Case study: warehouse fit-out

Banbury Warehouse, Oxfordshire

Warehouse fit-out in Oxfordshire: a 2,500 sq m warehouse redesigned and rebuilt in 8 weeks, with the site running throughout

Site kept running

8 weeks on site, with the
warehouse working throughout

The project

  • £350Kproject value, design and build
  • 2,500 sq mthe whole warehouse, Banbury
  • 148 sq mof new welfare and storage rooms
  • 1team for the design and the build

A busy warehouse that needed more from the same building

In 2018 our team, then trading as Focus Internal Ltd, was asked to redesign and rebuild a modern, busy 2,500 sq m warehouse in Banbury, Oxfordshire. The brief: offices and staff facilities inside the warehouse, more and better storage, and a building brought up to date, from the floor to the power supply.

The catch: the warehouse could not stop. Stock had to keep moving in and out around the works every day.

Craftex, as the company is now called, designed the whole scheme and built it as one warehouse fit-out contract: eight weeks on site, £350K, handed over with the business still trading.

A racking aisle in the Banbury warehouse: orange shelving stocked with boxes on the left, tall pallet racking with yellow and black striped beams ahead, grey crates on pallets and a pale resin floor

Warehouse fit-out in Oxfordshire: the brief

Floor area
2,500 sq m
Project value
£350K
Programme
8 weeks
Scope
Design and build

Refurbishing a warehouse that cannot stop?

Send us the floor plan and tell us what has to keep moving. We design the scheme, phase the works around your shifts and deliveries, and come back with a fixed-price proposal.

Warehouse offices, changing rooms and storage: what we built inside

A white self-contained block with double doors standing on the warehouse floor, a low steel barrier rail along its base, racking with boxes to the left and a black pool table on the pale floor

Offices built inside the warehouse

The design was ours, as a design and build contract: one team drew the layout, priced it and built it. The offices went in as self-contained blocks on the warehouse floor, with their own lighting, power and ventilation, so the open floor around them stayed free for stock and vehicles. Inside, the standard is that of an office fit-out, not a site cabin.

What this means for you: offices inside a warehouse do not need a mezzanine or an extension; a block on the floor, designed with the racking and the routes, is faster and cheaper.

A changing room with rows of pale grey lockers, a slatted timber bench with a black steel coat rail and sunlight on a pale floor

Changing rooms with lockers for the warehouse team

New changing rooms with lockers for personal belongings, slatted timber benches with coat rails and a custom-made sink. Pendant lamps hang from the high, open ceiling, so the rooms feel like part of a modern building rather than a corner of a shed.

What this means for you: size welfare for the busiest shift, not the average headcount; lockers and benches for everyone on site at once.

Wide white double doors standing open onto a storage area with shelving, pallet racking and stacked crates

Separate storage rooms with double doors

Separate storage rooms were built off the main floor, each with wide double doors for easy access with trolleys and pallets. Together with the new welfare rooms they add 148 sq m of enclosed space inside the existing building.

What this means for you: enclosed rooms keep valuable or sensitive stock apart from the open floor without a second unit or a lease extension.

A tall bay of grey pallet racking with boxes and crates on its levels, rising towards the roof steel

Pallet racking laid out with the aisles

Pallet racking was installed in the new storage rooms and on the open floor, drawn with the aisles and the forklift routes rather than squeezed around them, so the building holds more stock without slowing the picking.

What this means for you: racking specified with the floor and the routes in the same drawing rarely has to be moved later.

A wide storage aisle between long runs of orange shelving, with crates on pallets on a pale polished floor

New floors: made good, polished finish

The warehouse floor was made good across the building and finished to a polished, modern surface, so the new rooms and the existing areas read as one space. It also cleans easily and takes the forklift traffic.

What this means for you: decide the floor finish for the old and new areas together, before the rooms go up; a patch laid afterwards always shows.

Warehouse electrical upgrade, ventilation and safety barriers: the building brought up to date

The new block from the workshop side: copper pipework and conduit run along the white wall, a duct crosses under the roof, grey tool cabinets and workbenches stand against the block on the pale floor

Electrical upgrade with high-voltage works, and a ventilation upgrade

The incoming electrical supply and distribution were upgraded, including high-voltage works, with new power and lighting to the offices, the changing rooms and the storage rooms. The ventilation was upgraded for the building and ducted to the new rooms. Shutdowns were planned with the client, so the warehouse worked between them. Our MEP contractors handle both packages as one.

What this means for you: check the incoming supply before you design anything; new rooms and new plant often need more power than the building has.

A long white block on the warehouse floor with a low steel barrier rail running along its base, pallet racking stacked with boxes to the left and a pale resin floor

Steel safety barriers and pedestrian guardrails

Steel safety barriers and pedestrian guardrails were installed around the walkways, the new rooms and the plant, with rack-end protection where the forklift routes pass the racking. They separate people from vehicles and support the client's health and safety compliance.

What this means for you: mark where barriers go on the layout drawing, at racking ends, door openings and walkways, before the floor is finished.

A staff break-out area on the warehouse floor: bean bags and a table-tennis table on the pale resin floor, a scissor lift and racking with boxes beyond, white walls and roof steel overhead

Full redecoration, and eight weeks with the warehouse working

The whole warehouse was redecorated and refreshed: walls, steelwork and the new rooms in one finish, so the building looks as new as the rooms inside it. The works ran zone by zone around the client's deliveries and shift pattern, and the whole programme, from the first drawing to handover, took eight weeks on site.

What this means for you: put the phasing in the contract, not in an email, and let the team that drew the scheme build it, so nobody else has to be chased for the date.

Warehouse refurbishment in Banbury: at handover

Already have a layout or a quote?

Send it to us. We check it against what the build will really cost, and we will aim to beat the price.

Our team

  • in

Warehouse fit-out case study: the scope we delivered

One contract for the whole 2,500 sq m building, designed and built by one team while the warehouse kept trading.

PackageWhat it covered
DesignFull design of the scheme by our team: layout, rooms, racking, services and finishes, built as design and build
OfficesOffices built inside the warehouse as self-contained blocks with their own lighting, power and ventilation
Changing roomsChanging rooms with lockers, slatted timber benches and coat rails, a custom-made sink and pendant lighting
Storage roomsSeparate storage rooms with wide double doors; with the welfare rooms, 148 sq m of new enclosed space
Pallet rackingPallet racking in the storage rooms and on the open floor, laid out with the aisles and forklift routes
FloorsExisting warehouse floor made good throughout and finished to a polished, modern surface
ElectricalElectrical upgrade including high-voltage works; new distribution, power and lighting to the new rooms
VentilationVentilation upgrade for the building, ducted to the offices, changing rooms and storage rooms
Safety barriersSteel safety barriers and pedestrian guardrails around the walkways, rooms and plant; rack-end protection at the forklift routes
RedecorationRedecoration and refresh of the entire warehouse: walls, roof steelwork and the new rooms, one finish throughout
Site managementWorks phased by zone around the client's shifts and deliveries; the warehouse traded throughout the 8 weeks

Your warehouse

Get a quote for your project

Banbury is the proof. This project: about £140 per sq m across the whole 2,500 sq m warehouse, delivered in 8 weeks with the site running. Yours depends on how much of the floor you touch, the rooms you need and the state of the incoming power, so we do not show a generic calculator here: a whole-building refresh and a new-build-standard fit-out are priced very differently. Send us the floor plan and the brief, and we come back with a fixed-price proposal.

Free value: take this with you

Nine checks before you fit out a working warehouse

  1. Before you commit

    • List what must keep running. Loading, picking and fire routes decide where the works can go and when.
    • Ask the landlord what needs consent. New rooms, partitions and changes to services often do.
    • Talk to building control early. New rooms inside a warehouse still need escape routes, light and ventilation.
  2. While the design develops

    • Check the incoming power first. New rooms and plant often need an upgrade; a high-voltage job needs the network operator's dates.
    • Draw the racking with the aisles and vehicle routes, not around them.
    • Mark where barriers go: racking ends, door openings and walkways.
  3. Before work starts

    • Agree the phases in writing, around your busiest hours and deliveries.
    • Choose one floor finish for new and existing areas, so the space reads as one.
    • Give design and build to one contractor. Then one team answers for the layout, the cost and the date.

Certified, insured, compliant

  • ISO 9001 Quality Management
  • ISO 14001 Environmental Management
  • ISO 45001 Health & Safety Management
  • SafeContractor Approved
  • SSIP Safety Schemes in Procurement
  • CDM 2015 Principal Contractor
  • CIS Gross
  • Public Liability £10,000,000
  • Employers' Liability £10,000,000
  • Professional Indemnity available on request
  • Defects liability standard 12 months, extendable
  • Warranty up to 10 years available
  • Collateral warranties from our consultants & design team
  • ISO 9001 certified
  • ISO 14001 certified
  • ISO 45001 certified
  • SafeContractor approved
  • CHAS accredited
  • Constructionline Gold
  • TrustMark
  • RICS, Royal Institution of Chartered Surveyors
  • RIBA, Royal Institute of British Architects

What our clients say

See all reviews on Google
  • Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.

    Misha Levit

  • Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.

    Rhea Langford

  • I’d like to thank the team at Сraftex for the work they did on our office.
    It was really important for us to get the work done quickly, but without compromising on quality, as we regularly have clients and guests visiting and needed to move into the new office within a month.
    We spent around two weeks discussing and agreeing all the details before the work started. What I really appreciated was that everything we agreed beforehand was actually followed through during the job. The work was also completed on time.
    Thanks to the whole Сraftex team for a great job. I’d definitely use them again if we need any work done in the future.

    IURII PYLYPETS

  • We recently worked with Craftex and honestly couldn’t be happier with the results. From start to finish, the team was professional, reliable, and highly skilled. The quality of workmanship exceeded our expectations, and everything was completed on time and to a very high standard.
    Communication throughout the project was excellent, and they always went above and beyond to make sure we were satisfied. It’s rare to find a construction company that combines professionalism, attention to detail, and great customer service so well.
    Without a doubt, Craftex is one of the best construction companies we have ever worked with. Highly recommended to anyone looking for quality and trustworthy builders.

    Adam Miah

  • Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

    Pascal Hunt

  • Great company to work with as always. Super flexible at dealing with evolving requirements and fast deployment and execution.

    Akshay Khanna

  • Hired Craftex to do the full design and fit out of my gym in Chelsea. Super efficient and fast team. They gave the best price and a proper fast track program. We managed to open in less than 6 weeks with no headaches or surprises during construction. Quality was great, we had zero snags on completion. I’ve worked with a few companies before but these guys really impressed me from project management to how they treat the client. Top GGs.

    Александр Хоменко

  • I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.

    John Smith

  • Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

    Pawel Kamionka

  • Highly recommended!
    Craftex are the kind of fit-out contractors in London you can truly trust. From the very first meeting, they understood our vision and gave practical ideas to make the most of our space. They turned our old storage area into a clean, efficient, and well-organized warehouse. The team was professional, easy to work with, and clearly took pride in their work.

    Monika Kamionka

  • We brought in Craftex to refurb our London office and honestly, they made the whole thing way easier than we expected. They listened, suggested ideas we wouldn’t have thought of, and explained everything clearly. Not the cheapest quote we got, but the end result shows why, the place looks modern, clean, and our team actually enjoys being here now. Communication was spot-on too. No chasing and confusion, deadlines were hit. If you want people who genuinely care and don’t treat your project like “another job,” I’d recommend them.

    A Google User

  • Sviat and his team at Craftex were brilliant to work with on our office redesign. From the first meeting, they took the time to understand how we actually use the space rather than just pitching generic solutions. They came back with clever, practical ideas to maximise use of the space and get more employees and desks inside . Every step was handled professionally, and the process felt surprisingly smooth for a project of this size. They finished one week ahead of schedule, and the transformation is clear — our office feels brighter, more functional, and much more welcoming. I’d happily recommend Craftex to anyone who wants a reliable design team that also makes the journey enjoyable.

    Cucu Iulian

  • We recently worked with Sviat and the Craftex team on a complete warehouse refurbishment, and the results have been outstanding. From the very beginning, their team was professional, organized, and attentive to every detail. The project was completed on time and within budget, without disrupting our day-to-day operations.

    Simone Racaku

  • My experience with Craftex was excellent from beginning to end. They took the time to really listen to what I wanted and then offered practical suggestions that made the design even better. I always felt like they cared about creating a space that worked for me, not just one that looked nice on paper. The end result is an office that feels stylish, welcoming, and very functional for day-to-day work. The process itself was straightforward, well-managed, and never stressful. I’d definitely recommend Craftex if you’re looking for office design and build services in London — they made the whole journey a positive one.

    Ion Bounegru

  • I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

    Taron Papoyan

  • I had an amazing experience working with Sviat and the Craftex team on our office fit-out in London. They were always professional, responsive, and quick to offer the best advice whenever decisions needed to be made. I really appreciated how they balanced style with practicality — the office doesn’t just look fantastic, it works perfectly for our team. Everything was done with care and attention to detail, and the project never felt overwhelming because they managed it so well. Communication was clear from start to finish, and I always felt involved in the process. I would happily recommend Craftex to anyone looking for a trustworthy contractor.

    Artur Dvorak

  • Craftex carried out a warehouse fit-out for us, and I couldn’t be happier with the outcome. The space has been completely transformed into a highly organized and efficient environment that makes our daily operations much smoother.
    The team was professional but also very approachable — I always felt comfortable asking questions or giving feedback. They came up with smart, practical solutions that worked perfectly for our setup, and everything was explained clearly along the way.
    The best part was how they stuck to the agreed timeline, finishing on schedule without cutting corners. It’s rare to get both quality and reliability, but Craftex delivered both.

    Roma Shchukin

  • We’re extremely happy with Sviat and the Craftex team’s work. They suggested clever ideas, managed the project efficiently, and delivered a functional, modern space. The team was easy to communicate with and very professional throughout the process!

    Polina Lysenko

  • I can honestly say our office has been completely transformed thanks to Craftex. From the very first meeting, the team was approachable, professional, and full of creative ideas that really made sense for our business. They didn’t just focus on how the space would look but also how it would work for the team day-to-day. The new layout is efficient, modern, and welcoming, and you can tell they really thought about the details. The whole process was smooth and surprisingly stress-free. They kept me updated at every stage, which gave me confidence. I’m really happy with the results and wouldn’t hesitate to recommend them to anyone.

    Mykyta Khadzhynov

  • The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!

    Alaa Betar

  • We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.

    Ben Edell

  • These guys actually deliver. They handled our first industrial to residential conversion near Tower Bridge, turned an old warehouse into 4 modern flats. They stuck to the plan, kept the site clean and the timing was on point. No hidden extras, no drama, just a professional construction company in London that gets the job done.

    Богдан Главацкий

  • We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.

    Ardian Beleshi

  • This was a full high-end renovation of my Victorian rental apartment in Westminster, just off Sloane Square and Belgravia. The scope included full fit-out: electrics, plumbing, a new bespoke kitchen, and a luxury bathroom refurbishment. Craftex took care of everything and made the process easy. They weren’t the cheapest, but you can tell they really know what they’re doing when it comes to prime London property renovations.
    The team was professional, organised, and genuinely seemed to care about getting everything right. I was especially impressed with the quality of the finish – the attention to detail really shows in every corner.
    I’m very happy with the results and would definitely recommend Craftex to anyone looking for reliable, high-quality renovation work in Central London.

    Наталия Цимбалюк

  • I was stressed about timing since we had bookings lined up, but they smashed it. Even worked Saturday to finish the floor. My clients love the look — the beauty salon fit-out turned out exactly how I wanted. Couldn’t have pulled it off without their help. Genuinely appreciate the way they communicated throughout the refurbishment. If you need reliable help with beauty salon design or fit-out, especially in a place like Chelsea — these are the guys.

    Rami Jusupova

  • We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍

    Apartify Estates

  • Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.

    Hainro Eybers

  • Holistic therapy space fit-out
    Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.

    Dariia Shvyryda

  • Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody

    Nikita Nigai

  • Amazing experience with these guys. I trusted them my apartment in London and Business. They are always accurate, very professional, responsive and neat. They would always advice me right things for my best interest. I had luxury experience with them and I would definitely recommend Craftex to everyone.

    Motush Motushev

  • Could not be HAPPIER with Sviat and the Craftex team, they certainly showed me that they’re the number one office design company in London that we’ve had the pleasure of working with. They gave us a unique design just like we wanted, and we loved the first initial draft of the concept. Also have to give them props for Construction, I gave them a tight timeline as we needed to move our team in ASAP, so they pulled double shifts and I didn’t see a drop in quality. Will be to talking to the team when we move up to our next bigger office. Highly recommended A+++

    Mikhail Burdoev

  • Very professional company. Craftex did brilliant minimalistic design and completely refurbished my apartment to the highest quality.

    Vlad

  • I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away.
    We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP.
    We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care.
    We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.

    Lia Lavryk

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Warehouse fit-out and refurbishment: your questions

How long does a warehouse fit-out take?

Eight weeks on site here, for the whole 2,500 sq m warehouse: offices, changing rooms, storage rooms, racking, floors, the electrical and ventilation upgrades, the barriers and the redecoration. A smaller scope is quicker; a mezzanine or a new incoming supply takes longer. We agree the date in the contract before work starts.

What did the Banbury warehouse refurbishment cost?

£350K as design and build for the entire 2,500 sq m building. Every warehouse is different: the area you touch, the rooms you add and the condition of the incoming supply decide most of the price. We price yours from the floor plan and a survey, then send a fixed-price proposal.

Does a warehouse electrical upgrade include high-voltage work?

It can. At Banbury the upgrade included high-voltage works as well as the new distribution, lighting and power to the new rooms. We plan the shutdowns with you so the warehouse keeps working between them, and the same team designs and installs the ventilation, so the two packages are one job.

Do you install pallet racking as part of a warehouse fit-out?

Yes. The racking at Banbury went in with the new storage rooms, laid out with the aisles and vehicle routes rather than around them, and finished with steel safety barriers at the walkways. Racking is specified to the loads and the floor; the floor is checked before it goes up.

Was this a Craftex project?

Yes. In 2018 the company traded as Focus Internal Ltd. It was renamed Craftex Ltd in 2020: the same company, Companies House number 10210252.

Can you refurbish a warehouse while it stays open?

Yes. In Banbury the site worked throughout. We split the floor into zones, kept the aisles, loading routes and fire exits open and moved the noisy work and the power shutdowns to the hours you agree with us. More on how we plan it: what a warehouse fit-out includes.

Can you build offices inside a warehouse?

Yes. At Banbury the offices went in as enclosed blocks standing on the slab, each with its own power, lighting and air supply, which left the open floor free for stock and forklifts. Building control still applies: escape routes, daylight and fresh air for every room.

Do warehouses need ventilation?

Yes. The Workplace Regulations require enough fresh or purified air in every enclosed workplace, and the new changing rooms and offices needed their own supply. At Banbury we upgraded the ventilation for the building and ducted it to the new rooms as part of the same contract.

What does a full warehouse refurbishment include?

At Banbury: the design, offices built inside the warehouse, changing rooms with lockers, separate storage rooms, pallet racking, the floor made good to a polished finish, the electrical upgrade with high-voltage works, the ventilation upgrade, steel safety barriers and pedestrian guardrails, and a full redecoration of the building. Fit-out or renovation? The difference, explained.

Which other projects can I look at?

In Oxfordshire we also built the Banbury gym. In London our team fitted out a warehouse unit in Hackney, converted a railway arch warehouse for Drake's and refurbished a penthouse at Kensington Olympia.

Planning a warehouse fit-out or refurbishment?

Craftex designs it, prices it and builds it around your operations, as one accountable team.

Unit 5, 160 Buckingham Palace Road, London SW1W 9TR

info@craftex.co.uk

MESSAGE US ON WHATSAPP

Your details are used only to answer your enquiry (privacy).

WhatsApp us