For developers and business owners budgeting design
Architect Fees in the UK: How Architects Charge, by RIBA Stage, and What Changes the Number
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 9 min read
The short answer
Architects in the UK charge in one of three ways: a percentage of the construction cost, a fixed fee for a defined scope, or an hourly rate for open-ended work. The fee is split across the RIBA Plan of Work stages, and what moves it is complexity, planning risk, listed status, scale and the number of changes.
- The RIBA publishes no standard rates. Every fee is negotiated, and ARB guidance expects it in writing before work starts.
- Consultants, surveys, council fees, building control and VAT sit outside the architect's fee. Budget them separately.
- On design and build the design is priced against the build cost as it is drawn, so the consented scheme is the affordable one.
- We quote design per stage after a first meeting, with our construction team costing every option.
Architect fees in the UK are charged in one of three ways. A percentage of the construction cost, a fixed fee for a defined scope, or an hourly rate for open-ended work. The RIBA publishes no standard rate. The figure is negotiated, split across the RIBA stages, and moved by complexity, planning risk, listed status, scale and change.
That is the whole answer for a householder. For a developer or a business owner it is only the start. The architect's fee is one line in a design budget. That budget also carries engineers, a planning consultant, surveys, council fees and the duty-holder roles the law now puts on you.
This guide is written from the builder's side of the table, by the commercial architects London developers bring in with the construction team. It covers the three fee models, what you receive at each RIBA stage and what pushes the number up. It also shows why pricing the design against the build cost changes the economics.
Got a building or a site? Discuss your project and we will tell you what the design route looks like.
Architect fees in the UK: the three ways practices charge
The RIBA, the architects' professional body, describes three ways of calculating a fee. Each suits a different kind of project, and a practice may use more than one on the same job.
| Fee model | How it works | Suits | The risk to you |
|---|---|---|---|
| Percentage of construction cost | A percentage of the build cost excluding VAT, set against an initial budget | Projects whose scope is not yet defined | The fee rises if the design grows; many practices allow a 10% budget variance before adjusting it |
| Lump sum (fixed fee) | One agreed figure for a defined scope, usually split by stage | Projects with a clear brief and scope | A significant change reopens the fee; the sum may carry an allowance for risk |
| Time charge (hourly) | An hourly rate with capped hours, exceeded only with your approval | Feasibility studies and other open-ended work | Open-ended by nature: ask for a time estimate per stage |
The percentage model has a built-in conflict. The architect is paid more when the building costs more. The RIBA's guidance notes the usual fix. Many practices agree a variance of up to 10% of the construction budget before the fee is adjusted. Beyond that, the fee is renegotiated.
For commercial and development work the common answer is a fixed fee per RIBA stage. You know the cost of the next stage before you commit to it, and you can stop at the end of any stage. Structures can also be mixed: a time charge for the feasibility study, then a lump sum for the stages that follow.
Published percentages exist only for householder work. The HomeOwners Alliance guide for 2026 puts architects' fees between 3% and 15% of construction cost, with hourly rates of £50 to £100. Treat those as a householder benchmark, not a commercial one.
RIBA stages: what you get, and roughly when you pay
The RIBA Plan of Work 2020 splits a project into eight stages, from Stage 0 to Stage 7. Most projects run from Stage 1 to Stage 6. A fee proposal that follows the stages tells you what you receive for each payment, which is the only way to compare two quotes.
| No. | RIBA stage | What you receive | Fee usually falls |
|---|---|---|---|
| 0 | Strategic Definition | Confirmation that a building is the best way to meet your requirements | Often a time charge or included in feasibility |
| 1 | Preparation and Briefing | Project brief, site information, surveys, budget and programme | Early stages: the RIBA's example splits 35% of the fee across Stages 0 to 3 |
| 2 | Concept Design | Architectural concept, outline specification, cost plan, pre-application advice | Within the same early-stage share |
| 3 | Spatial Coordination | Design coordinated with structure and services; planning application generally submitted at the end | Within the same early-stage share |
| 4 | Technical Design | All information needed to construct; Building Regulations application; tender package | A further 35% in the RIBA's example |
| 5 | Manufacturing and Construction | Site queries answered, construction quality inspected, change control | The remaining 30% across Stages 5 and 6 |
| 6 | Handover | Building handed over, defects rectified, building manual | Within the same final share |
| 7 | Use | Post-occupancy evaluation, if commissioned | Usually a separate appointment |
Two things in that table matter for your budget. Stages 0 to 3 produce the planning application, so a design appointment that stops at planning is roughly the first third of a full service. Stage 4 is where the money is protected: it produces the technical package the build is priced from.
The RIBA also warns about a habit it sees among private clients. Submitting the planning application near the beginning of Stage 3, before the design is coordinated, brings early clarity on Section 106 and CIL. It also creates project risks, so the RIBA recommends it only for experienced clients.
We explain the application route in how to get planning permission for a development.
What moves an architect's fee up or down
Two buildings of the same size can carry very different design fees. The things that move the number are mostly visible before the appointment is signed.
- Novelty. A repeated floor plate costs less to draw per square metre than a one-off building with a bespoke facade.
- Planning risk. A scheme that needs pre-application meetings, a design review and a committee takes more rounds of drawing than one that fits the local plan.
- Listed buildings and conservation areas. The RIBA notes these are likely to attract higher fees, because more statutory consents are needed.
- Scale. Fees as a share of construction cost fall as the project grows, which is why the householder percentages do not transfer to commercial work.
- Changes. Every change after a stage is approved is redrawn work. Under a percentage fee it also raises the base the fee is calculated on.
- The procurement route. Under a traditional route the architect also administers the building contract on site, which is a Stage 5 fee. Under design and build that role sits with the contractor's team.
The item owners control most is the brief. A brief that fixes the area, the use, the budget and the opening date before Stage 2 removes most of the redrawing that inflates fees.
The extras nobody budgets for
The architect's fee is rarely the whole design cost. The RIBA is explicit that payments to the local authority for planning and building control sit outside the fee, as do travel and printing. VAT is usually charged on top. Beyond that, a commercial scheme needs people and reports the architect does not supply.
| Item | Who provides it | When it lands |
|---|---|---|
| Structural engineer | Separate appointment, or part of a design and build team | Stage 2 for options, Stage 4 for calculations |
| Mechanical and electrical engineer | Separate appointment, or part of a design and build team | Stage 3 coordination, Stage 4 design |
| Planning consultant and planning statement | Separate appointment, or part of a design and build team | Stages 2 to 3 |
| Surveys: measured, topographical, structural, ground, asbestos, ecology | Specialist surveyors | Stage 1, before concept design |
| Reports on the council's local list: daylight, heritage, transport, noise, energy | Specialist consultants | Before the planning application |
| Council fees: planning application, pre-application advice, building control | Paid to the authority | Submission and construction |
| Principal designer and principal contractor duties | Appointed by you in writing | Before construction starts |
| VAT | Charged on the fee | Every invoice |
The duty-holder roles are yours until you appoint someone
The last of those catches commercial clients out. Under CDM 2015 a client with more than one contractor on the project must appoint a principal designer and a principal contractor in writing. Since 1 October 2023 the Building Regulations require the same two appointments. If you do not make them, the law says you hold those duties yourself.
The council's planning fee is set nationally; our guide to planning application fees 2026 gives the current figures.
I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.
Design and build: one fee, one team
Under a traditional route the architect designs, the scheme goes to tender, and the builder prices it. If the tender comes back over the appraisal, the drawings go back to the architect. That redesign is paid for twice: once in fees and once in months.
Under design and build the design and the construction sit in one contract. The design fee is agreed with the team that will build the scheme, and the drawings are costed as they are made. At our practice that means a cost plan beside every option, so the scheme the council approves is the scheme you can afford to build.
How the two routes compare is in design and build vs traditional procurement.
Three projects where design and build set the number
Three Craftex projects show what that looks like. At Allitsen Road in St John's Wood a vacant corner building became four design options in four weeks. Each carried a schedule of accommodation and its own cost plan, compared on buildability, planning risk and viability.
Medusa in Knightsbridge arrived at RIBA Stage 2, a concept with a few visuals. Our in-house team completed the design. Because the same company builds, we could see the cost of every design decision and offer more affordable solutions. The 180 sq m clinic was designed and built across four floors in 17 weeks.
Portsoken House in Aldgate was designed by our in-house team and built by it. The result was 1,550 sq m of premium offices, delivered in seven months around occupied tenants.
How we quote design
We do not quote design as a percentage of anything. Design is agreed per stage and quoted after a first meeting, once we have seen the building and the brief. Design commissions start at £15,000 and construction runs from £100,000 under the same contract.
A workplace brief that starts with headcount and desks goes to our office design and space planning team. Private houses go to our high-end residential architects.
How to brief an architect so the fee is right first time
A fee proposal is only as good as the brief behind it. Most fee disputes start with a scope that was never written down. These six steps keep the number honest.
- Write the brief before you ask for a fee. Area, use, budget, opening date, and what the scheme must earn. A practice can only price a scope it can read.
- Ask for the fee by RIBA stage. One figure per stage, with the deliverables listed, so you can stop at any stage and compare quotes line by line.
- Ask what is excluded. Engineers, planning consultant, surveys, council fees, principal designer duties, VAT. Every exclusion in writing, before Stage 1.
- Fix the change procedure. What counts as a change, who approves it and how it is priced, so the fee cannot drift.
- Check the register. Only a person on the ARB register may practise or carry on business under a title containing the word architect.
- Get the build cost in the room early. A builder's cost plan beside the Stage 2 options is the cheapest insurance against a scheme that cannot be built on the number.
Put the terms in writing
Written terms are not optional. ARB guidance supporting the 2025 Architects Code expects clear written terms before work starts. They should name the parties, the scope, the fee or the method of calculating it, responsibilities, liability and how disputes are resolved. Amendments are recorded in writing too.
Our guide to how to choose an architect in London covers the questions to ask at the first meeting. The checklist below is the short version.
Craftex has worked this way since 2016, with around 60% of our labour in-house and every project delivered ahead of programme and on budget. Have a building or a site in London? Discuss your project and you will get the design route and a costed first option before you commit to a stage.
Before you sign an architect's appointment
- Brief written: area, use, budget, opening date, what the scheme must earn
- Fee quoted per RIBA stage with the deliverables for each
- Every exclusion listed: engineers, planning consultant, surveys, council fees, principal designer, VAT
- Change procedure and approval route agreed in writing
- Architect's ARB registration checked
- Builder's cost plan beside the Stage 2 options
- Principal designer and principal contractor appointments planned before site