Commercial Solar Panel Cost in 2026: Price per kWp, Payback and ROI

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read

Aerial view of two large logistics warehouses with solar panels covering their roofs

The short answer

Commercial solar panels cost about £500 to £900 per kWp installed in 2026, ex VAT. A 100 kWp array runs from £52,000 to £90,000, and cost per kWp falls as the system grows.

  1. Size sets the price per kWp: published figures fall from about £560 to £810 at 30 kWp to £500 to £750 at 250 kWp.
  2. The roof, scaffold, grid connection and any battery are priced on top of the panels.
  3. Payback depends on how much of the power the building uses itself, from about 4 years to over 8 on the same array.

Commercial solar panels cost about £500 to £900 per kWp installed in 2026, ex VAT. A 100 kWp array on about 600 m² of roof runs from £52,000 to £90,000. The roof, scaffold, grid connection and any battery come on top.

This guide is for finance directors, owners and landlords with a big flat roof. It shows published prices with publisher and date, then the payback, tax relief and buy-or-PPA choice. Our commercial solar installation work starts at £100,000, roughly 150 kWp of panels.

Want a number for your roof? Get a free solar survey and payback estimate.

Commercial solar panel cost per kWp in 2026

Two UK guides publish a price for each system size, and they do not agree. So the table shows each figure with its publisher and date. All are installed prices, ex VAT. They are published market figures, not Craftex quotes.

Aerial view of a long logistics warehouse roof fully covered in solar panels
A roof of this size is priced per kWp, with the roof works listed separately.
Commercial solar panel cost by system size, 2026
System sizeRoof neededInstalled costPublisher and date
30 kWpabout 180 m²£16,800 to £24,300Solar-Voltaics, 13 Feb 2026
50 kWpabout 300 m²£27,000 to £39,500Solar-Voltaics, 13 Feb 2026
100 kWpabout 600 m²£52,000 to £77,000Solar-Voltaics, 13 Feb 2026
100 kWpabout 600 m²£70,000 to £90,000Evo Energy, 31 Aug 2026
250 kWpabout 1,500 m²£125,000 to £187,500Solar-Voltaics, 13 Feb 2026
250 kWpabout 1,500 m²£175,000 to £225,000Evo Energy, 31 Aug 2026
500 kWpabout 3,000 m²£350,000 to £450,000Evo Energy, 31 Aug 2026

Roof needed is our arithmetic on a rule of thumb of about 6 m² per kWp (Utilita Business). Evo Energy adds that systems of 1 MWp and above often come in under £700 per kWp.

Why cost per kWp falls with size

Cost per kWp falls as the system grows because the design, survey, inverter and connection work is paid once. Solar-Voltaics' own bands slide from £560 to £810 per kWp at 30 kWp to £500 to £750 at 250 kWp. The two guides still differ by £18,000 at 100 kWp, so compare quotes on the same basis.

For a rough check, our solar page has a calculator. It uses £110 per m² of usable roof for arrays of 250 kWp and above, and £130 below that. That is indicative and ex VAT. A survey turns it into your figure.

What sits on top of the panel price

The tables above price the array. A quote for a real building adds the lines below. No guide prices them as a set, and we price them only from a survey.

  1. The roof. About 35% of 575 surveyed commercial roofs needed remedial work before panels. About 5% could not take them at all (Solar Surveys, via Insurance Times). A full re-roof runs £90 to £180 per m² (MyJobQuote, 2026), or £54,000 to £108,000 over 600 m². Our guide to commercial roof replacement cost sets out the options.
  2. The structure. Panels, frames and ballast add weight. An engineer checks the roof structure first. A weak roof may need a lightweight system.
  3. Scaffold and edge protection. Working at height needs safe access and edge protection. On a live site, crane lifts and access routes are planned around trading.
  4. Grid connection. Generation above 16 A (3.68 kW) per phase needs approval from the network operator under G99. Network works, where needed, are charged to the project.
  5. The insurer. Insurers judge rooftop PV against RC62, the fire code from RISCAuthority and the Fire Protection Association. Ask yours for its conditions before the design is fixed.
  6. Battery, chargers and monitoring. These are optional, priced separately, and covered below. A maintenance contract is also a running cost: Evo Energy puts it at £3,000 to £10,000 a year for a 500 kWp system.

Rooftop solar on a non-domestic building in England is usually permitted development, and the 1 MW limit was removed from 21 December 2023. Check listed status and conservation areas with the council first.

Roof first, then panels

A roof that must be repaired first changes the sum. The cheapest array on a roof with a few years left is often the dearest one. We run commercial solar installation and the roof works under one contract, so the date and the warranty have one owner. Get a free solar survey and payback estimate.

Commercial solar payback and ROI

Payback is the installed cost divided by what the array saves each year. The saving is the power you use yourself, multiplied by the price you would have paid for it. Exported power earns the export rate, which this example leaves out.

Published paybacks run wide, and the reason is self-use:

3.5 to 6 yearsPayback for most systems, Solar-Voltaics, 13 Feb 2026
7 to 12 yearsPayback range, Evo Energy, 31 Aug 2026
28pImport price per kWh used by both guides

To see the effect, take a 100 kWp array at £80,000, the middle of Evo Energy's £70,000 to £90,000. It makes 85,000 kWh a year at 850 kWh per kWp. Each kWh used on site saves 28p. The table changes only the share used on site.

Simple payback for a 100 kWp array by share of power used on site
Used on siteSaving a yearSimple payback
40%£9,5208.4 years
60%£14,2805.6 years
80%£19,0404.2 years

This is a method, not a Craftex result. It leaves out export income, maintenance and the 0.4% to 0.5% a year that panels lose output. Replace the 28p with your own tariff, and the 850 kWh with your roof's yield.

Self-use beats export. A site busy through daylight hours, such as a factory on day shifts, sits near the top of the table. A building that is empty at weekends sits near the bottom.

Export is paid under the Smart Export Guarantee, up to 5 MW. Each licensed supplier sets its own rate, which must always be above zero. Ask for the rate in writing, as it changes.

Tax relief: capital allowances and business rates

Solar panels are special rate expenditure under section 104A(1)(g) of the Capital Allowances Act 2001, added in 2012. It matters because the allowance depends on the pool the cost goes into.

A company can claim a 50% first-year allowance on special rate expenditure on new, unused plant. That comes from section 45S and the table in section 52, and the section has no end date. The balance stays in the pool and is written down over later years.

The Annual Investment Allowance is £1 million a year. It can cover most plant and machinery, for companies, sole traders and most partnerships. Companies controlled by the same person share one allowance. You cannot claim both allowances on the same cost. Our guide to capital allowances on commercial property covers the wider rules.

In England, panels and the batteries that store their power are also left out of the building's rateable value. That applies to days before 1 April 2035, under regulation 2 of SI 2022/405. The array does not raise your business rates bill.

Could not be HAPPIER with Sviat and the Craftex team, they certainly showed me that they’re the number one office design company in London that we’ve had the pleasure of working with. They gave us a unique design just like we wanted, and we loved the first initial draft of the concept. Also have to give them props for Construction, I gave them a tight timeline as we needed to move our team in ASAP, so they pulled double shifts and I didn’t see a drop in quality. Will be to talking to the team when we move up to our next bigger office. Highly recommended A+++

Mikhail Burdoev, Google reviewSee all reviews on Google

Buy, lease or PPA

There are three ways to pay for commercial solar. The choice decides who owns the array, who gets the saving and what the roof must allow.

Three ways to pay for commercial solar
RouteWho owns the arrayUpfront costWho gets the saving
Buy outrightYouThe full priceYou, all of it, plus the tax allowances
Lease or financeYou or the lessorLow or noneYou, less the payments
Power purchase agreement (PPA)The providerNoneShared: you pay the provider for the power

A PPA moves the cost and the risk to the provider and takes much of the saving with it. Buying costs more at the start and keeps the allowances. Whichever route you take, the roof must carry the system for the length of the contract.

The lease comes first. A tenant normally needs the landlord's licence to alter the roof, and the lease should say what happens to the panels at the end. A landlord can sell the power to its tenants, but each tenant needs its own contract. Ask your solicitor to read both, ahead of any design work.

For landlords there is a second reason to look. Solar can help a building toward a better EPC rating. EPC B by 2031 is proposed for let commercial buildings, not yet law. Our guide to MEES rules for commercial landlords sets out where that stands.

Battery storage and grid connection costs

A battery stores midday output for the evening. Published prices fall with size, as the figures below show. They are installed prices from Reonic (20 July 2026), citing Heatable.

Commercial battery cost by size, 2026
Battery sizeInstalled cost per kWh
Up to 50 kWh£400 to £800
100 kWh£200 to £400
200 to 500 kWh£300 to £500
500 kWh and up£140 to £240

A battery pays when much of your load falls after dark, or when much of the output would be exported. Evo Energy says self-use rises from 30% to 40% without a battery to 60% to 70% with a well-sized one. Reonic gives paybacks of 4 to 10 years. Size it from half-hourly data.

For a house rather than a site, see what a solar battery costs.

Grid connection and G99

Grid connection is the other cost that surprises buyers. Generation above 16 A (3.68 kW) per phase needs G99 approval. UK Power Networks asks for a notification under 5 kW. From 5 kW to 50 kW, the installer applies on its online portal. At 50 kW and above, the project follows a step-by-step process.

The operator's answer can set both the date and the cost, because it may require network works. Apply straight after the survey. Ask whether limiting the export would avoid reinforcement. No guide we found gives a reliable fee or timescale, so we state none.

We build for sites that cannot stop. At Banbury Warehouse we fitted out 148 sq m inside a live warehouse in 4 weeks, and operations never stopped. It was not a solar job, but the discipline is the same.

Gather these before you ask for a quote. They let a firm size the array and price the roof without a second visit.

Ready to price yours? Get a free solar survey and payback estimate. Send the last year of bills and the site address. Roof drawings and phone photos help. We inspect the roof covering, structure and incoming supply. Then we return a payback estimate and a programme counted back from your date, at no charge and with no obligation.

Before you ask for a commercial solar quote

  • 12 months of electricity bills, or half-hourly data
  • Roof age, covering and any warranty
  • Your lease and the landlord's consent
  • Your insurer's contact and its conditions
  • Your network operator's area
  • Your target switch-on date

Frequently asked questions

How much does commercial solar cost per kWp?

Published 2026 figures put commercial solar at about £500 to £900 per kWp installed, ex VAT. Solar-Voltaics (13 February 2026) gives £500 to £810 across 30 to 250 kWp. Evo Energy (updated 31 August 2026) gives £700 to £900. Roof works, grid connection and batteries come on top.

What is the payback period for commercial solar?

Published guides disagree: 3.5 to 6 years for most systems (Solar-Voltaics, 13 February 2026) and 7 to 12 years (Evo Energy, 31 August 2026). The gap is mostly how much power the building uses itself. At £80,000, 28p per kWh and 850 kWh per kWp, a 100 kWp array pays back in 5.6 years at 60% self-use.

Can I claim capital allowances on solar panels?

Yes, in most cases. Solar panels are special rate expenditure under section 104A(1)(g) of the Capital Allowances Act 2001. A company can claim a 50% first-year allowance on it, and the Annual Investment Allowance of £1 million can cover most plant and machinery. Ask your accountant which fits your year-end.

What is a solar PPA and is it better than buying?

In a solar power purchase agreement a provider owns and fits the array and you buy its power under contract. You pay little or nothing upfront but keep only part of the saving. Buying costs more at the start, gives you the whole saving and the tax allowances. The lease and the roof decide which route is open.

Is battery storage worth it for a business?

It can be, where much of the load falls after dark or most solar output would be exported. Published figures run from about £140 to £800 per kWh installed, with paybacks of 4 to 10 years (Reonic, 20 July 2026). Evo Energy says a battery lifts on-site use from 30% to 40% up to 60% to 70%.

Do I need G99 approval for commercial solar?

Yes, if the generation is above 16 A (3.68 kW) per phase, which covers any commercial array. Your network operator must approve the connection. Its answer can set the switch-on date and add network works, so the installer applies early. Arrays under 50 kW use the operator's online portal.