Office Relocation Cost: What a London Office Move Really Costs in 2026

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read

Bright office floor with white-topped timber desks, black mesh chairs and low-sun daylight from tall windows

The short answer

The cost of an office relocation is mostly the fit-out of the new space. In London in 2026 that is about £85.50 to £176 per sq ft all in, before VAT and fees.

  1. Removals, IT, dilapidations on the old office, Stamp Duty Land Tax and overlap rent come on top.
  2. Rent on two offices is a programme cost: the length of the fit-out decides how long it runs.
  3. A landlord contribution or rent-free period can offset the fit-out. Staying put removes the move lines.

The cost of an office relocation is mostly the fit-out of the new space. In London in 2026 that is about £85.50 to £176 per sq ft all in, before VAT and fees.

Removals, the IT move, dilapidations on the old office, Stamp Duty Land Tax and overlap rent come on top. This guide puts every line in one table with its source. We do the fit out of your new office in London, so we price that line from the inside.

Got a floor plan and a move date? Get a fixed figure and we will price the new floor.

Office relocation cost: every line in one table

A removal quote covers the van and the crates. A relocation budget covers the lease you leave and the lease you sign, as well as the move. Nine lines make up most budgets.

Every cost line in an office relocation, and what sets each one
Cost lineWhat sets the figurePublished figure
Fit-out of the new floorFloor area, spec, Cat A or shell£63 to £108 per sq ft construction
Furniture, AV and IT in the fit-outHeadcount and spec£22.50 to £67.50 per sq ft
IT and telecoms moveSeats, circuits, comms room£1,250 per desk, median
Dilapidations on the old officeYour lease and the landlord's scheduleQuoted per lease
Removals and cratesVolume, floors, lifts, out-of-hoursQuoted per move
Fees: legal, agent, surveyorEach adviser's termsQuoted per adviser
Stamp Duty Land Tax on the new leasePremium and net present value of rent0 %, 1 % and 2 % bands on rent
Overlap rent and business ratesWeeks between handover and moveRent and rating of each building
ContingencyYour risk appetiteNo standard figure

The fit-out figures are our 2026 London rates, before VAT and fees. Furniture is £18 to £54 per sq ft and AV and IT £4.50 to £13.50.

The IT figure is one UK IT firm's published median for a 40 to 80 seat move, excluding new hardware. Cloudswitched published it on 3 September 2026. It is a supplier's figure, not a quote.

We found no dated, named UK source for removals, so we print no figure. Ask two removers for a quote on your volume and floors.

VAT at 20 % applies to most goods and services, so to most lines above. Whether you can recover it depends on your VAT position, so ask your accountant.

Fitting out the new office is the biggest cost

Take a 60-person team. At about 100 sq ft per person that is a 6,000 sq ft floor. The fit-out alone runs well into six figures before anything else is added.

Office with full-height glass partitions, an exposed ceiling and a desk with a black mesh chair
£513,000 to £1,053,000fit-out of a 6,000 sq ft floor at £85.50 to £176
£75,000IT relocation for 60 seats, one supplier's median

Both numbers are before VAT. The fit-out line is our arithmetic on our own rates: 6,000 sq ft at £85.50, £122 and £176 gives £513,000, £729,000 and £1,053,000. The IT line is Cloudswitched's median of £1,250 per desk, times 60.

Our rates are for a Cat B fit-out on a Cat A floor in good order. That is the landlord's base build plus your meeting rooms, kitchen, furniture, AV and IT. A shell floor costs more, because the landlord's base build is then yours to pay for.

The full table by spec is in our office fit out cost per sq ft guide. For your own floor, use the office fit-out cost calculator.

Two cautions on the IT line. First, check what your fit-out price already includes, because cabling can sit in both. Second, budget it early: Cloudswitched's own case study shows a 54-person firm spending just over £96,000 against a £28,000 line.

Want the fit-out figure before you sign? Send us the plan and we price the fit out of your new office in London from it.

Leaving the old office: dilapidations and reinstatement

This cost arrives after you have left. It is the work your lease says you owe on the old office, and the landlord prices it in a schedule of dilapidations.

The Dilapidations Protocol sets the expected order. The landlord's schedule generally comes within 56 days after the lease ends. You usually respond within 56 days after the landlord sends its demand. It is expected conduct, not a statutory deadline.

So the bill lands while the new fit-out is already paid for. Read the repair, decoration and reinstatement clauses before you commit to a move date. Then budget a figure for them.

Our guide to a schedule of dilapidations costs sets out what a schedule lists, the published cost benchmark and how to respond. Strip-out and reinstatement are building work, so a contractor's price from a survey is a useful second view against the landlord's.

Tax, fees and the rent you pay twice

Stamp Duty Land Tax applies to a new non-residential lease in two parts. The premium is taxed at 0 % up to £150,000, 2 % on the next £100,000 and 5 % above £250,000. The rent is taxed on its net present value.

SDLT on a new non-residential lease, rates from GOV.UK
Charged onBandRate
PremiumUp to £150,0000 %
Premium£150,001 to £250,0002 %
PremiumAbove £250,0005 %
Net present value of rent£0 to £150,0000 %
Net present value of rent£150,001 to £5,000,0001 %
Net present value of rentAbove £5,000,0002 %

The two parts are calculated separately, then added together. A lease whose rent has a net present value under £150,000 pays no SDLT on the rent. Your solicitor will confirm the figure on your lease.

Business rates start on the new premises. They follow the property's rateable value and a multiplier set for the tax year. Look up the building's rateable value on gov.uk before you sign.

Overlap rent is the cost people forget. You pay rent on the new floor while it is fitted out. You also carry the old office until the lease ends. The fit-out programme decides how many weeks both run. At Beaumont House, the client had five weeks left on its old lease, and we refurbished 750 sq m in three.

Beaumont House shows what a short programme does. The client had five weeks before the lease expired and other contractors quoted at least 12 weeks. We were on site two weeks after the first contact. We rebuilt 750 sq m in three weeks for £350K and moved the furniture and equipment.

Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody

Nikita Nigai, Google reviewSee all reviews on Google

How a landlord contribution or rent-free period offsets the move

Landlords compete for tenants with incentives. They come in three forms: a rent-free period, a capital contribution towards your fit-out, or landlord's works done before you move in.

Office atrium with large planters, trees and green chairs beside a glass wall

Each form lowers a different line. A rent-free period covers rent while the floor is fitted out, so it attacks the overlap. A contribution lowers the fit-out line. Landlord's works shrink the scope you have to price.

The form matters as much as the amount. In many deals you fund the works first and the contribution follows against evidence. Tax treatment also differs by form, so take advice before you accept one.

Our guide to a landlord fit-out contribution explains the three forms and what to agree in the heads of terms. Price your fit-out first, so you know what the incentive has to cover.

Relocate or refurbish: what changes on the cost sheet

Both routes pay for building work. Laxton's 2026 puts UK office refurbishment at £1,000 to £1,800 per m² for the building work, before fees and VAT. Our all-in relocation fit-out rates are £920 to £1,890 per m², because they include furniture, AV and IT.

The ranges overlap. So the fit-out is not what separates the two routes. The move lines are.

Lines that exist only if you move
Cost lineStay and refurbishRelocate
Overlap rentNoOften
SDLT on a new leaseNoCan apply
Dilapidations on the old officeOnly at the end of your current leaseYes, on leaving
Removals and IT moveSmall, by phaseYes
Business rates on a second buildingNoYes

Staying costs you phasing and out-of-hours work. It also keeps the building you have. Our office refurbishment cost guide prices that side per m². Cost both routes on the same floor area, then compare the totals.

Building the relocation budget in six steps

You can finish the first three this month. They need your lease and a floor plan, not a survey.

  1. Lease dates. Note the lease end, any break date and the clauses on repair and reinstatement.
  2. Floor area. Work out the area from headcount, at about 100 sq ft per person as a first cut.
  3. Fit-out figure. Run the calculator for a range, then ask for a fixed figure after a survey.
  4. Move lines. Get IT, removals and fee quotes for your own seats and volume.
  5. Tax and rent. Ask your solicitor for SDLT and your accountant for VAT. Look up the new rateable value.
  6. Programme. Work back from the lease end and add the overlap weeks to the total.

Our office relocation checklist takes the same move month by month, from team and brief to snagging. Ready for step 3? Get a fixed figure and send us the floor plan.

  • The new floor plan and its area in sq ft or m²
  • Your move date, the old lease end and any break date
  • The landlord's Cat A specification for the new floor
  • Heads of terms, including any rent-free period or contribution
  • Any fit-out quote you already hold for the new floor
  • Quotes for IT and removals for your headcount

Frequently asked questions

How much does it cost to relocate an office?

The fit-out of the new floor is the largest line: about £85.50 to £176 per sq ft all in for a London office in 2026, before VAT and fees. Removals, the IT move, dilapidations on the old office, Stamp Duty Land Tax on the new lease and overlap rent come on top.

What are the main costs of an office move?

The fit-out of the new space, furniture, AV and IT, the IT and telecoms move, removals, dilapidations on the old office, professional fees, Stamp Duty Land Tax on the new lease and rent paid on two offices while the new one is fitted out. Business rates start on the new premises.

Who pays for the fit-out when you move office?

Usually the tenant. The landlord delivers a Cat A base build and you pay for the Cat B fit-out on top. A landlord contribution, a rent-free period or landlord's works can offset it, so agree them in the heads of terms before you sign.

Do you pay stamp duty on a new office lease?

Possibly. Stamp Duty Land Tax on a new non-residential lease has two parts. The premium is taxed at 0 % to £150,000, 2 % on the next £100,000 and 5 % above £250,000. The rent is taxed on its net present value at 0 % to £150,000, 1 % to £5,000,000 and 2 % above.

Is it cheaper to refurbish or relocate an office?

Refurbishing avoids the lines that exist only if you move: overlap rent, SDLT on a new lease, dilapidations on the old floor, removals and the IT move. Both routes pay for building work, so cost the same floor area both ways and compare the totals.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Price the move before you sign the new lease.

Send us the new floor plan and your move date. We come back with a fixed figure and a programme.