Skip to content
Request a callbackCallback

For owners and developers with a planning refusal

The Planning Appeal Process: Timescales and Costs

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read

Georgian brick terrace with chimney stacks under a cloudy sky

The short answer

If the council refuses your application, sets conditions you cannot accept or does not decide in time, you can make a planning appeal to the Planning Inspectorate in England. Most appeals must be made within six months, and householder and minor commercial refusals within 12 weeks.

  1. For applications made from 1 April 2026, most appeals cannot add new evidence.
  2. If a new report or design change would fix the refusal, resubmit instead.
  3. Written appeals took a median of 18 weeks in the 12 months to September 2026.
  4. 31% of section 78 planning appeals were allowed in July to September 2026.

A planning appeal asks the Planning Inspectorate to overturn a council's refusal, its conditions or its failure to decide in time. In England, most appeals must reach the Inspectorate within six months of the decision notice.

A refusal is not the end of a scheme. Many good schemes are refused first and consented later. The question is which route gets you to a consent sooner: an appeal, or a better application. Our planning appeal consultants start every refused scheme with that question.

The rules changed for applications made on or after 1 April 2026. Most appeals now follow a fast written procedure where you cannot add new evidence. That makes the application itself your appeal case.

Holding a refusal now? Send us the decision notice. Our Development Director, a former housebuilding managing director, reads it and tells you, free, whether an appeal or a fresh application is the better route. Book a site visit and we will see the scheme on the ground too.

Appeal or resubmit: decide first

Before anything else, decide which route gets you a consent soonest. The answer depends on why the scheme was refused. Read the decision notice and the officer's report side by side. The reasons for refusal name the policies the scheme failed, and the report shows how close it came.

Appeal or resubmit, by situation
SituationUsually better to
The refusal turns on a point a design change or new report can fixAmend and resubmit, as the Inspectorate advises
The refusal is a judgement you think is wrong, and your application made the full caseAppeal
Committee refused against the officer's recommendationAppeal is often strong; read the minutes
You cannot accept a conditionAppeal the condition, or apply to vary it under section 73
The council ran out of time and will not agree an extensionAppeal for non-determination, or keep negotiating

Our planning consultancy team starts every refused scheme the same way. Read the reasons, check them against policy and the officer's report, then choose. Send us your notice and a director will run that check for you, free.

Planning appeal deadlines

These are the Inspectorate's time limits in England for appeals on applications made from 1 April 2026. Miss them and the appeal will not be accepted.

Time limits to appeal
AppealDeadline
Householder refusal12 weeks from the decision notice
Minor commercial refusal12 weeks from the decision notice
Householder or minor commercial: conditions6 months from the decision notice
All other planning applications6 months from the decision notice
Non-determination6 months after the council's deadline passed
Advertisement consent8 weeks
Enforcement notice on the same developmentOften 28 days

The council's decision periods are 8 weeks for most applications and 13 weeks for major development. It is 16 weeks where an environmental impact assessment is needed, unless you agree longer in writing.

If you do not own the whole site, you must notify every owner. Do it within the 21 days before you submit.

The April 2026 change: no new evidence

Since April 2026, the Inspectorate's guidance sets out a stricter process for appeals on new applications.

  1. Part 1 written procedure. Most section 78 appeals now follow it.
  2. No new evidence. You cannot submit evidence the council did not consider. The exception is a material change, such as a new policy or court judgment.
  3. No new comments. Interested people cannot comment at the appeal stage. Their earlier comments go to the Inspector.
  4. Revise instead. If a new report or amended scheme would fix the refusal, the guidance says to submit a new application.
  5. Obligations up front. A completed planning obligation, such as a unilateral undertaking, goes in with the appeal.

We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.

Ben Edell, Google reviewSee all reviews on Google

How to make a planning appeal, step by step

Only the person who made the planning application can appeal in England. You appeal online, through the Inspectorate's "Appeal a planning decision" service on GOV.UK.

  1. Check the deadline. It runs from the date on the decision notice, or from the end of the council's decision period.
  2. Gather the papers. Send the appeal form, your application form, the decision notice and any completed planning obligation.
  3. Copy the council. After you submit, you must forward a copy of the appeal to the council.
  4. Wait for the start date. The Inspectorate checks the appeal and confirms the procedure. The date of that letter is the start date.
  5. The council replies. Under Part 1, it sends its questionnaire within 5 working days of the start date and tells interested people.
  6. Site visit and decision. The Inspector usually visits the site, then sends the written decision.

Non-determination and listed building consent appeals follow a separate Part 2 written procedure. The steps are similar, but the timetable differs.

How long a planning appeal takes

These figures come from the Planning Inspectorate's statistical release of 22 October 2026. They cover the 12 months to September 2026.

18 weeksMedian, written representations
24 weeksMedian, hearings
27 weeksMedian, inquiries
31%Planning appeals allowed, Jul to Sep 2026

The median across all cases was 18 weeks. The mean was 29 weeks, because long cases pull the average up. These figures include older applications too. There is little data on the new procedure yet.

Costs and what happens after the decision

Each side normally pays its own appeal costs. Costs can be awarded against a party that behaves unreasonably and causes the other side needless expense. A council refusing on a ground it cannot back up is one example. Read the costs guidance before you appeal, not after.

The Inspector's decision is final on the planning merits. A High Court challenge is possible only on a point of law, within six weeks. If the appeal is dismissed, the reasoning still helps. It tells you exactly what a revised scheme has to fix.

London-specific points

London adds layers that change how refusals play out.

  1. The Mayor's role. Large schemes are referable to the Mayor of London, who can direct refusal or take over the application.
  2. Heritage. Many central London refusals turn on conservation areas and listed buildings. Listed building consent appeals follow the same deadlines.
  3. Daylight and sunlight. A frequent reason for refusal on dense sites. The study belongs in the application. Rights of light are a separate legal question: see right to light for London developers.
  4. Affordable housing and viability. For major housing, the London Plan routes often decide whether to appeal or resubmit. The time-limited 20% route is open to applications validated before 31 March 2028. See CIL and Section 106 explained.

Build the application like an appeal

The best protection against a refusal is also the best appeal: a complete, well-evidenced application.

  1. Test the scheme before you draw it. A development viability assessment checks policy, heritage, daylight, access and the numbers first.
  2. Use pre-application advice to surface the council's objections early.
  3. Submit every report the scheme needs, even where the validation list does not insist.
  4. Answer every policy in the planning statement, especially the ones you depart from.
  5. Keep a record of meetings and officer feedback. It matters for costs and for committee.
  6. Decide your fallback before the decision: what you would change, and what you would defend.

At Allitsen Road in St John's Wood, four design options were tested against the City Plan, the London Plan, structure and viability. That happened before any one was recommended. Choosing the option on planning risk keeps a scheme out of the appeal system.

For the planning routes themselves, see our planning services and change of use planning pages. Weighing what consent could add to land? Our land value uplift and planning gain team can show the difference.

Refused, or about to submit? Send us the decision notice or the drawings. A director will tell you, free, whether to appeal, resubmit or strengthen the application first. Book a site visit if you want us to walk the site with you.

Frequently asked questions

How long do I have to appeal a planning refusal?

Six months from the decision notice for most applications, including change of use and new homes. Twelve weeks for householder and minor commercial refusals. Where an enforcement notice covers the same development, the limit can fall to 28 days from the council's decision notice.

Who can make a planning appeal?

The applicant, and nobody else. Neighbours and objectors have no right of appeal against a grant of permission. If you bought a site after a refusal, the earlier application is not yours to appeal, so ask us to look at the options.

Can I submit new evidence with a planning appeal?

Mostly not, where the application was made from April 2026. The Inspector looks only at what the council saw, unless circumstances have materially changed. Where a new report would overcome the refusal, the Inspectorate's guidance points you to a revised planning application.

How long does a planning appeal take?

Over the 12 months to September 2026, decisions on written appeals took a median of 18 weeks from a valid appeal. Hearings took 24 weeks and inquiries 27. Long cases pull the average for all appeals up to 29 weeks.

What percentage of planning appeals succeed?

The Planning Inspectorate's release of 22 October 2026 puts the allowed rate for section 78 planning appeals at 31% for July to September 2026. That was the same as the quarter before.

Is it better to appeal or resubmit?

If design changes or extra evidence can fix the refusal, resubmitting is usually quicker, and it is what the Inspectorate recommends. If the council's judgement was wrong and your application already made the full case, an appeal can be the better route.

Who pays for a planning appeal?

Normally each side pays its own. An award is possible where one side behaved unreasonably and that cost the other side money it should not have spent.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Got a refusal, or a scheme you want to get right first time?

Send us the address with the refusal notice, or the scheme before you submit. A director reads it and gives you a free, straight answer on the route we would take. Book a site visit.

WhatsApp us