Construction Cost Plan: How It Is Built

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 4 min read

Red scale rule lying across a printed technical drawing

The short answer

A construction cost plan is the budget for a building, broken into elements and checked at each design stage. It starts as an order of cost estimate and becomes a pre-tender estimate before contractors price the job.

  1. RICS NRM 1 sets the standard method: order of cost estimate, then formal cost plans 1, 2 and 3.
  2. Elements follow a fixed list, from substructure and frame to services, preliminaries and fees.
  3. Risk is held as separate allowances, not hidden inside the rates.
  4. A cost plan is only as good as the design and the market data behind it.

A construction cost plan is the budget for a building, broken into elements and checked at every design stage. Done well, it tells you what the scheme will cost before contractors price it. Done badly, it is a single number that the first tender breaks.

Most cost plans in the UK follow RICS NRM 1, the standard for cost estimating and cost planning. This guide walks through how a cost plan is built, stage by stage, and where it usually goes wrong.

Before you rely on one, test it against the people who would build the scheme. Ask for our free cost and buildability review, or send us your drawings and we will tell you where the risk sits.

How a construction cost plan develops

A cost plan is not written once. It grows with the design, and each version is more detailed than the last.

The stages of a construction cost plan under RICS NRM 1
StageWhenWhat it is based on
Order of cost estimateBrief, before a designFloor area, functional units or broad elements
Formal cost plan 1RIBA Stage 2, concept designCost targets for each group element
Formal cost plan 2RIBA Stage 3, spatial coordinationElements and sub-elements, measured from drawings
Formal cost plan 3RIBA Stage 4, technical designDetailed measurement and specification
Pre-tender estimateWhen contractors are engagedThe pricing documents the contractors will price

Each stage should narrow the range. If the figure jumps between stages, something in the design or the brief changed, and the plan should say what. Keep every version, so the change can be traced.

The order of cost estimate

The order of cost estimate answers one question: is the budget realistic for this brief? It comes before there is a design to measure.

NRM 1 allows three methods at this stage:

  1. Floor area method. A cost per square metre of gross internal floor area.
  2. Functional unit method. A cost per unit of use, such as per bed space, per house type or per square metre of retail area.
  3. Elemental method. Broad costs for the main elements of the building.

Whatever the method, the estimate should state its basis, the date of its rates and what it excludes. An estimate without those three is a guess with a total.

The elemental cost plan under NRM 1

Once a design exists, the cost plan breaks the building into elements and sets a cost target for each one. NRM 1 fixes the list, so two cost plans can be compared line by line.

NRM 1 group elements in a cost plan
GroupWhat it covers
0 to 1Facilitating works and substructure
2 to 4Superstructure, internal finishes, fittings and equipment
5Services: mechanical, electrical, plumbing and lifts
6 to 8Prefabricated units, work to existing buildings, external works
9 to 10Main contractor's preliminaries, overheads and profit
11 to 12Project and design team fees, other project costs
13 to 14Risks and inflation

On a refurbishment or conversion, group 7, work to existing buildings, often carries the most uncertainty. That is where surveys pay for themselves.

Risk allowance and contingency

NRM 1 treats risk as a cost in its own right, not as padding hidden in the rates. It recommends holding risk as separate allowances:

  1. Design development risks, for the design still to be finished.
  2. Construction risks, such as ground conditions and existing structure.
  3. Employer change risks, for changes the client may still make.
  4. Employer other risks, such as programme or funding issues.

When an element overruns, the overspend is covered by a transfer from the right allowance. When an element comes in under its target, the surplus goes back. The allowances should shrink as the design firms up.

Our guide to how much contingency a project needs covers sizing it by stage.

Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

Pascal Hunt, Google reviewSee all reviews on Google

From cost plan to tender

The last version, the pre-tender estimate, is the figure the tenders are judged against. It is only useful if it was built from the same documents the contractors price.

Three things keep the plan and the tenders comparable:

  1. One set of documents. The drawings, specification and scope the plan measured are the ones that go out to tender.
  2. The same exclusions. Anything left out of the plan is left out of every tender, in writing.
  3. Provisional sums with figures. Undesigned items carry the same amount in the plan and in every price; see provisional sums in construction.

If the tenders still come back above the plan, value engineering is the next step, before anyone cuts scope.

Who prepares the cost plan

On most projects a quantity surveyor or cost consultant appointed by the client prepares the cost plan. Their independence is the point: they check the design team's ambitions against cost.

What a consultant's plan cannot do is test prices against a live supply chain. That is where a contractor's pre-construction input adds value. On a two-stage tender or under a pre-construction services agreement, the builder prices the elements while the design can still change.

We do both sides of that conversation. An RICS-qualified quantity surveyor on our team reads the cost plan. Our in-house construction team, around 60% of the labour on our projects, prices how it would actually be built.

Already holding a cost plan or a quote? Send it to us. We'll beat it for the same scope, and we reply the same working day. Or get a free cost review before you go to tender.

Frequently asked questions

What is a cost plan in construction?

A cost plan is the budget for a building project, broken down into elements such as substructure, frame, finishes and services, with allowances for fees, risk and inflation. It is prepared and updated as the design develops, so the client can control cost before the project goes to tender.

What is the difference between a cost estimate and a cost plan?

Under RICS NRM 1, the order of cost estimate comes first, at the brief stage, and uses floor area, functional units or broad elements. The cost plan follows once there is a design, and sets a cost target for each element, which is checked as the design develops.

Who prepares a construction cost plan?

Usually a quantity surveyor or cost consultant appointed by the client. On a two-stage or design and build route, the contractor also prices the scheme in pre-construction, which tests the plan against real market prices before the contract is signed.

What is NRM 1?

NRM 1 is the RICS standard for order of cost estimating and cost planning for capital building works. The third edition was published in October 2021 and took effect on 1 December 2021. It sets the stages, the elements and how risk and inflation are allowed for.