For clients about to sign a building contract
JCT Contracts Explained: The Types of JCT Contract and Which One to Use
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read
The short answer
A JCT contract is a standard-form building contract published by the Joint Contracts Tribunal. Which one you need depends on who designs the work, how complete and complex the design is, and whether a consultant will run the contract.
- Minor Works for simple jobs where the client's drawings and specification define the work.
- Intermediate or Standard Building Contract for traditional work as it grows in size and complexity.
- Design and Build where the contractor completes the design and builds it for one sum.
A JCT contract is a standard-form building contract published by the Joint Contracts Tribunal (JCT). The form you need depends on who designs the work, how complete the design is and who will administer the contract. For most commercial schemes the choice falls between Minor Works, Intermediate, Standard Building Contract and Design and Build.
This guide is for clients, funders and advisers who have been handed a JCT form to sign. We are a construction company in London that builds from £100,000 to £10M and above. We read these forms as the party that has to build to them. Holding a draft now? Get a free pre-construction review.
What a JCT contract is
The Joint Contracts Tribunal publishes standard forms of building contract. The parties choose a form and complete it for the project, instead of drafting a contract from nothing.
Each form has three parts. The agreement, or articles, names the parties and the price. The conditions are JCT's standard text on design, time, payment, insurance and termination. The contract particulars hold the project's own settings: dates, damages for delay, retention and the defects period.
JCT launched its 2024 edition with Design and Build on 17 April 2024 and has issued the other families since. The table in the next section shows where each form stands on JCT's own pages, checked on 29 October 2026.
Every JCT form is also written to meet the Construction Act, the Housing Grants, Construction and Regeneration Act 1996. It sets minimum rules on payment and adjudication for construction contracts. We set them out in the last section.
Types of JCT contract compared
JCT publishes more than a dozen families. Most commercial work uses five of them. The table gives the use of each form and its 2024 status, as JCT lists it.
| Contract | What it is for | 2024 edition |
|---|---|---|
| Minor Works (MW, MWD) | Simple work that the client's drawings, specification or work schedules define | MW and MWD 2024, May 2024 |
| Intermediate (IC, ICD) | Traditional work that is more involved, with provisions for named specialists | IC and ICD 2024, July 2024 |
| Standard Building Contract (SBC/Q, SBC/AQ, SBC/XQ) | Larger or complex traditional work, with, approximate or without quantities | Listed available, October 2024 |
| Design and Build (DB) | One contractor completes the design and builds for a lump sum | DB 2024, 17 April 2024 |
| Major Project (MP) | Large-scale projects, for employers who regularly procure and contractors able to take more risk | MP 2024 |
| Management Building Contract, Construction Management | Employer appoints a management contractor or construction manager, who runs separate works contracts for a fee | MC, CM/A and CM/TC 2024 |
| Prime Cost, Target Cost | Open-book pricing: cost plus a fee, or a target cost | PCC 2024, TCC 2024 |
| Measured Term, Repair and Maintenance | A steady flow of maintenance and minor works, or a set programme of repairs | MTC 2024, RM 2024 |
| Home Owner (HO/B, HO/C and HO/CA) | Work to a home the client lives in or will live in | 2021 edition, current |
| Pre-Construction Services Agreement (PCSA) | Contractor advises on design and cost before the building contract is signed | PCSA 2024 |
Value limits and the pre-construction agreement
JCT's own pages give no value limit for Minor Works or Intermediate. Scope and complexity decide, as the next section shows. The pre-construction agreement has its own guide: pre-construction services agreement.
If your form is not in this table, or is heavily amended, a construction company in London can price it as written. Send us the form, the amendments and the drawings.
How to choose the right JCT contract
JCT publishes a guide to selecting a main contract. Its flowchart dates from the 2016 edition, and the 2024 forms keep the same family names. These are its questions, in a working order.
- Is the work to your own home? JCT's Home Owner contracts cover a dwelling the client occupies or will occupy. HO/B is for work with no consultant overseeing it, HO/C and HO/CA for work with one.
- Do you want the contractor to employ works contractors under your direction? That is the management route: the Management Building Contract, or Construction Management where you appoint the trade contractors yourself.
- Will the contractor complete the design? If so, the route ends at the JCT Design and Build Contract. For small jobs there are contractor's design versions: MWD and ICD.
- Is the design fully developed, with detailed documents? Traditional forms assume it is. Do you need a bill of quantities? Then choose the Standard Building Contract with Quantities. If the work is to be measured afterwards, choose approximate quantities.
- Is the work complex, or heavy in building services? JCT's guide then points to the Standard Building Contract. If not, and detailed procedures or named sub-contractors are needed, it points to Intermediate. If neither applies, it points to Minor Works.
- Who will administer the contract? Traditional forms expect a consultant, such as an architect or contract administrator. Repair and Maintenance is written for employers who need none.
When the design is not ready
JCT's guide shows the pre-construction agreement can sit in front of the Standard Building, Intermediate, Design and Build and Major Project contracts. The contractor then helps finish the design before the price is fixed.
Choosing a form is also choosing a procurement route. Our guide to design and build vs traditional procurement covers that choice. If no price can be fixed yet, the open-book alternative is in our guide to the cost plus contract.
We build mainly as a design and build main contractor. At Portsoken House in Aldgate our in-house team designed 1,550 m² of offices. We built them in seven months, around tenants who stayed in the building.
JCT Minor Works and Intermediate contracts
These two are the forms people search for most. JCT sets no value limit for either, so the test is scope: how simple the work is, and how complete the client's design information is.
| Point | Minor Works (MW) | Intermediate (IC) |
|---|---|---|
| Design information | Drawings, a specification or work schedules from the client | Drawings, plus bills of quantities, a specification or work schedules |
| Price and payment | Lump sum, monthly interim payments | Lump sum, monthly interim payments |
| Named specialists | Not a stated feature | Provisions to cover them |
| Contractor's design version | MWD | ICD |
Both forms leave the client's design with the client. In MWD and ICD, the contractor takes a defined designed portion. That is a smaller step than a full design and build contract.
A job that looks simple on paper can still be services-heavy. A fit-out with new mechanical plant, or a refurbishment that needs named specialists, may belong under Intermediate or the Standard Building Contract. If the drawings are still moving, none of these forms is a good fit yet.
Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.
JCT or NEC: the difference for a client
NEC is a separate family of contracts. Its NEC4 Engineering and Construction Contract (ECC) is written for engineering, building and construction work. The table sets it next to JCT in plain terms.
| Point | JCT | NEC4 ECC |
|---|---|---|
| Shape | A family of separate forms, chosen by who designs and how complex the work is | One contract with six main options, A to F, chosen by pricing method |
| Who runs it | A contract administrator or employer's agent, depending on the form | A project manager acting for the client |
| Early warning | 2024 forms add collaborative working provisions | Contractor and project manager must give early warning of matters that could affect price or time |
| Changes | Variations, with listed causes of extra time and extra money | Compensation events, which the contractor generally has to notify within eight weeks |
| Pricing | Lump sum forms, plus Prime Cost and Target Cost | Priced, target, cost reimbursable or management options |
Neither is better. Use the form your funder, adviser or public client requires, and one you have a team to administer. The client-side role is explained in our guide to the employer's agent.
Before you sign a JCT contract
Read the contract particulars first. They hold the dates, the damages for delay, the retention percentage, the defects period and the insurance options. Both sides complete them, so they are the part you can negotiate.
Then read the amendments. Ask who drafted them and what each one moves. A contractor that accepts every amendment without changing its price has either not read them or plans to recover the cost in claims.
The payment rules to check
The Construction Act sets the payment minimum for a construction contract. A contract with a residential occupier is excluded. These are the points to check.
- Payment cycle. The contract needs an adequate mechanism for what is due and when, and a final date for payment. Payment by instalments is a right unless the work will take under 45 days.
- Payment notice. The payer, or the payee, gives it no later than five days after the payment due date.
- Pay less notice. A payer who wants to pay less gives notice before the final date for payment. The notice period is the one the parties agree, or the Scheme for Construction Contracts sets.
- Adjudication. Either party can give notice at any time. The adjudicator then decides within 28 days of referral, unless the time is extended.
Retention, variations and the CDM roles
Two other documents sit alongside the contract. Retention in construction explains the money held back and when it is released. Variations in construction contracts explains how changes are instructed and valued.
Where more than one contractor will work on the project, the client must appoint a principal designer and a principal contractor. It must do so in writing, before the construction phase begins. Our guide to principal contractor vs main contractor sets out who holds each role.
Use this list before you sign. If you want a second pair of eyes on the form and the drawings, get a free pre-construction review. Send them together. Already have a quote? Send it to us. We'll beat it.
- Contract particulars complete: dates, delay damages, retention, defects period, insurance
- Every amendment listed against the JCT standard, with who asked for it
- Design responsibility clear: client's design, contractor's designed portion, or both
- Payment cycle, payment notice and pay less notice dates in the contract
- Retention percentage and release dates agreed
- Variations: how they are instructed in writing and how they are valued
- Principal designer and principal contractor named in writing
- Administrator named: architect, contract administrator or employer's agent