For owners and developers with a planning refusal
The Planning Appeal Process: Timescales and Costs
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
If the council refuses your application, sets conditions you cannot accept or does not decide in time, you can make a planning appeal to the Planning Inspectorate in England. Most appeals must be made within six months, and householder and minor commercial refusals within 12 weeks.
- For applications made from 1 April 2026, most appeals cannot add new evidence.
- If a new report or design change would fix the refusal, resubmit instead.
- Written appeals took a median of 18 weeks in the 12 months to September 2026.
- 31% of section 78 planning appeals were allowed in July to September 2026.
A planning appeal asks the Planning Inspectorate to overturn a council's refusal, its conditions or its failure to decide in time. In England, most appeals must reach the Inspectorate within six months of the decision notice.
A refusal is not the end of a scheme. Many good schemes are refused first and consented later. The question is which route gets you to a consent sooner: an appeal, or a better application. Our planning appeal consultants start every refused scheme with that question.
The rules changed for applications made on or after 1 April 2026. Most appeals now follow a fast written procedure where you cannot add new evidence. That makes the application itself your appeal case.
Holding a refusal now? Send us the decision notice. Our Development Director, a former housebuilding managing director, reads it and tells you, free, whether an appeal or a fresh application is the better route. Book a site visit and we will see the scheme on the ground too.
Appeal or resubmit: decide first
Before anything else, decide which route gets you a consent soonest. The answer depends on why the scheme was refused. Read the decision notice and the officer's report side by side. The reasons for refusal name the policies the scheme failed, and the report shows how close it came.
| Situation | Usually better to |
|---|---|
| The refusal turns on a point a design change or new report can fix | Amend and resubmit, as the Inspectorate advises |
| The refusal is a judgement you think is wrong, and your application made the full case | Appeal |
| Committee refused against the officer's recommendation | Appeal is often strong; read the minutes |
| You cannot accept a condition | Appeal the condition, or apply to vary it under section 73 |
| The council ran out of time and will not agree an extension | Appeal for non-determination, or keep negotiating |
Our planning consultancy team starts every refused scheme the same way. Read the reasons, check them against policy and the officer's report, then choose. Send us your notice and a director will run that check for you, free.
Planning appeal deadlines
These are the Inspectorate's time limits in England for appeals on applications made from 1 April 2026. Miss them and the appeal will not be accepted.
| Appeal | Deadline |
|---|---|
| Householder refusal | 12 weeks from the decision notice |
| Minor commercial refusal | 12 weeks from the decision notice |
| Householder or minor commercial: conditions | 6 months from the decision notice |
| All other planning applications | 6 months from the decision notice |
| Non-determination | 6 months after the council's deadline passed |
| Advertisement consent | 8 weeks |
| Enforcement notice on the same development | Often 28 days |
The council's decision periods are 8 weeks for most applications and 13 weeks for major development. It is 16 weeks where an environmental impact assessment is needed, unless you agree longer in writing.
If you do not own the whole site, you must notify every owner. Do it within the 21 days before you submit.
The April 2026 change: no new evidence
Since April 2026, the Inspectorate's guidance sets out a stricter process for appeals on new applications.
- Part 1 written procedure. Most section 78 appeals now follow it.
- No new evidence. You cannot submit evidence the council did not consider. The exception is a material change, such as a new policy or court judgment.
- No new comments. Interested people cannot comment at the appeal stage. Their earlier comments go to the Inspector.
- Revise instead. If a new report or amended scheme would fix the refusal, the guidance says to submit a new application.
- Obligations up front. A completed planning obligation, such as a unilateral undertaking, goes in with the appeal.
We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.
How to make a planning appeal, step by step
Only the person who made the planning application can appeal in England. You appeal online, through the Inspectorate's "Appeal a planning decision" service on GOV.UK.
- Check the deadline. It runs from the date on the decision notice, or from the end of the council's decision period.
- Gather the papers. Send the appeal form, your application form, the decision notice and any completed planning obligation.
- Copy the council. After you submit, you must forward a copy of the appeal to the council.
- Wait for the start date. The Inspectorate checks the appeal and confirms the procedure. The date of that letter is the start date.
- The council replies. Under Part 1, it sends its questionnaire within 5 working days of the start date and tells interested people.
- Site visit and decision. The Inspector usually visits the site, then sends the written decision.
Non-determination and listed building consent appeals follow a separate Part 2 written procedure. The steps are similar, but the timetable differs.
How long a planning appeal takes
These figures come from the Planning Inspectorate's statistical release of 22 October 2026. They cover the 12 months to September 2026.
The median across all cases was 18 weeks. The mean was 29 weeks, because long cases pull the average up. These figures include older applications too. There is little data on the new procedure yet.
Costs and what happens after the decision
Each side normally pays its own appeal costs. Costs can be awarded against a party that behaves unreasonably and causes the other side needless expense. A council refusing on a ground it cannot back up is one example. Read the costs guidance before you appeal, not after.
The Inspector's decision is final on the planning merits. A High Court challenge is possible only on a point of law, within six weeks. If the appeal is dismissed, the reasoning still helps. It tells you exactly what a revised scheme has to fix.
London-specific points
London adds layers that change how refusals play out.
- The Mayor's role. Large schemes are referable to the Mayor of London, who can direct refusal or take over the application.
- Heritage. Many central London refusals turn on conservation areas and listed buildings. Listed building consent appeals follow the same deadlines.
- Daylight and sunlight. A frequent reason for refusal on dense sites. The study belongs in the application. Rights of light are a separate legal question: see right to light for London developers.
- Affordable housing and viability. For major housing, the London Plan routes often decide whether to appeal or resubmit. The time-limited 20% route is open to applications validated before 31 March 2028. See CIL and Section 106 explained.
Build the application like an appeal
The best protection against a refusal is also the best appeal: a complete, well-evidenced application.
- Test the scheme before you draw it. A development viability assessment checks policy, heritage, daylight, access and the numbers first.
- Use pre-application advice to surface the council's objections early.
- Submit every report the scheme needs, even where the validation list does not insist.
- Answer every policy in the planning statement, especially the ones you depart from.
- Keep a record of meetings and officer feedback. It matters for costs and for committee.
- Decide your fallback before the decision: what you would change, and what you would defend.
At Allitsen Road in St John's Wood, four design options were tested against the City Plan, the London Plan, structure and viability. That happened before any one was recommended. Choosing the option on planning risk keeps a scheme out of the appeal system.
For the planning routes themselves, see our planning services and change of use planning pages. Weighing what consent could add to land? Our land value uplift and planning gain team can show the difference.
Refused, or about to submit? Send us the decision notice or the drawings. A director will tell you, free, whether to appeal, resubmit or strengthen the application first. Book a site visit if you want us to walk the site with you.