For developers and occupiers signing a building contract
The JCT Design and Build Contract 2024: A Client's Guide
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
The JCT Design and Build Contract 2024 is the standard UK contract where one contractor completes the design and builds the works for a lump sum. JCT launched it on 17 April 2024.
- You set out what you want in the Employer's Requirements; the contractor answers with its Proposals.
- The contractor is responsible for completing the design, so what you leave vague, it designs and prices.
- Payment is a lump sum, paid by interim stages or periodic payments set in the Contract Particulars.
- DB 2024 cut the Employer's interim extension of time review from 12 to 8 weeks.
The JCT Design and Build Contract 2024 (DB 2024) is the standard JCT form where the contractor completes the design and carries out the works. The price is a lump sum. JCT launched the 2024 edition on 17 April 2024.
We are a construction company in London that delivers projects under one design and build contract, so this guide is written from the client's side. It covers the documents, design responsibility, payment, time and the 2024 changes, in plain words, without reproducing the contract. Get a free pre-construction review of your draft before you sign.
How the JCT design and build contract fits together
DB 2024 is a lump sum contract. The client is called the Employer. These are the documents that make it up. Still choosing a form? Our guide to the types of JCT contract compares them.
| Document | Who writes it | What it does |
|---|---|---|
| Articles of Agreement | Both parties | Names the parties, the Employer's Agent, the principal designer and principal contractor, and the contract sum |
| Contract Particulars | Both parties | The project settings: dates, damages for delay, payment method, insurance, retention, defects period |
| Employer's Requirements | The client and its design team | What must be built, to what standard, with how much design already done |
| Contractor's Proposals | The contractor | How the contractor will meet the requirements |
| Contract Sum Analysis | The contractor | Breakdown of the lump sum, used to value changes and stage payments |
| Conditions | JCT standard text | The rules on design, time, money, quality, insurance, termination and disputes |
The Employer's Requirements are the most important document you write. Anything left vague, the contractor will price and design to the cheapest compliant answer. Anything over-specified, you pay for, including design risk you meant to pass on.
Who carries design responsibility
Under DB the contractor is responsible for completing the design. Law-firm commentary on DB 2024 reports that the standard form sets that duty at reasonable skill and care, and excludes fitness for purpose. It is not an absolute promise that the building will suit its purpose.
Many clients amend that duty, and contractors price the amendment. Two points catch clients out.
- Design already done by your team. If your architect has taken the design far before the contractor joins, the contract must say who is responsible for it. The standard form does not make the contractor check and adopt it automatically.
- Novation. It is common to transfer your architect and engineers to the contractor, so the same designers carry on. It keeps continuity, but your former designers now work for the contractor.
Want a construction company in London to read the draft with you before the price is fixed? This is the stage to ask.
Payment, retention and the contract sum
DB is a lump sum contract. JCT describes the payment structure as a lump sum with interim stage or periodic payments. The Contract Particulars say which applies.
Each interim payment follows the Construction Act regime. The contract needs an adequate payment mechanism and a final date for payment. A payment notice is due within five days of the due date. The paying party can issue a pay less notice, stating the sum and how it is calculated.
The retention percentage, the defects period and the rate of damages for delay are set in the Contract Particulars. So they are yours to negotiate.
Changes are valued using the Contract Sum Analysis where it applies. If you expect to change the scope, ask for a detailed breakdown at tender. It is your best protection when a change is priced.
Great company to work with as always. Super flexible at dealing with evolving requirements and fast deployment and execution.
Time: extensions and damages for delay
The contractor must finish by the completion date or pay the agreed damages for delay. It can claim extra time for listed causes outside its control, called Relevant Events. It can claim money for a separate list, called Relevant Matters.
DB 2024 changes this in several ways.
- The Employer now has 8 weeks, down from 12, to decide an interim extension of time.
- Epidemics are a new Relevant Event.
- The change in law event is wider and takes in government guidance.
- The antiquities provision now also covers asbestos, contaminated material and unexploded ordnance found on site.
That last point matters in London. Older buildings and brownfield sites often turn up asbestos and contamination. Decide in the contract who carries that risk, rather than on the first day of strip-out.
What changed in JCT DB 2024 compared with 2016
JCT's author says DB 2024 preserves the risk allocation between the parties. The changes alter how the contract is run, and some of them move cost.
| Area | DB 2016 | DB 2024 |
|---|---|---|
| Notices | Mostly by post or hand | Email provisions for standard and critical notices |
| Interim extension of time review | 12 weeks | 8 weeks |
| Epidemics | Not a Relevant Event | New Relevant Event |
| Asbestos, contamination, unexploded ordnance | Not expressly covered | Within the antiquities provision |
| Building Safety Act | Not reflected | New Article for the principal designer and principal contractor under Part 2A; cross-undertakings on duties |
| Collaborative working | Optional extra provision | In the main contract |
| Sustainability | Optional | Clause in the main contract |
| Disputes | Negotiation optional | Notification and negotiation clause in the main contract |
| Insolvency | Older grounds | New grounds under 2020 insolvency law |
| Fluctuations | Printed in the contract | Options published on the JCT website |
Your Employer's Agent and the contractor's team need to work to the 2024 rules, not habit.
Building Safety Act duties in the contract
Since the Building Safety Act 2022, Part 2A of the Building Regulations puts duties on clients, designers and contractors. DB 2024 reflects that.
- It records who is appointed principal designer and principal contractor for Building Regulations purposes, in a new Article.
- Both parties undertake to comply with their duties under the CDM Regulations and Part 2A.
- The client can certify that its CDM appointees also hold the Part 2A roles, instead of appointing separate ones.
Higher-risk buildings bring a separate approval regime. For new buildings, gov.uk sets 18 m or 7 storeys, with two or more residential units, or a care home or hospital. If your scheme is one, ask your adviser whether the standard form needs amending. Our guide to Gateway 2 and second staircases explains the regime.
Common amendments clients ask for
These are negotiated deal by deal. Each moves risk, and each has a price.
- A stronger design duty, sometimes up to fitness for purpose.
- Contractor responsibility for your earlier design, after checking it.
- Transfer of your design team to the contractor.
- Collateral warranties for funders, buyers and tenants.
- Clear allocation of ground, contamination and existing-structure risk.
- Tighter limits on what counts as a Relevant Event.
A contractor who accepts everything without changing the price has either not read the amendments, or plans to recover the cost in claims.
When design and build is the right contract
Design and build suits clients who want one party responsible for design and construction. It gives one lump sum and one point of contact. It works best when the brief is settled before signing.
If the design is still moving, use a pre-construction services agreement first, then DB. The contractor helps develop the design before the price is fixed.
If no fixed price makes sense yet, the alternative is an open-book route. Our guide to the cost plus contract in UK construction covers the JCT Prime Cost contract, target cost and GMP.
At Medusa in Knightsbridge, we joined at RIBA Stage 2 with a concept the budget could not support. We adapted the design until the vision and budget matched. The 180 m² spa and beauty clinic was then designed and built across four floors in 17 weeks.
This guide covers one form. For the other JCT contracts, see how to choose between them. The Standard Building Contract, for example, assumes the design is already developed in detail. The wider choice is covered in design and build vs traditional procurement. The client-side role that runs the contract is explained in our guide to what an Employer's Agent does.
Before you sign a JCT design and build contract
We are a construction company in London and a design and build contractor. We also act as client-side construction project managers when a client wants someone to run the contract. We take on construction projects from £100,000. Get a free pre-construction review and send us the draft contract with the brief.
Pre-signing checks
- Employer's Requirements complete, with clear performance standards.
- Responsibility for any earlier design written in.
- Payment method, retention, defects period and delay damages set.
- Asbestos, contamination and existing-structure risk allocated.
- Principal designer and principal contractor named.
- Contract Sum Analysis detailed enough to value changes.
- Collateral warranties agreed for funders and tenants.
- Employer's Agent appointed and briefed on the 2024 notice rules.