For commercial landlords and asset managers
MEES Regulations for Commercial Property: EPC E Today, EPC B by 2031 for Larger Buildings
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 10 min read
The short answer
The MEES regulations stop a landlord letting, or continuing to let, a commercial building in England or Wales rated F or G without a registered exemption. The next step is EPC B from 2031 for buildings over 1,000 m², proposed on 18 June 2026 and not yet law.
- EPC E has applied to new lettings since 1 April 2018 and to every existing lease since 1 April 2023.
- The EPC C step for 2027 has been dropped; buildings under 1,000 m² stay at E.
- The seven-year payback test and the exemptions stay, and penalties can reach £150,000 per breach.
- Plan the works around your next lease event, so the building pays for them once.
The MEES regulations mean you cannot let, or keep letting, a commercial building in England or Wales rated F or G without a registered exemption. EPC E has been the floor for new leases since 1 April 2018 and for every existing lease since 1 April 2023.
The next step is EPC B from 2031 for buildings over 1,000 m². The government proposed it on 18 June 2026, and it is not yet law. That sounds far off. It isn't. Most landlords can only do major works at a break, an expiry or a void. A lease event in 2028 may be your one chance.
This guide covers the regulations as they stand, the June 2026 response, the exemptions, the penalties and the works that move a rating. It is written by the team that carries out MEES upgrade works for commercial landlords.
Got a lease event coming? Get a free MEES check: send us your EPC and its recommendation report and we will price the works.
The MEES regulations for commercial property today
The Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015 set the standard. Regulation 27 says a landlord must not let a sub-standard non-domestic building. Sub-standard means an EPC rating below E.
The rule arrived in two stages. From 1 April 2018 it caught every new tenancy, extension and renewal. From 1 April 2023 it caught continuing to let on an existing lease. So a building that was lawful when the tenant moved in can now be in breach. Nothing on site has to change.
A commercial EPC lasts ten years and you need a valid one to sell or let. Many certificates on London buildings are years old. Do not plan works around one of those: commission a fresh assessment first, so the packages are modelled against the rating the building has now.
For the certificate price and the works per sq ft, see what a commercial EPC and the upgrade works cost.
MEES regulations by 2031: what changes and what is only proposed
On 18 June 2026 the government published its interim response to the 2019 and 2021 consultations. It says it is proposed that all private rented buildings over 1,000 square metres will need to reach EPC B from 2031, where cost effective. The intention is for buildings below 1,000 square metres to stay at the current minimum of EPC E.
Two more lines matter. The previously proposed interim EPC C milestone for 2027 will not be taken forward. And the existing flexibility mechanisms, including the 7-year payback test and exemptions, will remain in place.
| Requirement | Status | What it means for a landlord |
|---|---|---|
| EPC E for new leases, renewals and extensions | In force since 1 April 2018 | No new letting of an F or G building without a registered exemption |
| EPC E for every existing lease | In force since 1 April 2023 | Continuing to let an F or G building is a breach, even mid-lease |
| EPC C by 2027 | Dropped | Will not be taken forward (interim response, 18 June 2026) |
| EPC B from 2031, buildings over 1,000 m² | Proposed | Where cost effective; needs secondary legislation through Parliament first |
| Buildings under 1,000 m² | Proposed to stay at E | No higher standard and no date set |
| Seven-year payback test and exemptions | Staying | Confirmed in the interim response |
None of the 2031 standard is law yet. The response says it will only take effect following the successful passage of secondary legislation through Parliament. The full government response is still to come. It will set out how the 1,000 m² threshold works. Treat 2031 as the planning date and the detail as open.
MEES 2030 and EPC C 2027: the dates that changed
Older guides still quote two dates, and both have moved. The 2021 consultation asked about EPC B by 2030. The interim response of 18 June 2026 proposes EPC B from 2031 instead, and only for private rented buildings over 1,000 m².
The interim EPC C milestone for 2027 will not be taken forward. So no EPC C step is coming in 2027, and EPC E is the only standard in force. A page that calls EPC B compulsory in 2030 is out of date.
MEES exemptions and the seven-year payback test
You are not asked to do the impossible. The 2015 Regulations and the government's guidance give a landlord six exemptions, and each one must be registered before it protects you.
- All relevant improvements made. Every improvement that passes the seven-year payback test has been done, or there are none, and the building is still below the minimum.
- Seven-year payback. A recommended measure fails the test if its energy bill savings over seven years are less than its cost.
- Wall insulation. The only relevant improvements are wall insulation, and written expert advice shows they would harm the fabric or structure.
- Third-party consent. A tenant, superior landlord, lender, freeholder or planning authority has refused consent, or attached conditions you cannot reasonably meet.
- Devaluation. A surveyor on the RICS register of valuers advises that the works would reduce the market value by more than 5 per cent.
- New landlord. A six-month exemption from the date you became the landlord.
Most exemptions last five years and apply from the day you register them on the PRS Exemptions Register. A consent exemption refused by the tenant can instead end with that tenancy. They do not pass to a buyer: a new owner starts again.
What counts as a relevant improvement is set by regulation 28. It must be a measure listed in the Green Deal order or in Table 6 of Approved Document L2B. And it must be recommended for your building in a recommendation report or a surveyor's report.
How the seven-year payback test works
The test compares two numbers for each recommended measure, or package of measures. One is the cost of buying and installing it. The other is the expected value of the energy bill savings over seven years, counted from the date the installation is completed.
If the savings are less than the cost, the measure fails and you need not install it. The formula sits in regulation 28(3) to (8), and chapter 2 of the full non-domestic guidance explains it.
To register the exemption you upload three quotes from qualified installers, your confirmation that the measure fails, and the cost calculations. So the quotes are evidence, not paperwork. A vague quote with no scope behind it is a weak base for a five-year exemption.
The same test runs the other way. Where a measure passes, it is a relevant improvement and you are expected to make it before you can rely on the all-improvements exemption.
Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.
Penalties for breaching MEES on a commercial building
Local Weights and Measures Authorities, in practice trading standards, enforce the regulations. They can serve a compliance notice up to 12 months after a suspected breach. Regulation 41 sets the penalties for a non-domestic building.
| Breach | Financial penalty | Cap |
|---|---|---|
| Letting in breach for less than three months | Up to the greater of £5,000 or 10 per cent of rateable value | £50,000 |
| Letting in breach for three months or more | Up to the greater of £10,000 or 20 per cent of rateable value | £150,000 |
| False or misleading information on the register | Up to £5,000 | £5,000 |
| Failing to comply with a compliance notice | Up to £5,000 | £5,000 |
Every penalty also carries a publication penalty: the breach goes on the public register. The bigger costs are usually indirect. A building you cannot re-let. A lender that will not refinance an F-rated asset. A buyer who prices the upgrade into the offer.
If your EPC sits below E, our MEES upgrade works for commercial landlords start from the certificate you already hold. Send it to us with the recommendation report.
The works that move a commercial EPC rating
A non-domestic EPC rates the building's services and fabric, not the tenant's energy bills. So the works that move it are the ones that change those inputs. Every building is different. Use this as the list to put to your assessor, and ask for each package to be modelled before you spend.
| Measure | What it changes in the EPC | Best time to do it |
|---|---|---|
| LED lighting with presence and daylight controls | Lighting energy, usually the largest single input in an office | Any void, or floor by floor in an occupied building |
| Heating and cooling plant, often a heat pump in place of gas boilers or end-of-life air conditioning | Heating, cooling and hot water efficiency | Plant replacement at a lease end or when the plant fails |
| Controls: time, zone and temperature controls or a building management system | How the plant is run | With the plant, or alone where the plant is sound |
| Fabric: roof and wall insulation, glazing, sealing air leaks | Heat loss through the envelope | A full Cat A refurbishment or a re-roofing |
| On-site generation: roof-mounted solar panels | Offsets the building's modelled energy use | Any time the roof and the structure allow it |
Two notes from the contractor's side. Lighting is the cheapest step and often the one that lifts a building clear of E. Heating and cooling plant is the biggest step. It also needs the longest lead time and the most design. In many buildings, new rooftop plant needs the landlord's own planning consent too.
Our M&E services team designs and installs the plant, controls and lighting packages. For a suitable roof we also carry out commercial solar installation, and our sustainable and low-carbon fit-outs keep what works and replace only what doesn't.
Time the works with lease events, so you pay once
Work backwards from 2031. Most commercial leases give the landlord limited rights to carry out works while the tenant is in occupation. The natural windows are breaks, expiries and voids. Each one is also the moment the building is opened up anyway, for dilapidations or a Cat A refit.
That is the point of lining the two up. A tenant handing back a floor settles dilapidations. The landlord was going to re-let it as a Cat A floor anyway. Put the lighting, controls and plant into that same programme. The building is disrupted once, the EPC is re-assessed once, and the new lease starts on a compliant rating.
Our guide to Cat A vs Cat B fit out explains what a landlord usually hands over.
Occupied buildings are not a reason to wait. At Portsoken House in Aldgate we delivered 1,550 sq m of offices on two floors, with a full mechanical and electrical package, in seven months. The other floors were let throughout, so the noisy work ran at night and at weekends.
If the upgrade looks uneconomic, the building may have a better future as something else. Our guide to what to do with an empty office building compares the options. For the tenant who moves in next, see our sustainable office design tips.
Six steps before your next lease event
A landlord with several buildings needs a plan, not a scramble in 2030. Craftex has delivered construction projects since 2016, with around 60 per cent of the labour in-house. Every project has finished ahead of programme and on budget. We work in empty units and in occupied buildings across London.
The checklist below is the plan in six steps. Steps one to three are desk work you can do this month. Steps four to six need the building opened up, so the lease event sets the date. Want the works priced before you brief an assessor? Get a free MEES check by sending us your EPC and recommendation report.
Your MEES plan before 2031
- List every let building: EPC rating, certificate expiry, floor area over or under 1,000 m², next break or expiry.
- Commission a fresh EPC on any building whose certificate is years old or near expiry, so you plan around the real rating.
- Ask the assessor to model lighting, plant, controls and fabric as separate packages, with the rating each one reaches.
- Price the packages with a contractor and run the seven-year payback test on each one, with three quotes where you need the exemption.
- Put the works that pass into the dilapidations and Cat A programme for the next lease event.
- Register any exemption you rely on before the breach date, and diarise its five-year expiry.