For owners whose work is already built
Retrospective Planning Permission: What to Do When the Work Is Already Built
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 9 min read
The short answer
Retrospective planning permission is a normal planning application made after the work is done, under section 73A of the Town and Country Planning Act 1990. There is no penalty for applying and no guarantee of consent.
- Apply before the council issues an enforcement notice: after one, it can refuse to consider your application.
- Work finished more than 10 years ago (4 years if completed before 25 April 2024) may already be lawful: ask for a certificate instead.
- An enforcement notice must be appealed before it takes effect, at least 28 days after it is served.
- A refusal means appeal, alter the work to a version the council will accept, or remove it.
Retrospective planning permission is planning permission applied for after the work has been done. It is made under section 73A of the Town and Country Planning Act 1990. The council assesses it like any other application, and can grant or refuse it.
If you are reading this, the work is probably already built. A rear extension, a loft, a mezzanine, a change of use, a new shopfront. A neighbour has complained, a council letter has arrived, or a buyer's solicitor has asked for paperwork that does not exist.
This guide is written by a London planning consultant team that also builds. It covers the routes, the deadlines and the costs. Holding a council letter? Tell us what was built and we will tell you the route.
What retrospective planning permission is, and what it is not
Section 73A lets a council grant permission for development carried out before the date of the application. It covers work done without permission, work that outlived a temporary permission, and work done in breach of a condition. The permission can take effect from the date the work was carried out.
Applying is not an admission of guilt and carries no fine. Building without permission is not a criminal offence in itself. The offences come later: ignoring an enforcement notice, a stop notice or a breach of condition notice.
Government planning practice guidance on enforcement, updated 6 May 2026, goes further. Councils should invite an application where the work has a reasonable prospect of being acceptable.
Two more things it is not. It is not a route to Community Infrastructure Levy relief: a retrospective permission is generally not eligible for CIL exemptions. And it is not a sign-off under the Building Regulations, which is a separate process covered below.
Three routes: apply, certify, or wait
The right route depends on one date: when the work was substantially completed, or when the use began. Enforcement time limits changed on 25 April 2024 under the Levelling-up and Regeneration Act 2023.
| Breach | Time limit |
|---|---|
| Building works substantially completed on or after 25 April 2024 | 10 years |
| Building works substantially completed before 25 April 2024 | 4 years |
| Change of use to a single home, on or after 25 April 2024 | 10 years |
| Change of use to a single home, before 25 April 2024 | 4 years |
| Any other breach, including other changes of use and breaches of condition | 10 years |
| Demolition of an unlisted building in a conservation area | No time limit |
Once you know the date, there are three routes.
- Certificate of lawfulness. If the time limit has passed, apply under section 191. The council must issue the certificate if your evidence shows the use or works were lawful on the date you applied.
- Retrospective application. If the time limit has not passed and the work is acceptable in planning terms, apply under section 73A. The drawings show the work as built.
- Wait. Doing nothing is a risk, not a plan. The council can act at any time within the limit, and a buyer's or lender's solicitor will find the gap in the paperwork.
Our guide to outline, full and certificate of lawfulness applications explains what evidence a certificate needs. The best evidence is dated: invoices, photographs, council tax records, aerial imagery and statutory declarations from people who saw the work.
The enforcement process, step by step
Councils rarely start with an enforcement notice. The usual sequence runs from a letter to a notice, and each step has its own deadline.
- Complaint and site visit. Most cases start with a neighbour. An officer visits and compares what is built with the planning history.
- Planning contravention notice. A formal request for information. You have 21 days to return it. Not answering, or answering falsely, is an offence.
- Enforcement warning notice. New since 25 April 2024. It says the work has a reasonable prospect of consent and gives you a date to apply by. There is no appeal against it.
- Temporary stop notice. Used where the council wants an activity stopped at once. It lasts up to 56 days in England.
- Enforcement notice. It states the breach, the steps to put it right and the time allowed. Copies must be served within 28 days of issue, and at least 28 days before the date it takes effect.
- Compliance period. Once the notice takes effect and the period runs out, the owner is in breach. Failing to comply is an offence punishable by a fine, and the court must consider the financial benefit gained.
Expedient is the test. A council must be satisfied there is a breach and that a notice is expedient, judged against the development plan. A small overrun of a permitted development limit may never be worth a notice. A new floor of flats, a commercial kitchen extract or a change of use that affects neighbours usually will be.
Appealing an enforcement notice: the seven grounds
An enforcement notice can be appealed to the Planning Inspectorate. The appeal must be received before the date the notice takes effect, which is at least 28 days after service. The Inspectorate's procedural guide, updated 22 April 2026, says there is no discretion: a late appeal is turned away. Appeals are submitted online only.
| Ground | What you argue |
|---|---|
| (a) | Planning permission ought to be granted, or the condition discharged |
| (b) | The matters in the notice have not occurred |
| (c) | They occurred, but they are not a breach of planning control |
| (d) | The time limit had already passed when the notice was issued |
| (e) | Copies of the notice were not served as the Act requires |
| (f) | The steps required go beyond what is needed to remedy the breach |
| (g) | The time given for compliance is too short |
Ground (a) is the planning merits. It carries a fee of twice the planning application fee for the same development, paid to the council.
Since 25 April 2024 there is a catch. If the council issued the notice after you made a related application, ground (a) is not available for two years after that application was decided. The merits are then argued through a planning appeal against the refusal instead.
Timescales are long. The Planning Inspectorate's statistical release of 22 October 2026 gives a median of 66 weeks from a valid enforcement appeal to a decision. Planning appeals by written representations took a median of 18 weeks. Our planning appeal guide for London covers the planning route in detail.
What a refusal means: appeal, alter, or remove
A refused retrospective application is a refusal like any other. You have six months to appeal to the Planning Inspectorate, or 12 weeks for a householder application. If an enforcement notice has also been served, the enforcement deadline governs, and it is shorter.
- Appeal. Right where the officer's report misreads policy or the committee went against its officer. For applications made from 1 April 2026, most appeals cannot add new evidence, so the application itself is the case.
- Alter. Often the cheapest route. Councils refuse on specific points: height, depth, a window, materials, a roof terrace, noise from plant. A revised scheme that removes the point goes in as a new application.
- Remove. The last resort, and what an enforcement notice requires if nothing else succeeds.
For a commercial or mixed-use building the alteration route usually needs construction, not just drawings. A lowered parapet, obscured glazing, a relocated flue, an acoustic enclosure around plant, a mezzanine cut back from the shopfront. Having the designer and the builder in one team keeps the revised drawings buildable and priced before they are submitted.
Amazing experience with these guys. I trusted them my apartment in London and Business. They are always accurate, very professional, responsive and neat. They would always advice me right things for my best interest. I had luxury experience with them and I would definitely recommend Craftex to everyone.
What retrospective planning permission costs
There is no separate fee for a retrospective application. You pay the fee for the application the work would have needed. The figures below are the council fees in England from 1 April 2026; a rise is proposed from 8 December 2026.
| Application | Fee |
|---|---|
| Householder: extension or alteration to a house | £548 |
| New commercial floorspace, 40 to 1,000 m² | £610 per 75 m² |
| Change of use of a building, other than to homes | £610 |
| Certificate of lawfulness, existing use or works | Same as the full application fee |
| Certificate of lawfulness, proposed use or works | Half the full application fee |
| Enforcement appeal on ground (a) | Twice the application fee |
The full schedule and the proposed December figures are in our guide to planning application fees in 2026.
The fee is the small part. Professional costs cover a measured survey of what was built, as-built drawings and a planning statement. Add any reports the council asks for: daylight, noise, heritage, transport.
The works are the real variable. Nothing if consent is granted as built. An element rebuilt if it is not. The whole thing taken down if a notice stands and every appeal fails.
Listed buildings and the Building Regulations: two separate problems
Retrospective planning permission does not cover a listed building. Unauthorised works that affect its character are a criminal offence under section 9 of the Planning (Listed Buildings and Conservation Areas) Act 1990. The penalty on indictment is up to two years' imprisonment, a fine, or both.
There is no time-limit immunity for a listed building. Retrospective listed building consent can be applied for, but take advice before anything else.
Nor does it cover the Building Regulations. Work done without building control approval needs a regularisation certificate under regulation 18 of the Building Regulations 2010. The authority can require the work to be opened up, tested and sampled.
The certificate is evidence, not conclusive proof, that the work complies. Buyers' solicitors ask for both documents, so plan for both at the start.
How we help: survey, redesign, cost, apply, build
Our planning work starts from the building, not from the forms. Retrospective cases are won on accurate as-built information and a realistic view of what the council will accept.
- Survey what was built. A measured survey and as-built drawings, so the application describes the real building.
- Design the compliant version. Where the work as built will not get consent, we draw the version that will and show the difference.
- Cost the alterations. Each option priced before you choose, so the planning decision is also a budget decision.
- Run the application. Planning statement, submission, officer negotiation, and the appeal if one is needed.
- Deliver the works. The same team builds the alterations, as a construction company in London with around 60% of its labour in-house.
Homeowner with a single rear extension? The same rules apply, and the planning route is usually simple enough for an architect alone. We take on construction projects from £100,000. For a small extension our advice is short: apply early, and apply before the notice.
If the building is commercial or mixed use, or the fix needs construction, tell us what was built and when. We check the planning history and the time limits, and come back with the route and a price for the works.
Before you apply
- Date the work: invoices, photographs, aerial imagery, statutory declarations from people who saw it.
- Pull the planning history for the address, including conditions on earlier permissions.
- Check whether the building is listed or in a conservation area.
- Check whether the work has a Building Regulations completion certificate.
- Ask whether a certificate of lawfulness is possible before paying for a retrospective application.
- Do not wait for the enforcement notice.