House Renovation Cost in London: What Decides It
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read
The short answer
A house renovation in London costs about £1,150 to £1,350 per m² for a refurbishment and £1,530 to £1,800 per m² for a full back-to-brick renovation with Craftex (our indicative 2026 rates, construction only, ex VAT and fees). A 150 m² house with a full renovation comes to roughly £230,000 to £270,000; prime finishes, basements and listed fabric sit above that.
- Structure, services and the kitchen and bathroom specification move the price more than the floor area does.
- London access, parking and party walls add cost that the same house outside London would not carry.
- Add 20% VAT, design fees and a contingency of 5% to 10% to the construction figure.
- A fixed price only exists after a survey, drawings and a written scope. Anything earlier is an estimate.
The cost to renovate a house in London is decided by how deep the work goes, not by what the house is worth. A prime townhouse and a smaller house with the same scope cost much the same per square metre. The finish, the structure and the access are what separate them.
At Herbert Crescent in Knightsbridge, a 450 m² prime refurbishment cost £1.5M over 32 weeks.
This guide shows what decides a house renovation cost. It covers the scope, the six things that move it, the costs outside the quote and the programme. It is written by the team behind our house renovation in London service, which renovates prime homes as one design and build team.
Still choosing the house? Our guide to buying a property to renovate covers the checks to make before you offer.
Our indicative 2026 rates are in the table below; a fixed figure needs a survey. Want a real one? Get a fixed price and we will survey the house.
House renovation cost by scope
Price the renovation by what you are doing to the house. Three scopes cover almost every brief, and each one costs clearly more per square metre than the one before it.
| Scope | What it covers | What pushes it up |
|---|---|---|
| Light refresh | Decoration, flooring, lighting, perhaps one kitchen or bathroom; layout and services kept | Joinery and stone chosen at the top end |
| Full refurbishment | Layout kept: new kitchen and bathrooms, rewire, replumb, new heating, flooring, decoration, joinery | Old services, more bathrooms, a larger kitchen |
| Structural renovation | Back to brick: openings and steels, new services, underfloor heating, bespoke joinery, high-specification rooms | Basements, listed fabric, prime finishes |
New floor area is a different calculation again. A loft, a rear extension or a new basement is priced as new build per square metre of new floor. Our build cost calculator gives a first range for each scope from your floor area.
| Scope | £ per m² | 150 m² house |
|---|---|---|
| Light refresh | Below £1,150, priced room by room | Under £172,000 |
| Full refurbishment | £1,150 to £1,350 | £172,000 to £203,000 |
| Structural renovation, back to brick | £1,530 to £1,800 | £230,000 to £270,000 |
| Extension or new floor area | £1,835 to £2,880 of new floor | Priced on the new area |
Prime houses usually sit at the deep end. Herbert Crescent in Knightsbridge, 450 m², went back to brick with bespoke joinery made in-house. A 400 sq m penthouse at Kensington Olympia was redesigned and rebuilt inside an occupied building. Same team, different scope, very different cost per square metre.
What moves a house renovation cost up or down
The scope sets the starting point. These six things decide where in it your house lands, and whether it leaves it altogether.
Structure, services and heating
- Structure. Every wall you remove needs a steel, an engineer and building control. Opening the back of a house into one room is the commonest reason a refurbishment becomes a structural renovation.
- Electrics and plumbing. A house that needs a rewire and a replumb is a full refurbishment whatever else you do. Both go in before plaster, so they set the sequence.
- Heating. A new boiler is a line item. Underfloor heating or a heat pump with new emitters touches floors, walls and the electrical supply.
Specification, access and neighbours
- Kitchen and bathroom specification. The same room can cost several times more depending on the units, stone, brassware and tiling. Decide it on samples before the price is fixed.
- London access and parking. Skips, deliveries, parking suspensions and scaffolding on the pavement all add labour hours. A mews house costs more to work in than a detached house with a drive.
- Party walls and neighbours. Work on a shared wall needs at least two months' notice; digging near a neighbour's foundations needs one month. No reply within 14 days means a dispute, and surveyors are appointed.
The age of the house runs through all six. A period house that has never been opened up will show you tired joists, old lead pipes and a chimney breast removed without support. That is why the survey comes before the price.
VAT, fees and contingency: the costs outside the builder's quote
A builder's figure is usually construction only. Three more lines turn it into the real budget, and most owners forget at least one.
Design and professional fees. A full refurbishment needs drawings, a specification and someone to run the consents. A structural renovation also needs an engineer, building control and often party wall surveyors. Our guide to architect fees in the UK shows how design fees are usually structured.
Contingency. We advise 5% to 10% of the construction cost, depending on complexity. On an older house you have not opened up, carry more. An unused contingency is the best outcome of a renovation, not a wasted one.
Borrowing? Our guide on how to fund the works covers retentions, further advances and bridging loans.
Planning and building control. You should not normally need planning permission for internal alterations, including removing an internal wall. Building regulations still apply to the structure, electrics, plumbing, heating, windows and the roof.
A listed house needs listed building consent for significant internal work. Extensions, basements, roof changes and street-visible changes in a conservation area need planning. A flat needs the freeholder's licence as well.
This was a full high-end renovation of my Victorian rental apartment in Westminster, just off Sloane Square and Belgravia. The scope included full fit-out: electrics, plumbing, a new bespoke kitchen, and a luxury bathroom refurbishment. Craftex took care of everything and made the process easy. They weren’t the cheapest, but you can tell they really know what they’re doing when it comes to prime London property renovations. The team was professional, organised, and genuinely seemed to care about getting everything right. I was especially impressed with the quality of the finish – the attention to detail really shows in every corner. I’m very happy with the results and would definitely recommend Craftex to anyone looking for reliable, high-quality renovation work in Central London.
Adding space: lofts, extensions and basements
Many prime renovations add floor area at the same time. Each addition has its own cost drivers, on top of the renovation of the existing house.
- Mansard and loft suites. Structure, the roof, the stair and the planning position decide the cost. See our loft conversion service.
- Glazed rear and garden extensions. Glazing, steels and the foundations set the figure. See our house extensions service.
- Basements. Excavation, underpinning, waterproofing and party walls make this the deepest cost per square metre. See our work on basement conversions.
For the design side at the top of the market, read how much luxury home design costs.
How long a house renovation takes
Time costs money on a renovation, because you are paying for a home you cannot live in. These are three of our London homes, each run by one team from design to keys.
A refurbishment that keeps the layout runs in weeks because the sequence is known. A structural renovation runs in months because steels, new services and bespoke joinery each have their own lead time.
Before any of that, allow for design, consents and ordering. Drawings, building control, party wall notices and joinery orders usually take several months. A renovation that starts before the design is fixed is the one that overruns.
How to turn an estimate into a fixed price
Every early figure is an estimate. A fixed price needs three things that do not exist on day one: a survey, drawings and a written scope. Here is how we get there.
- Survey. We walk the house, open up what we can and read the structure, the services and the borough.
- Drawings and specification. Layouts, joinery, the kitchen and bathrooms are agreed on drawings and samples. Long-lead items are ordered before the strip-out.
- Fixed price for the written scope. One figure for everything on the drawings. Changes are agreed in writing and priced before the work is done.
- Programme written into the contract. The date is set after the survey, not guessed at the first meeting.
Want a quick range before the survey? The renovation cost calculator on our service page gives one from the floor area and the scope.
What we take on
We renovate prime houses and apartments across London, as one team that designs, gets the consents, builds and certifies. Around 60% of our labour is in-house, which keeps the joinery and the finishes under our own control. Every project we have delivered has finished ahead of programme and on budget.
A single new bathroom or a light refresh is better served by a good local builder. We say so on the first call. For a whole-house refurbishment or a structural renovation, get a fixed price and we start with the survey.
Before you fix your renovation budget
- Measure the whole floor area, every storey, and pick the scope honestly.
- Decide the kitchen and bathroom specification on samples before the price is fixed.
- Add 20% VAT to every construction and fee line, unless the home has been empty for two years or more.
- Hold a contingency of 5% to 10%, more on an older house you have not opened up.
- Serve party wall notices early: two months for a shared wall, one month for excavation.
- Check the planning position: listed, conservation area, flat or freehold, extension or internal only.
- Allow months for design, consents and ordering before the first day on site.
- Get the price fixed against drawings and a written scope, with changes agreed in writing.