Skip to content
Request a callbackCallback

For developers procuring a main contractor

PCSA: What a Pre-Construction Services Agreement Covers

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 8 min read

Printed construction drawings on a desk with drafting tools and a protractor

The short answer

A PCSA (pre-construction services agreement) pays a main contractor to help develop the design, programme and price before the building contract is signed. It is the first stage of a two-stage tender.

  1. You fix overheads, profit and the basis of preliminaries in stage one.
  2. The services schedule should list named outputs with dates, not general advice.
  3. You should keep a licence to use the work product and be free not to proceed.
  4. It pays off on schemes with real risk: basements, retained façades, tight sites.

A PCSA is a pre-construction services agreement. It pays a main contractor to help develop the design, programme and price before the building contract is signed.

In construction it is the first stage of a two-stage tender, with the contractor working alongside your design team.

On most London schemes the builder's knowledge arrives too late. The design is finished, the tenders come back high, and the savings now mean redesign. A PCSA fixes the timing. You buy the contractor's input while it can still change the scheme, not later in variations and delay.

Our pre-construction services page shows what we review at this stage: buildability, cost plan and programme. Have a scheme in design? Get a free cost and buildability review.

What a PCSA means in construction

PCSA and pre-construction services agreement are the same thing. It is a contract for services, not for building work. The contractor is paid to advise, programme and price. You get a design that can be built at the price you were given.

The JCT publishes a standard form, the Pre-Construction Services Agreement (General Contractor), now in a 2024 edition. Earlier editions came out in 2016 and 2011. JCT describes it as designed for appointing a contractor to carry out pre-construction services under a two-stage tender process.

JCT lists it for use with its 2024 Standard Building Contract, Design and Build Contract, Major Project Construction Contract and Intermediate Building Contract. It works whether or not the contractor will design any of the building. Our guide to JCT contract types explains how to choose between those forms.

How a PCSA fits a two-stage tender

A single-stage tender asks contractors to price a finished design. That works when the design really is finished. On most London schemes it isn't. Basements, party walls, façade retention, utilities and approvals all carry unknowns that only a builder will price honestly.

Two-stage procurement splits the job. Our guide to two-stage tendering compares it with a single-stage tender.

Stage one and stage two compared
Stage one (PCSA)Stage two (building contract)
What is agreedOverheads and profit, preliminaries or their basis, the PCSA fee, the route to a contract sumThe full contract sum, programme and risk allocation
ContractA PCSA (JCT publishes a standard form) or a bespoke agreementA building contract, often design and build
Design statusBeing developed towards technical designComplete enough to price, with defined contractor's design portions
How the price is builtOpen book: packages tendered with you and your cost consultantAgreed from the stage one tenders
Your exitYou can usually stop and pay only the PCSA feeCommitted to build

Parties often amend the standard form heavily or write their own. Either way, the same few clauses decide whether it protects you. To see how two-stage compares with other routes, read design and build vs traditional procurement.

What a PCSA should deliver

The services schedule is the heart of the agreement. If it says "provide pre-construction advice", you have bought nothing you can enforce. In the JCT form the pre-construction services sit in Annex B. Ask for named outputs, with dates.

A useful schedule for a London residential or mixed-use scheme usually includes:

  1. Buildability reviews. Written comments on the architect's and engineer's drawings at agreed stages.
  2. A construction programme. From start on site to completion, with the logistics plan behind it: crane, hoist, deliveries, road closures.
  3. A cost plan the contractor stands behind. Updated at each design stage and reconciled with your own consultant's numbers.
  4. Package tenders run open book. Shortlist, tender documents, returns and a recommendation for each package.
  5. Surveys and investigations. Ground, utilities, asbestos, opening-up and condition surveys of neighbouring buildings.
  6. A risk register. With owners, costs and the decision each risk needs.
  7. Input to approvals. Building control, the fire strategy, party wall notices, highways licences and the construction logistics plan.
  8. A stage two proposal. The contract sum, programme, clarifications and exclusions.

That list is longer than many contractors offer. It is also what turns a PCSA from goodwill into a priced plan.

Want these outputs priced on your scheme? Our pre-construction services put a cost and buildability review in front of you before you sign anything. Get a free cost and buildability review.

The terms that matter most

The fee and how it is earned

There is no standard PCSA fee. It follows the services schedule and the team time it needs. In the JCT form the fee, rates, additional payments and reimbursable expenses sit in Annex A.

Fees are paid as a lump sum, monthly or against milestones. Milestones tied to outputs keep both sides honest: programme issued, packages tendered, proposal submitted. Agree whether the fee is credited against the contract sum if stage two goes ahead.

Overheads, profit and preliminaries

These are the numbers you buy certainty on in stage one. Fix the overheads and profit percentage. Fix the preliminaries as a schedule of items with rates, not one line. Then a longer programme at stage two can be checked line by line.

Design responsibility

Under a PCSA the contractor comments on design. It should not quietly become responsible for design it never produced. If it does produce design, say so in the agreement. Temporary works, a basement sequence or a cladding package are examples.

The JCT form has a clause on liability for design work and a section on professional indemnity and public liability insurance. Add the standard of care and the cover that go with any design the contractor takes on.

Who owns the work product

You need a licence to use everything the contractor produces, whether or not you proceed. Programmes, surveys, logistics plans and tender documents all count. Without it, walking away at stage two means starting again. The JCT form deals with use of the contractor's information in its own section.

Exit and no obligation to proceed

The agreement should say you are not obliged to award stage two, and what you pay if you stop. The JCT form covers termination at will and the payment that follows. It should also deal with drift. Set a long-stop date, after which either side can end the agreement.

Early works

Demolition, enabling works or a basement dig sometimes need to start before the price is fixed. That is a separate instruction with its own price and scope. It never "just starts" under the PCSA.

Payment and disputes

A PCSA is a contract like any other, with payment applications, due dates and notices. The JCT form has sections for each, and for adjudication.

Under the Construction Act, an agreement to do design work or advise on building is a construction contract. It must relate to construction operations (section 104(2)). A party to a construction contract can refer a dispute to adjudication (section 108(1)). A PCSA that covers design or building advice will usually fall within that.

I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

Taron Papoyan, Google reviewSee all reviews on Google

A PCSA or a letter of intent

Letters of intent get people moving before a contract is signed. They are a different tool.

PCSA and letter of intent compared
PCSALetter of intent
PurposePays for advice, programme and pricingAuthorises limited works or orders while a contract is agreed
ScopeDefined services scheduleDefined works, usually capped by value or time
Typical riskWeak schedule, unclear design liabilityWorks run on with no contract and no cap
Use it whenYou want a contractor's input during designA long-lead item or early works can't wait

The common failure is a letter of intent that runs for months past its cap. Both sides then argue about what was agreed. If the contractor will do real work before the contract, a PCSA plus a separately priced early works instruction is cleaner.

Stage two is often a design and build contract. Our guide to the JCT Design and Build Contract explains the clauses that follow a PCSA.

When a PCSA is worth it

Worth it when the scheme has real construction risk. Think basements, retained façades, tight urban sites and occupied neighbours. Conversions of existing buildings qualify too, where nobody knows what is behind the plaster. So do higher-risk residential buildings that need the Building Safety Regulator's approval before work starts.

Less useful when the design is complete, the building is simple and plenty of contractors will price it in one stage.

We saw why early builder input matters on Slingsby Place in Covent Garden. The building was taken back to its shell behind retained façades. A tower crane stood inside the footprint, with neighbours on every side. The works were led by Martin Hickey, now our Preconstruction Director, as Project Director.

The temporary works design for the façade retention was signed off before demolition. Decisions like that only get made in time when a contractor is at the table during design.

How we work before the build contract

Earlier questions come first: whether a site works, what it could hold and how long it could take. Those sit in a development viability assessment.

Because design and construction sit under one roof, the team that prices the scheme is the team that builds it. On a design and build route, that closes the gap between what was drawn and what was priced. Already have a design team? Our construction project management service can run the two-stage process on your side.

For the bigger picture, read our construction project planning guide. Taller residential schemes should also read our guide to Gateway 2 and the second staircase rule. It explains the approval periods to build into the stage one programme. Ready to test the route? Get a free cost and buildability review and send the drawings.

Before you sign a PCSA

  • The services schedule lists outputs and dates, not general advice.
  • Overheads and profit are fixed as percentages; preliminaries are itemised.
  • The fee basis, payment triggers and any credit against stage two are written down.
  • Design responsibility is clear, with PI cover where the contractor designs.
  • You have a licence to use all work product if you don't proceed.
  • There is no obligation to award stage two, and there is a long-stop date.
  • Open-book package tendering is described: who sees the returns and how they compare.
  • Early works, if any, are instructed separately with their own price.

Frequently asked questions

What does PCSA mean in construction?

PCSA stands for pre-construction services agreement. It is the contract that appoints a main contractor during design, before the building contract is signed, usually as the first stage of a two-stage tender.

Is a PCSA legally binding?

Yes. It is a contract for services: the contractor must provide what the services schedule describes and you must pay the agreed fee. It does not commit either party to the construction works unless it says so.

Who pays for pre-construction services?

The client, usually the developer, pays the PCSA fee. Agree up front whether it is credited against the contract sum if the contractor is appointed for stage two.

What is a PCSA fee based on?

The services schedule and the team time it needs. The JCT form sets out the fee, rates, additional payments and reimbursable expenses in Annex A. A fee can be a lump sum, paid monthly or against milestones, and may be credited against the contract sum.

What is the difference between a PCSA and a letter of intent?

A PCSA pays for advice, programming and pricing during design. A letter of intent authorises limited works or orders while the main contract is agreed. A letter of intent that runs on without a cap is a common source of disputes.

Can I walk away after the PCSA?

Usually yes. A well-drafted PCSA says you are not obliged to award stage two, sets out what you pay if you stop, and gives you a licence to use what the contractor produced.

Which JCT contracts can a PCSA be used with?

JCT lists its PCSA 2024 for use with the 2024 Standard Building Contract, Design and Build Contract, Major Project Construction Contract and Intermediate Building Contract. JCT says it can be used whether or not the contractor will be responsible for any design work.

When should a PCSA start?

During design development, early enough for the contractor's comments to change the design before it is fixed. Starting after the technical drawings are finished turns the agreement into a pricing exercise.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Have a scheme in design and no contractor yet?

Send us the drawings. We review the cost and buildability first, free, and tell you whether a two-stage route makes sense for the scheme.

WhatsApp us