For landlords and investors planning an HMO
HMO Planning Permission: C4 or Sui Generis
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 10 min read
The short answer
An HMO needs planning permission when Class L does not cover it: seven or more residents, an Article 4 area, or a commercial building. Outside those cases, a house can become a small C4 HMO for up to six residents with no application.
- Class C4 is a house shared by three to six unrelated residents. Class L lets a C3 house become C4 without an application.
- An Article 4 direction removes that right. Newham and Hounslow, for example, have borough-wide directions for C3 to C4.
- More than six residents is a sui generis use. Class L does not cover it, so you apply for change of use.
- Planning is one consent of three: the works need Building Regulations approval and many HMOs need a licence.
HMO planning permission depends on how many people will live in the building and what the building is today. A house can become a small HMO for up to six residents without an application, unless an Article 4 direction applies. Seven or more residents, or any commercial building, needs a full planning application.
That answer hides three legal tests. The C4 use class sets the limit at six. Class L of the permitted development rules gives the free route. An Article 4 direction can take it away in any area the council specifies, up to a whole borough.
Get the route wrong and the rooms your price relies on may never be allowed. This guide covers each test in turn, then the policies councils use to refuse. Planning self-contained homes instead? See our flat conversion in London service.
It is written by the team behind our HMO conversion service, who check the route, draw the layout and build it. Found a house? Send us the address for a free HMO route check before you exchange.
When an HMO needs planning permission
Three questions decide the route. What is the building's use class today? How many residents will live there? Is there an Article 4 direction on the address?
A house is Class C3. A small HMO is Class C4. A large HMO, with more than six residents, is sui generis. A shop or office usually sits in Class E, and a pub is sui generis already.
| Starting point | Up to six residents | Seven or more residents |
|---|---|---|
| House (Class C3), no Article 4 direction | No application: permitted development under Class L | Full planning application (sui generis) |
| House (Class C3) in an Article 4 area | Full planning application for C3 to C4 | Full planning application (sui generis) |
| Office, shop, pub or other commercial building | Full planning application for change of use | Full planning application (sui generis) |
The table covers the use only. A rear extension, a loft dormer or new windows are building works with their own planning rules. They are judged separately from the change to an HMO.
Find your row in the table, then read the section for it below.
The C4 use class: what counts as a small HMO
The C4 use class is defined in the Use Classes Order 1987. It covers the use of a dwellinghouse by not more than six residents as a house in multiple occupation. The Planning Portal describes it as a small shared house for three to six unrelated people, living there as their main home.
"House in multiple occupation" takes its meaning from section 254 of the Housing Act 2004. In short, the residents do not form a single household and share at least one basic amenity. Basic amenities are a toilet, personal washing facilities or cooking facilities.
A household is a family in the wide sense of section 258. Couples count as one household, and so do parents, children, siblings, grandparents, aunts, uncles, nephews, nieces and cousins. Three friends sharing a kitchen are three households. A couple and their child are one. Count the households you plan to let to before you look at Class L.
Class L: from house to small HMO without an application
Class L sits in Part 3 of the General Permitted Development Order 2015. It permits two changes of use. A house (C3) can become a small HMO (C4), and a small HMO can go back to a house. Neither needs a planning application, where no Article 4 direction applies.
Class L has one limit. It does not apply if the result is two or more separate dwellings. Splitting a house into self-contained flats is a different route, covered in our guide to converting a house into flats in London.
Permitted development means no application, not no paperwork. Under section 192 of the Town and Country Planning Act 1990 you can apply for a certificate of lawfulness of proposed use. If the council is satisfied the C4 use would be lawful, it must issue the certificate. The fee is half the full application fee.
That certificate is the cleanest proof of the route for a buyer or a licensing officer. For a use that has already begun, section 191 provides a certificate of lawfulness of existing use instead.
Sui generis HMOs: seven or more residents
Class C4 stops at six residents. Above six, the Planning Portal says, an HMO becomes a sui generis use: "in a class of its own". It sits outside every use class, so no class-to-class rule covers it.
Class L only covers C3 to C4 and back. A large HMO is outside it, so you need a full planning application for the change of use. That applies to a house, to an existing six-bed C4 HMO taking a seventh resident, and to a commercial building.
An HMO application typically falls in the national council fee category "other changes of use of a building or land", currently £610. A fee of £732 is proposed from 8 December 2026, if Parliament approves the draft regulations. The council then has 8 weeks to decide a non-major application, or longer if you both agree in writing.
| Point | Small HMO (Class C4) | Large HMO (sui generis) |
|---|---|---|
| Residents | 3 to 6, not one household | More than 6 |
| From a house, no Article 4 | No application under Class L | Full planning application |
| From a house, Article 4 area | Full planning application | Full planning application |
| Mandatory licence | If 5 or 6 people in 2 or more households | Yes, where 2 or more households share |
Article 4 directions on HMOs in London
An Article 4 direction is a council order made under article 4 of the General Permitted Development Order. It removes named permitted development rights in a defined area. For HMOs it removes the Class L change from C3 to C4.
The house can still become an HMO, but only with planning permission. The application is then judged against the borough's policies, which is where most schemes are won or lost.
London boroughs can make a direction, and some cover the whole borough. Newham made its direction on 31 July 2012 and it came into force on 31 July 2013. The 2013 confirmation notice applies to the whole borough except the area within the control of the London Legacy Development Corporation.
Hounslow's borough-wide direction for C3 to C4 took effect on 4 September 2023. It excludes open land, some industrial areas, two business parks and Mogden Sewage Works.
New directions keep being made, so check the address on the day you price the deal. Our guide to Article 4 directions in London explains where to check and what to do if the building is caught. For the borough-by-borough HMO picture, read our guide to HMO Article 4 directions.
What a council weighs on an HMO application
Once an application is needed, the council judges it against its local plan. The fee and the eight weeks are the easy part. The policy test decides the outcome, and it is visible before you exchange.
Council policies on HMOs differ by borough, and these are six points we test. Read the local plan for the address on each one before you commit.
- Concentration. Some boroughs limit how many HMOs can sit in one street or area. A fresh application on a street already full of them starts weak.
- Family housing. Some London plans protect family-sized houses from conversion. The policy can apply whether or not an Article 4 direction exists.
- Room standards. The layout must meet the borough's HMO amenity standard: room sizes, kitchens and bathrooms per resident.
- Neighbours. More residents means more comings and goings. Councils look at noise, privacy and the effect on the street.
- Refuse, bikes and parking. Bins and cycle storage need a home. A terrace with no rear access can fail on bins alone.
- Loss of another use. A shop, office or pub is weighed for what the area loses before the rooms are looked at.
Our rule is simple. We appraise every HMO at the room count the borough's policy and standards support, not the count on the agent's floor plan.
Want the six points read for your address? Ask for a free HMO route check and we do it with you.
We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍
Commercial buildings to HMO: office, shop or pub
A commercial building never qualifies for Class L, which only starts from a house. A pub is sui generis already; a shop or office usually sits in Class E. In every case the HMO needs a full planning application for change of use.
The same buildings often make good HMOs. Deep plans and high ceilings help, and a goods entrance makes bins and bikes easy. A shell can take a clean new layout instead of a compromise around a narrow Victorian stair. Our guide to Class E explains which commercial buildings sit where.
The build is a material change of use under the Building Regulations. Fire, sound and energy requirements then apply to the whole building. That is why the job belongs with a commercial to residential conversion team. For the budget, including VAT and the costs outside the build, see our guide to commercial to residential conversion cost.
Planning is one of three consents
Planning permission decides the use. It does not approve the works or allow you to let the rooms. An HMO needs three separate yeses, and each one has its own officer.
- Planning. Class L, a certificate of lawfulness or a full application, as set out above.
- Building Regulations. Adding residential rooms, or changing their number, is a material change of use under regulation 5. The building must then meet set requirements, including fire safety and sound between rooms.
- Licence. An HMO occupied by five or more people in two or more households needs a mandatory licence. Some London boroughs license smaller HMOs too, through additional licensing.
Design the layout to all three at once. A plan that wins planning but fails the licence costs you a room, or a redesign. Our guide to HMO licence and regulations covers the licence conditions in full.
How we check the planning route before you buy
An HMO has four hand-offs where money leaks. Each gap is a redesign or a lost room.
- The planning consultant to the architect
- The architect to the fire engineer
- The fire engineer to the builder
- The builder to the licensing officer
We close them under one contract, from the first check to the licence-ready build. Send us the address and the number of residents you want. We check the use class, the Article 4 map and the borough's HMO policies. Then we draw the layout to the licensing standard, run the application where one is needed, and build it.
Craftex started in 2016 as a carpentry and joinery company. Around 60% of our labour is still in-house, which keeps the fire doors, partitions and joinery under our own control. We take on construction from £100,000 and design from a £15,000 minimum order. Every project we have delivered has finished ahead of programme and on budget.
Ready to test a building? Our change of use planning team checks the planning route before you exchange, so your offer matches the rooms you can let. Send us the address for your free route check, and we run the list below with you.
Before you exchange on an HMO
- Confirm the building's use class today and the number of residents you need
- Decide whether the scheme is C4 (up to six) or sui generis (seven or more)
- Check the Article 4 map for the exact address on the day you price it
- Read the borough's HMO concentration, family housing and amenity policies
- Where Class L applies, consider a certificate of lawfulness of proposed use
- Draw the layout to the licensing standard before the planning drawings
- Check whether mandatory or additional licensing applies at the address
- Allow for the planning fee, Building Regulations and the licence fee