Cladding Safety Scheme: Eligibility, Funding and Works

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read

Riverside apartment blocks in London, including a curved block with a gold-coloured grid facade

The short answer

The Cladding Safety Scheme is the government fund, run by Homes England, that pays for life-safety cladding works on residential buildings over 11 metres in England. Since 1 September 2025 it is the single scheme for those buildings, London included.

  1. Only the Responsible Entity, the party legally responsible for external repairs, or its representative can apply.
  2. The FRAEW must come from a firm on the scheme's panel.
  3. Funding comes in up to two stages: pre-tender support, then full cost funding once the works package is approved.
  4. The works contract must name a principal contractor, hold retentions and include a 12-month defects period.

The Cladding Safety Scheme is the government fund that pays for life-safety cladding works on residential buildings over 11 metres in England. Homes England runs it, and since 1 September 2025 it is the single scheme for those buildings, London included.

The money goes to the building's Responsible Entity, not to leaseholders. It covers the works a FRAEW recommends to address the risk from the cladding. It also sets rules for the works contract.

We carry out cladding remediation in London as main contractor, so this guide follows the scheme through to the works. We are not on the assessor panel and we do not run applications. Planning one? Get a free remediation scope.

Who the Cladding Safety Scheme is for

Only the Responsible Entity can apply: the person or organisation legally responsible for the building's external repair and maintenance. A representative, such as a managing agent, can lead the application with evidence of authority.

Who can be the Responsible Entity
Responsible EntityTypical building
Freeholder or head leaseholderPrivate blocks with long leases
Management company or RMCBlocks where the lease puts repair on the company
Right to Manage companyBlocks managed by qualifying leaseholders
Registered provider of social housingHousing association and council blocks
Section 24 managerBlocks with a tribunal-appointed manager

Leaseholders cannot apply unless they are the head leaseholder acting as the Responsible Entity. GOV.UK suggests leaseholders contact their Responsible Entity and encourage it to apply.

The scheme is a last resort. Homes England will not fund a building where a developer has agreed, under the developer remediation contract, to fix it. Where a developer has not signed but is still trading, you are expected to pursue it first.

Eligibility: height, wall system and the FRAEW

Three tests decide eligibility. The building must be over 11 metres, residential or mixed use with residential leaseholders, and it must have cladding as PAS 9980 defines it.

Height is measured from the lowest external ground level to the finished floor of the top occupied storey. Plant rooms, roof gardens, gyms and storage on the top floor do not count as occupied.

11 mminimum height, to the top occupied storey
1 Nov 2023FRAEWs accepted from panel firms only
10 Jan 2022works that started earlier are not funded

The FRAEW comes after the first stage of the application. Once it is submitted, you instruct a FRAEW from the scheme's panel of fire risk assessors, summarised on the scheme's own summary sheet. Masonry or concrete walls may not need one at all.

The scheme does not fund hotels, offices or buildings with no residential leaseholders or affordable housing tenants. It also excludes buildings where works started on site before 10 January 2022.

Our guide to FRAEW and PAS 9980 explains the appraisal, and the EWS1 form guide covers what lenders ask for.

How the application and grant stages work

The application runs through the Building Remediation Hub, one building per application. Funding then comes in up to two stages.

  1. Eligibility. You submit building details, proof of authority, leaseholder engagement and other funding routes explored.
  2. FRAEW. A panel assessor appraises the walls and recommends the works.
  3. Pre-tender support. Where offered, it pays for the professional team, design and a competitive tender. It cannot pay for capital works.
  4. Works package. You submit the tendered costs. Homes England's cost consultants check they are eligible and reasonable, and ask whether competitive bids were obtained.
  5. Full cost funding. Once approved, you sign the works package deed, enter the works contract and draw payments monthly.

Pre-tender support is not a promise of full funding. GOV.UK warns that applicants may be proceeding at risk until the full award is confirmed.

Building Safety Fund for taller buildings

The Building Safety Fund opened in June 2020 for buildings over 18 metres. It closed to new applications on 1 September 2025. From then the Cladding Safety Scheme became the single scheme for all buildings over 11 metres in England.

Which fund applies, by when the application was made
BuildingBefore July 2023July 2023 to August 2025From 1 September 2025
11 to 18 mMedium Rise Scheme pilot, from November 2022Cladding Safety SchemeCladding Safety Scheme
Over 18 m, in LondonBuilding Safety FundBuilding Safety FundCladding Safety Scheme
Over 18 m, outside LondonBuilding Safety FundCladding Safety SchemeCladding Safety Scheme

A separate window for buildings under 11 metres closed on 9 October 2026, with existing applications still being assessed.

Choosing a contractor the funder accepts

The scheme sets out what the works contract must contain. Read it before you tender, because a contract that misses these points delays the works package deed.

What the Cladding Safety Scheme asks of the works contract
RequirementWhat GOV.UK asks for
Principal contractorThe main contractor, appointed under CDM 2015 and competent
Principal designerNamed, under CDM 2015
Contract administratorA chartered CA, employer's agent or architect
Cost consultantA chartered quantity surveyor or cost consultant, such as RICS
RetentionAt least 5% to practical completion, then at least 2.5% for the defects period
Defects periodAt least 12 months
Design liabilityPI cover that does not exclude cladding, where the contractor designs
FormExecuted as a deed, with adjudication or arbitration

One more rule protects independence. One party cannot provide full consultancy services and also act as, or appoint, the lead contractor. Homes England also expects firms on the works to be part of the Considerate Constructors Scheme.

Price matters too. The cost consultants check that costs are reasonable and competitively obtained. Already have a tender back? Send it to us. We'll beat it, line by line, in the format the consultants check.

We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍

Apartify Estates, Google reviewSee all reviews on Google

Timescales and resident communication

The scheme expects a realistic but ambitious programme, and Homes England must be told of any change to it. Once funded, a progress report is due every month.

Residents are told at each step. GOV.UK lists the milestones the Responsible Entity must report on:

  1. Eligibility application submitted, and its outcome.
  2. Works application submitted.
  3. Procurement, with timescales and likely causes of delay.
  4. The funding outcome and the grant funding agreement.
  5. Start on site, with estimated start and end dates.
  6. Works completed.

On site, applicants must limit the impact on residents: phasing, access to common spaces, ventilation and light, noise and privacy. In a higher-risk building over 18 metres, the Building Safety Regulator must also approve the works before they start.

Lived-in blocks are where we work. At Pan Peninsula in Canary Wharf we rebuilt a 290 sq m penthouse in 10 weeks with residents at home. Neither that nor Kensington Olympia was a cladding job, but the access and resident planning are the same.

Ready for the works package? Send us the FRAEW and the tender pack for a scope, a cost plan and a programme with dates.

  • Responsible Entity confirmed, with authority for any representative
  • Developer checked against the developer remediation contract
  • Height measured to the top occupied storey
  • FRAEW from a scheme panel firm, with the summary sheet
  • Professional team: principal designer, contract administrator, chartered cost consultant
  • Competitive tender and a works contract that meets the scheme's terms
  • Building Safety Regulator approval planned, if the building is higher-risk
  • Updates to leaseholders and residents at every milestone

Frequently asked questions

Who can apply to the Cladding Safety Scheme?

The Responsible Entity: the person or organisation legally responsible for the building's external repair and maintenance, or its representative. That can be a freeholder, head leaseholder, management company, RTM company or social housing provider. Leaseholders cannot apply unless they are the head leaseholder acting as the Responsible Entity.

Is the Building Safety Fund still open?

No. The Building Safety Fund, opened in June 2020 for buildings over 18 metres, closed to new applications on 1 September 2025. Since then the Cladding Safety Scheme has been the single scheme for all buildings over 11 metres in England, including those in London.

Does the Cladding Safety Scheme fund buildings under 11 metres?

A separate window for buildings under 11 metres, delivered through the scheme, closed to new applications on 9 October 2026. Applications made before the deadline are still being assessed.

Will the scheme pay if the developer is still trading?

Homes England will not fund a building where a developer has agreed, under the developer remediation contract, to fix it or pay. Where the developer has not signed but is still trading, you are expected to take reasonable steps to get it to fix the cladding first.

What will the Cladding Safety Scheme not pay for?

It will not fund wider redecoration, renewal or general maintenance, the replacement of windows or other elements, repair and renewal costs, or building insurance premiums. It funds reasonable costs of works recommended in the FRAEW to address life-safety risks from the cladding.

Do I need a FRAEW to apply?

Yes. After you submit the first part of the application, you instruct a FRAEW from the scheme's panel of fire risk assessors. Homes England has only accepted FRAEWs from panel firms since 1 November 2023.