The Employer's Agent Role: Duties, Limits and Fees

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 9 min read

Ground slab poured on a London new-build site, with materials stacked ready for the frame

The short answer

An employer's agent is the person a client names in a JCT design and build contract to act for it under that contract. They issue instructions and payment notices, value changes, and handle completion, defects and the final account, so the contractor deals with one authorised voice.

  1. The agent acts for the client on the contract, not as a neutral certifier.
  2. Site possession, paying the contractor and the liquidated damages notice stay with the client.
  3. A project manager leads the whole project; the agent runs the signed contract.
  4. Fees are agreed scheme by scheme, so compare what each fee buys, not the headline.

An employer's agent is the person a client names in a design and build contract to act for the client under it. The role covers instructions, payment notices, changes, completion and defects, so the contractor deals with one authorised voice.

Search "employers agent" and the architect, project manager and quantity surveyor all get mixed together. They are separate roles. We act as employer's agent on schemes we do not build, on your side of the contract.

On those schemes, every variation is priced and agreed in writing before the work starts. Where we build, your own independent agent gets everything from us. Setting one up? Discuss your project and we will talk it through.

The employer's agent role in plain terms

The JCT Design and Build Contract is written for a client who appoints someone to act for it. RICS practice information calls that person the employer's agent. The contract names them, and the contractor takes its instructions from them.

The agent is the client's voice on the contract, not a neutral referee. They handle the paperwork, the money and the changes from signing to the final account. The client still makes the decisions that matter: what to build, what to pay for and what to change.

The contract suits jobs where the contractor completes the whole design. Where the contractor designs only parts, RICS points to other JCT forms and a contract administrator. Check which applies to your scheme before you appoint anyone.

What an employer's agent does at each stage

The work changes with the project stage. This is what an employer's agent typically handles.

Typical employer's agent tasks by stage
StageTypical tasks
Before tenderHelp prepare the Employer's Requirements, advise on procurement, set up the tender
TenderIssue documents, answer queries, analyse bids and the Contractor's Proposals, report on value and risk
ContractAgree amendments with the client's lawyer, complete the contract settings, check bonds, insurances and warranties
ConstructionReceive applications, issue payment and pay less notices, value changes, run progress meetings, review contractor design
CompletionInspect, deal with practical completion, track defects, manage the rectification period and retention
Final accountAgree the final contract sum and close out

RICS treats the work after the contract is signed as the core role. Tender-stage work is an extra, and a quantity surveyor is often appointed separately for it. Read the appointment, not the job title.

Some schemes appoint the contractor first under a pre-construction services agreement. The agent's contract role then starts when the building contract is signed.

Duties under a JCT design and build contract

The contract names the agent. RICS describes it as giving that person full authority to act for the client, unless the client says otherwise by notice. That covers applications, consents, instructions, notices, requests and statements. Which JCT form fits your job is covered in our guide to JCT contract types.

Four duties follow from that authority.

  1. One named person. RICS says the contract should name one individual, with their firm named alongside. Other consultants have no authority to instruct the contractor.
  2. Instructions in writing. Every instruction goes out in writing, so nothing on site depends on memory.
  3. Payment notices. The agent, or another person the client authorises, can give the payment notice and the pay less notice.
  4. Completion and defects. The agent inspects before practical completion, tracks defects through the rectification period and checks the final account.

Three things stay with the client: giving possession of the site, paying the contractor, and the notice about deducting liquidated damages. Keep those three on your own list from day one.

I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

Taron Papoyan, Google reviewSee all reviews on Google

How the agent handles a change, step by step

Changes are where an employer's agent earns the fee. The contractor developing its own design is not a change; a change to your requirements is. This is a typical sequence.

  1. The client wants something different. The agent checks whether it is a real change to the Employer's Requirements.
  2. The agent asks for a quotation first, where time allows, so the cost and time effect are known.
  3. The client decides, with the agent's advice on value and programme.
  4. The agent issues the instruction in writing, in the form the contract requires.
  5. The change is valued, using the contract sum breakdown where it applies, and paid in the next interim payment.
  6. Any time effect is assessed through the extension of time process, within the 2024 deadlines.

Skipped steps cause disputes. A verbal instruction on site with no agreed price is the most common start of a final account argument. On the schemes we run, no change reaches site until its price is agreed in writing. Ask any agent you interview how they stop verbal instructions.

Why the employer's agent is not independent

On a traditional JCT contract, the architect or contract administrator certifies payment and completion. RICS calls that an impartial role, and it only exists once a contract does.

Design and build works differently. The employer's agent acts for the client, effectively as if it were the Employer. RICS adds that when the agent certifies or decides, it should act impartially.

What that means in practice:

  1. For the client. The agent is on your side and reports to you. The contractor can dispute its decisions as it would yours, including by adjudication.
  2. For the contractor. There is no neutral referee. If the agent also certifies, the appointment and contract must say so.
  3. For lenders. Because the agent is not independent, funders generally appoint their own monitoring surveyor.
  4. For conflicts. An agent cannot act where your confidential information could reach the contractor. That is why a builder cannot be your agent on its own job.

The choice of route sits upstream of this. Our guide to design and build vs traditional procurement shows how the agent's position changes with it.

Employer's agent, project manager and quantity surveyor compared

Several roles sit on the client's side of a building contract. They are easy to mix up.

Client-side roles compared
RoleActs forPositionMain job
Employer's agentThe clientActs as the Employer, impartial when certifyingRun the design and build contract, payments and changes
Project managerThe clientLeads the team for the clientLead the whole project, team, programme and decisions
Quantity surveyorThe clientAdvises on costCost plans, tender pricing, valuations and the final account
Contract administrator or architectThe contractImpartial, exists once the contract doesCertify payment, completion and extensions on traditional contracts
Monitoring surveyorThe lender or investorIndependent of the borrowerReport to the funder on cost, programme, quality and risk
Clerk of worksThe clientInspects for the clientInspect the quality of work on site

The employer's agent and the project manager are the pair people confuse. A project manager often starts at inception and leads the team. The agent's contract role starts when the contract is signed. One firm can hold both appointments.

A quantity surveyor often does the cost work behind the agent. Many employer's agents are quantity surveyors themselves. The lender's role is covered in our guide to the development monitoring surveyor.

The 2024 JCT changes an employer's agent works to

The JCT Design and Build Contract 2024 changed several things an agent handles every week.

  • Most notices can now go by email. Check the contract particulars for whether the parties have opted in to email for default and termination notices.
  • An email notice is deemed received on the next Business Day after it is sent. Send notices early.
  • The client's period to decide an extension of time fell from a maximum of 12 weeks to 8 weeks.
  • Matters likely to lead to a dispute must now be notified, and named senior people meet to negotiate. Adjudication stays available under the Construction Act.
  • The contract has a new Article on who is appointed principal designer and principal contractor for Building Regulations purposes.

An agent working from 2016 habits will miss deadlines that now run shorter. The wider changes are in our guide to the JCT Design and Build Contract 2024.

How employer's agent fees are agreed

There is no standard employer's agent fee. Fees are agreed scheme by scheme, and two proposals with the same headline can buy very different services. These points move the fee most.

  1. Scope. Post-contract administration only, or tender and contract preparation as well.
  2. Size and length. A longer build means more valuations, meetings and notices.
  3. Time on site. Weekly visits cost more than monthly ones, and find problems sooner.
  4. Cost work. Whether a quantity surveyor's valuations and final account are included.
  5. Certification. Whether the agent also certifies, which the appointment must say.

Ask for each proposal as a written list of services, then compare them line by line. We do not publish fees; we agree them once we have read your brief.

Want that list for your scheme? Ask our employer's agent team to review your scheme. Our guide to development management fees explains how the wider client-side roles are paid.

Choosing an employer's agent: who acts and what to check

Most employer's agents are quantity surveyors, building surveyors or project management firms. The role is mostly about contracts, money and change. These five points matter more than the profession.

  1. Design and build experience. The agent must judge contractor design against your requirements without redesigning it.
  2. Cost control. Change valuations, interim payments and the final account are where money is won or lost.
  3. Notice discipline. A missed pay less notice or extension of time deadline costs real money.
  4. Time on site. An agent who visits once a month learns about problems from the payment application.
  5. No ties to the contractor. No commercial links with the firm being administered.

Red flags when appointing

  • No experience of the contract edition you are signing.
  • A fee so low it can only buy a monthly visit.
  • An appointment that does not name one individual, their authority limits, and whether they certify or only administer.
  • No cost management in the scope where changes are likely.
  • No answer on who in the firm will actually do the work.

Take this list to every interview, including ours.

When you need an employer's agent, and when we can act

On a simple design and build job, an experienced client can run the contract itself. Most clients still appoint one, because a single missed notice can cost more than the fee.

On a design and build project, the contractor's team and the client's agent deal with each other every week. Below £5M, one design and build team is usually the simpler route.

On schemes of £5M or more, the client side needs more than one person. Our construction project management directors run programme, cost, tender, approvals and lender reporting before a contractor is appointed.

Where another contractor builds, our development management team can act as your employer's agent, on schemes from £3M to £150M GDV. An RICS-qualified quantity surveyor on our team checks every valuation. Our Development Director, Rob Barton, was a housebuilding managing director in a previous role.

Where we build, appoint your own agent; we hand them programme, valuations and change records. Discuss your project or ask us to review your scheme. We come back to you the same working day.

Frequently asked questions

What is an employer's agent in construction?

It is the person or firm a client appoints to act for it under a design and build contract. The contract names them, and the contractor takes instructions, notices and payment decisions from them rather than from the client directly.

Do I need an employer's agent on a design and build project?

The JCT design and build form expects someone to act for you, but that can be you or an employee. Most clients appoint an outside agent, because one missed payment notice or deadline can cost more than the appointment.

Can the contractor's own team act as my employer's agent?

No. The agent holds your confidential instructions and must value the contractor's work fairly, which a builder's own staff cannot do. That is why we act as employer's agent only on schemes we do not build.

Employer's agent or project manager: which one do I need?

A project manager leads the project for you from the start: team, programme and decisions. An employer's agent administers the building contract once it is signed. Larger schemes often use both, and one firm can hold both appointments.

How is an employer's agent different from a contract administrator?

A contract administrator, usually the architect on a traditional JCT contract, certifies payment and completion as an impartial party. An employer's agent on design and build acts for the client, though RICS says it should still be fair when it certifies or decides.

Who usually acts as employer's agent?

Usually a quantity surveyor, building surveyor or project management firm with design and build experience. RICS says the contract should name one individual, with their firm named alongside, so the contractor knows who has authority.

Why do lenders appoint a monitoring surveyor as well?

The employer's agent works for the borrower, so it is not independent of them. Lenders generally want their own report on cost, programme and risk, so they appoint a monitoring surveyor who answers to them.

How much does an employer's agent cost?

There is no standard fee. It depends on the scope, the size and length of the build, how often the agent is on site, and whether tender work is included. Get each fee proposal as a written list of services and compare them line by line.