Development Feasibility Study: What It Includes and Costs

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read

Tower cranes above a new residential development under construction in London

The short answer

A development feasibility study tests whether a site can carry a scheme that gets consent, can be built and makes a profit. It sets out planning, design options, build cost, GDV, land value, programme and risks, so you can decide before you buy or apply.

  1. It is prepared before the planning submission, ideally before you exchange or bid.
  2. Architects lead on design, quantity surveyors on cost, and a developer-builder prices the options it would build.
  3. A full study with several options usually takes about four weeks with us; our first site appraisal is free.
  4. It is not a RICS valuation. A lender instructs its own RICS-regulated valuer for that.

A development feasibility study tests whether a site can carry a scheme that gets consent, can be built and makes a profit. It turns a site and an idea into a decision, with evidence behind every figure.

This guide sets out what a study answers and contains, who prepares it, what it costs in time and money, and a sample structure. Planning figures are for England.

We prepare each development feasibility study with our own build team pricing every option. At Allitsen Road we issued four costed options in four weeks. Own a site, or about to bid on one? Get a free site appraisal.

What a property feasibility study answers

A feasibility study sits before the planning submission. Its job is to stop a bad purchase or a weak application before money is spent on either. It answers six questions.

  1. What can be built? Planning policy, designations and the site's history set the limits. Design options test them.
  2. What will it cost? A build cost for each option, including the site-specific extras a standard rate leaves out.
  3. What will it be worth? The gross development value (GDV) of the finished homes or space, from local evidence.
  4. What can you pay for the land? The residual land value, once costs and a profit are taken off.
  5. How long will it take? A programme from planning to completion, which drives finance and holding costs.
  6. What could go wrong? A risk register, with each risk priced or given an owner.

The answer can be no. A study that steers you away from a bad site has done its job. Consent alone does not settle the question either. Our guide on why planning permission does not mean viable shows how consented schemes still fail.

Not sure your site would pass these six questions? Send us the address, and we will tell you, free, whether a paid study is worth it.

What a development feasibility study includes

Most studies share seven parts. The depth of each depends on the site and the decision in front of you.

The seven parts of a development feasibility study
PartWhat it contains
PlanningLocal plan policy, designations, Article 4 directions, the planning history and what nearby sites were granted
Design optionsEach option drawn to plan, section and schedule of accommodation, checked against space standards
Build costA cost for each option, with abnormal costs and a contingency shown separately
GDVThe value of the finished scheme, from sold or let comparables nearby
Residual land valueGDV less build, fees, planning obligations, finance and profit
ProgrammeDates for design, planning, pre-construction and the build
RisksEach risk, its likely cost and who owns it

The build cost is the line most studies get wrong. A rate per m² is a start; a cost plan for each option is evidence. Check it allows for abnormal costs in construction, such as ground, demolition, party walls, utilities and access. In our studies, the team that would build each option prices it.

GDV and residual land value turn the scheme into a land price. National planning guidance describes GDV as "an assessment of the value of development". The line-by-line arithmetic, with a worked example, is in our guide to GDV and residual land value.

Planning obligations belong in every option. Affordable housing, section 106 and the Community Infrastructure Levy (CIL) can move land value more than any construction choice.

Who prepares a feasibility study: architect, QS or developer-builder

Several kinds of firm prepare feasibility studies. Each starts from its own trade, and that shapes the answer you get.

Who prepares a feasibility study, and what to check
WhoUsually leads onWhat to check
ArchitectSite and planning context, massing, layouts, unit numbers and areasSome add a rough cost per m²; few test sales values or land value
Quantity surveyor (QS)Build cost estimates and cost plansPrices the design it is given, so ask who drew the options
Planning consultantPolicy, planning history and the planning routeThe Planning Portal says consultants help with feasibility studies and viability
Developer-builderOptions, cost plans from the team that would build, GDV and land valueAsk whether the cost is priced unit by unit or taken from a rate

The gaps between these firms are where money leaks. An architect draws, a surveyor prices, a planner advises, and often nobody signs the whole answer.

A valuation is a separate job. A lender instructs its own RICS-regulated valuer for a Red Book valuation. A feasibility study is not a RICS valuation, and ours is not either.

We are a development and construction company. One firm signs each study, and our construction team prices every option. Our Development Director, Rob Barton, acquired £228M of land in his previous housebuilding roles.

Want one firm to sign the whole answer? Ask for a free first appraisal and we will look at your site.

We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.

Ben Edell, Google reviewSee all reviews on Google

Feasibility study cost and timescale ranges

Fees depend on the site, the number of options and how deep the cost and value work goes. A single figure would mislead, so we explain how fees are set.

RIBA lists three ways architects charge: a percentage of construction cost, a lump sum, or a time charge. It names the time charge, an hourly rate with capped hours, as suited to feasibility studies.

Our first site appraisal is free. A feasibility study, or a full appraisal with a lender pack, is a fixed fee per site, agreed in writing before work starts. We never charge a percentage of land value or GDV.

On timing, allow about four weeks for a full study with several options, cost plans, an appraisal and a programme. A single-option appraisal is quicker. Our free site appraisal comes back within a few working days.

A good study also puts numbers on the costs and waiting times that follow it. These are the national figures for England.

Planning fees and decision periods a study should budget for (England, checked 4 November 2026)
ItemFigure
Planning application, fewer than 10 new homes£610 for each dwellinghouse
Planning application, between 10 and 50 new homes£659 for each dwellinghouse
Decision period, most applications8 weeks
Decision period, major development13 weeks
Decision period with an environmental impact assessment16 weeks

Fees come from the Planning Portal fee guide V2026.1, in force from 1 April 2026. Higher fees are proposed from 8 December 2026 in draft regulations. Decision periods come from GOV.UK and can be extended by agreement.

For a first build figure, our 2026 London rates per m² are £1,980 to £2,925 for a new-build house. A house to flats conversion runs £1,035 to £1,890, and office to residential £1,035 to £1,755. These are construction only, ex VAT and fees. Try our build cost calculator; your fixed figure comes after a survey.

Finance feasibility study: what lenders look at

A finance feasibility study usually means the study a development lender asks to see. The contents are the same as any study. The audience is stricter, so the evidence has to be.

Lenders generally focus on these points:

  1. GDV evidence. Comparable sales or lettings, not asking prices.
  2. Build cost. A priced cost plan with a clear scope, not a rate and a long list of exclusions.
  3. Planning. The consent position, with section 106 and CIL in the numbers.
  4. Programme. Realistic time for approvals, utilities and the build.
  5. Contingency. Enough for the site, especially on conversions and refurbishment.
  6. The team. The track record of the developer and the contractor.
  7. The exit. Who will buy or rent the finished scheme, and on what evidence.

A lender instructs its own RICS-regulated valuer, and during the build a monitoring surveyor checks cost and cash flow. Our study gives that valuer a drawn scheme, a priced build cost and a programme to test.

We do not lend, arrange loans or give financial advice. This section is general information. If useful, we can introduce the lenders we work with on our own projects.

Start with the free site appraisal, before you pay for a full study or a lender pack.

Sample feasibility study structure

Writing your own, or checking one you have been sent? This structure suits most residential and mixed-use sites. Keep each section short, and show the evidence behind every figure.

  1. Executive summary. The recommendation, the preferred option, GDV, build cost, land value and the main risks, on one page.
  2. Site and existing use. Address, area, the current lawful use and the condition of any building.
  3. Planning position. Policy, designations, history, nearby decisions and planning obligations.
  4. Design options. Plans, sections and a schedule of accommodation for each option.
  5. Cost plan. A cost for each option, with abnormal costs and a contingency shown separately.
  6. Appraisal. GDV, costs, fees, finance, profit and the residual land value for each option.
  7. Sensitivity. What happens to land value if sales fall or costs rise.
  8. Programme. Dates from instruction to completion.
  9. Risk register. Each risk, its likely cost and its owner.
  10. Recommendation. Buy, walk away, renegotiate, or which scheme to take to planning.

On the profit line, state the figure you used and why. National planning guidance says 15% to 20% of GDV "may be considered a suitable return to developers" when councils test their local plans.

Any viability assessment sent to a council should be written on the basis that it will be made public. That is the position in national planning guidance.

Allitsen Road: a feasibility study issued in four weeks

74 Allitsen Road in St John's Wood was a vacant former private members' club, derelict inside. It was bought at auction in 2026 without proper due diligence.

We designed and priced four options, from converting the building as it stood to seven apartments. Four options, real cost plans and a GDV appraisal were issued in four weeks.

£6.0Mgross development value (GDV)
4options designed, costed and appraised
4 weeksto issue the study
97%of the maximum GDV from the recommended option

The recommended option reached 97% of the maximum GDV at 91% of the maximum cost, without excavation. Digging the basement would have added about £240k and about three months, for one one-bed worth £260k to £350k.

Raising the ground floor gave a habitable basement instead. Floor levels kept the extended building at 10.8 m, 200 mm below the 11 m sprinkler threshold. This is a feasibility study; the scheme has not been built.

Read the full Allitsen Road feasibility study. Want the same test on your own site? Get a free site appraisal.

Before you rely on a feasibility study

  • The build cost is a cost plan per option, not one rate
  • GDV comes from sold or let comparables nearby
  • Affordable housing, section 106 and CIL are priced per option
  • Every option is checked against space standards
  • The programme has dates, not just durations
  • One person signs the study and stands behind the figures

Frequently asked questions

What is the difference between a feasibility study and a development appraisal?

An appraisal is the financial model: GDV, less costs and profit, leaving the land value. A feasibility study wraps it in evidence: the planning position, the design options and a build cost for each. Without the study, you may be appraising the wrong scheme.

Is a feasibility study a RICS valuation?

No. A valuation for a lender is a formal opinion of value from a RICS-regulated valuer, and the lender instructs its own. A feasibility study tests what a site could become and what that is worth to a developer. Craftex does not issue Red Book valuations.

Should I commission a study before I buy a site?

Yes, ideally before you exchange or bid at auction. That is when the findings can still change the price or stop the purchase. Allitsen Road was bought at auction without proper due diligence; the study came afterwards.

Can I write a feasibility study myself?

You can draft the structure and the planning research yourself. The weak points are usually the build cost and the sales evidence. Use a cost plan per option and sold comparables, not one rate per m² and asking prices. Then have the figures checked by someone who builds.

Does a feasibility study guarantee planning permission?

No. It tests the scheme against policy and precedent, and it names the planning risk. The council decides the application. The Planning Portal notes that even a planning consultant cannot guarantee approval.

How reliable is the build cost in a study?

It depends on how the cost was built. A single rate per m² is an indication only. A cost plan per option, priced trade by trade at worst case, is a firmer basis for a decision. At Allitsen Road the cost plans were worked up unit by unit, including forward inflation.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Get a builder's number before you buy

Send us the site. We draw the options, our build team prices each one, and you get GDV, land value and a programme in one study.

WhatsApp us