Chelsea. Super efficient and fast team. They gave the best price and a proper fast track program. We managed to open in less than 6 weeks with no headaches or surprises during construction. Quality was great, we had zero snags on completion. I’ve worked with a few companies before but these guys really impressed me from project management to how they treat the client. Top GGs.
If consultation is skipped: the £250 cap and dispensation
Without consultation, or dispensation, each leaseholder whose share would exceed £250 pays no more than £250.
The landlord can ask the First-tier Tribunal to dispense with the requirements. The tribunal may do so if satisfied that it is reasonable. In Daejan Investments v Benson in 2013 the Supreme Court said the main question is whether leaseholders suffered real prejudice from the breach.
Leaseholders must identify some credible prejudice. The landlord then has to answer it. The tribunal can grant dispensation on terms, such as reducing the sum claimed and paying the leaseholders' reasonable costs.
Dispensation is not available for works to which section 20D applies. If your scheme involves fire safety remediation, take advice on which regime governs it.
Planning major works with residents at home
The consultation fixes the price. The programme decides how the next months feel for the people who live in the block. Plan these before the notice goes out, because leaseholders will ask.
Scaffold, deliveries, noise and waste are the usual complaints. Residents want to know the dates, the working hours and who to call. A single main contract for roof, windows and decoration avoids three firms blaming each other. For a roof and facade replacement, agree the scaffold dates with residents first.
We have refurbished in a building that stayed occupied. At Kensington Olympia, a 400 sq m penthouse refurbishment in a fully occupied building, we kept disruption to residents low. The building managers were happy with the delivery, noise and waste management. It finished on time with zero snags. That was a penthouse, not block major works.
Every project we have delivered has finished ahead of programme and on budget. Major works are one part of landlord works we take on across London and the UK.
Before you send the notice of intention
- A surveyor's report or maintenance plan that gives the reasons for the works
- A description of the works leaseholders can read, or a reasonable place and hours to inspect it
- The 30-day end date written into the notice
- An address for observations and nominations
- A list of firms to ask, at least one wholly unconnected with the landlord
- One specification that every firm will price
- A plan for residents' access and communication