For developers, landowners and buyers in England
How Long Does Planning Permission Last?
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read
The short answer
In England, full planning permission usually lasts three years from the date it is granted. If work has not lawfully begun by then, the permission expires and you need a new one.
- Outline permission needs every reserved matters application in within three years, then a start within two years of the last approval.
- A trench for the foundations or the demolition of a building can count as a start, once any conditions that must be met first are discharged.
- In England, a Section 73 application cannot extend the time to start or to apply for reserved matters.
- The time limit asks only for a lawful start, but a council can serve a completion notice on a scheme that stalls.
How long does planning permission last? In England, a full planning permission lasts three years from the date it is granted, unless the council sets a different period. The scheme does not have to be finished in that time. It has to be lawfully begun.
That start is where most lapsed consents go wrong. A consent that has quietly expired cannot be built, however good the drawings are. Our planning consultants in the UK check the decision notice, the conditions and the evidence of any start. We do it before a client buys a site or builds on it.
This guide sets out the time limits in the Town and Country Planning Act 1990, section by section.
Buying a site with planning, or sitting on a consent that is running out? Send us the address for a free site appraisal. We check the expiry date, the conditions and whether a start on site or a fresh application is the safer route.
The three-year default for full planning permission
Section 91 of the Act puts a time limit on almost every planning permission. The development must be begun before "the applicable period" ends. In England that period is three years from the date of the grant. In Wales it is five years.
The council can set a longer or a shorter period in the decision, if it has a planning reason. The 2026 NPPF lets officers consider a shorter time limit on housing schemes, under policy HO13. If the decision notice forgets the condition altogether, the Act adds the three years anyway.
Three points catch owners out:
- The clock starts on the decision date. It runs from the date the permission is granted, not from the day the conditions are discharged.
- You can start on day one. Nothing in the Act stops work from the date of the grant, once any conditions allow it.
- A court challenge adds time. Since 18 February 2026, permission from a court to bring a challenge extends the period by one year in England. Further appeals can add more.
| Consent | Time limit | Where it is set |
|---|---|---|
| Full planning permission, England | Begin within 3 years of the grant | Section 91 |
| Full planning permission, Wales | Begin within 5 years of the grant | Section 91 |
| Outline permission, reserved matters | Apply within 3 years of the outline grant | Section 92(2)(a) |
| Outline permission, start on site, England | Begin within 2 years of the last reserved matters approval | Section 92(2)(b) |
| Prior approval, commercial to homes (Class MA) | Complete within 3 years of the prior approval date | GPDO 2015, MA.2(5) |
How long a decision takes to arrive is a separate clock. Our guide to how long planning permission takes covers the statutory periods for a decision and what happens in practice.
Outline permission and reserved matters
An outline permission settles the principle and leaves "reserved matters" for later approval. Under the procedure order, they are access, appearance, landscaping, layout and scale. Section 92 gives outline consent two clocks, not one.
- Apply for every reserved matter. Each application must be made within three years of the date of the outline grant.
- Begin the development. In England, work must start within two years of the final approval of the reserved matters. If they are approved on different dates, the clock runs from the last approval.
Here is how the two clocks fit together. Take an outline permission granted in March 2026. Every reserved matters application must be in by March 2029. If the last one is approved in September 2029, work must begin by September 2031.
The first clock is about making the application, not getting the approval. A reserved matter submitted in time can still be approved after the three years. A matter left out cannot be added once the period has passed.
The council can set longer or shorter periods for both clocks. On a phased scheme, it can also set separate periods for separate parts, and the start clock then follows each part. Wales uses a different rule: five years from the outline, or two years from the last approval if that is later.
Lawful commencement: what counts as a start on site
Section 56 decides when a development has begun. It is the earliest date on which any "material operation" that is part of the approved development begins. The work has to belong to the consented scheme, on the consented footprint.
The Act lists what counts as a material operation:
- Any work of construction in the course of erecting a building.
- Any work of demolition of a building.
- Digging a trench that will contain the foundations, or part of them.
- Laying an underground main or pipe to the foundations, or to that trench.
- Any operation in laying out or constructing a road, or part of a road.
- A change of use that is itself material development.
A short length of foundation trench in the right place can be enough. Surveys, site clearance and a new hoarding are not on the list. Do not rely on them alone.
The conditions matter as much as the digger. Many permissions include conditions that must be met "before development begins". Read each one and get the discharge in writing first. Government guidance says work in breach of a pre-commencement condition is unlawful and may lead to enforcement action. The council may argue that such work was not a lawful start.
We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.
Renewal and section 73: what each route can do
There is no simple renewal of a planning permission in England. Owners often expect to extend the date with a Section 73 application. The Act now rules that out.
Section 73 lets you apply to build a scheme without complying with some of its conditions. The council looks only at the conditions. But two limits apply to time:
- No extension of time. In England, a Section 73 permission must not extend the time to start the development, or to apply for reserved matters.
- No use after expiry. Section 73 is not available at all once the time to begin has passed without a start.
Section 73 still has a place. Before the date, it can change a condition on design, hours or phasing, and the new permission keeps the original deadline. A small change can go through a non-material amendment under section 96A instead. Our guide to Section 73 and non-material amendments compares the two routes.
| Route | What it does | Its limit |
|---|---|---|
| Lawful start on site | Meets the time limit for good | Conditions that must be met first are discharged |
| Fresh planning application | A new permission with a new three years | Judged against the local plan and NPPF of the day |
| Section 73 application | Changes conditions before the date | Cannot move the start date in England |
| Non-material amendment | Small changes to the approved scheme | Only changes the council accepts are not material |
A fresh application is the honest renewal. It carries a new fee and a new decision, and the policy may have moved since the first consent. The Town and Country Planning Act 1990 explained shows how sections 57, 73 and 91 fit together.
Other consents and their time limits
Section 91 does not apply to every kind of permission. The Act lists the exceptions, and each one works on its own clock.
- Permitted development. Rights granted by a development order are outside section 91. A prior approval for commercial space to homes under Class MA must be completed within three years of the prior approval date.
- Retrospective permission. A permission for work already carried out has no start clock, because the work exists.
- Temporary permission. A permission granted for a limited period ends on the date set in its condition.
- Outline permission. It follows section 92, not section 91, as set out above.
Class MA is the one that catches developers out. Its clock is a completion date, not a start date. An office-to-homes scheme that starts late can run out of time before the last flat is finished.
A permission that has been lawfully begun has met its time limit. The Act still lets a council act on a scheme that stalls. If it thinks the work will not be completed within a reasonable period, it can serve a completion notice. The permission then ends on a deadline at least 12 months after the notice is served.
These rules apply in England. Wales shares the 1990 Act but uses longer periods, and Scotland and Northern Ireland have their own planning law.
Expiry risk when you buy a site with planning
A planning permission runs with the land. Section 75 says it benefits the land and everyone with an interest in it, so it passes to a buyer. The clock passes with it. A new owner does not get a fresh three years.
A site sold "with planning" can be close to its date, or past it. A consent that has lapsed adds nothing a buyer can build. Before you exchange, check these points against the council's records:
If the deadline falls before completion of the purchase, agree in the contract who makes the start and when. A lawful start by the seller on the right footprint keeps the consent alive for the buyer.
The safest purchase is one costed before exchange. At Allitsen Road in St John's Wood, a derelict club bought at auction became four costed schemes with a planning strategy in four weeks. Our Development Director, Rob Barton, took 10,000+ homes through planning in his previous roles.
Is the deadline on your consent, or on the site you want to buy, getting close? Send us the address and get a free site appraisal. We read the decision notice, the pre-start conditions and any evidence of a start. You will know if the permission is alive and what it needs.
For a fuller view of the land, see our development feasibility and site appraisal service.
Before you buy a site with planning permission
- The decision date and the time limit condition on the decision notice.
- For outline consent, the date of every reserved matters application and approval.
- Each condition marked "before development begins", and whether it was discharged in writing.
- Evidence of any start on site: dated photos, invoices and the council's letters.
- Any Section 73 permissions, which in England keep the original deadline.
- Any completion notice served on a scheme that started and stopped.