Case study: office reception fit-out

Portsoken House Reception, Aldgate

Office reception fit-out: 70 sq m designed and rebuilt in 12 weeks of nights and weekends

Rebuilt in

12 weeks, working through
the night and at weekends

The project

  • 70 sq mreception in Aldgate
  • 1team for the design and the rebuild
  • 7+months on Portsoken House, offices first
  • £450Kproject value

Office reception design for a building that never closed

This office reception fit-out was the last piece of the Portsoken House office fit-out in Aldgate. Our team of designers and construction professionals spent more than seven months on the building, starting with a complete refurbishment of the second and eighth floors (the Portsoken House office fit-out).

The reception is the first impression of the building for tenants, prospective tenants and visitors, so the brief was a premium entrance worthy of the address: Aldgate is one of the capital’s most sought-after locations for commercial tenants.

The catch: the rest of the building was let and in use. The 70 sq m reception had to be designed and rebuilt in 12 weeks without interrupting a single tenant.

The rebuilt reception seen from the stair: full-height glazing and glass doors to the street, the dark grey desk with red flowers and the white directory panel

Office reception fit-out in Aldgate: the brief

Reception, designed and rebuilt
70 sq m
Nights and weekends only
12 weeks
Rest of the building, in use
Fully let
City of London
Aldgate, EC3

Rebuilding a reception in a building that stays open?

Send us your plans and the building’s rules for works. We come back with a night-and-weekend programme and a fixed-price proposal.

Reception area design: what changed in 70 sq m

The finished reception in use: visitors at the dark grey desk under the rectangular light frames, the stair with lit treads and the floor directory behind

A new shop window, lift surrounds and walls

To make the best use of every square metre, the reception went through a series of structural changes while the building’s original features were respected. The biggest is the new shop window at the entrance, which floods the space with natural light.

The lift surrounds facing the reception were rebuilt, and the walls were re-plastered with new plaster wall panels for a sleek, smooth finish. Daylight was the starting point of the office design.

For your reception: decide what can open up to daylight before you choose a single finish.

Italian stone, bespoke joinery and the light from upstairs

It is how we approach every office fit out in London: one team designs it, the same team builds it, and the finishes are chosen for the people who will walk over them every day.

  • 01

    Premium Italian stone

    Italian stone tiles were supplied and fitted across the floor: the surface that takes the footfall of every tenant, viewing and visitor, chosen to last.

  • 02

    Bespoke joinery

    Joinery made for this space and built under the same contract as the structure and the finishes: one contract, one price and one team to hold to it.

  • 03

    The light from upstairs

    Modern light fittings went in: the same rectangular fittings used throughout the offices above, so the entrance and the workspace read as one building.

    For your reception: stone and joinery have the longest lead times of the job, so order them as soon as the design is signed.

Office reception refurbishment at night and at weekends

Portsoken House from the street: the stone corner building in Aldgate with its ground-floor entrance, a red London bus passing and the City towers behind

Work only outside office hours, one team for the whole building

Every other floor stayed occupied. We worked outside office hours, through the night and at weekends, so the building’s tenants were never interrupted, and the reception was ready for them every morning. We worked closely with the client on the design, so the entrance reflects the location and the restored property’s luxurious appeal. More on how we plan this: office refurbishment while occupied.

Across Portsoken House, keeping the design and the build under one roof gave the client accurate pricing and considerable savings. The same approach runs our commercial fit-out and refurbishment work in shared buildings. For another office delivered against the clock, see Beaumont House.

What this means for you: if your entrance must open every morning, ask any contractor to show the night shifts in the programme, not only the price.

Already have a quote for your reception?

Send us your quote. We check it against your programme and the building’s rules, and we will aim to beat the price.

Our team

  • in

Office reception fit-out: the scope we delivered

Designed with the client and built by the same team, worked only outside office hours.

PackageWhat was done
DesignIn-house, worked up closely with the client
Structure and glazingStructural changes; a new shop window at the entrance
Lift surroundsRebuilt on the reception side
WallsRe-plastered with new plaster wall panels
Floor and joineryItalian stone tiles supplied and fitted; bespoke joinery
LightingModern rectangular fittings, matching the offices above
Programme12 weeks, nights and weekends only

Free cost calculator

Get a quote for your project

The Portsoken House reception is the proof. Now it is your turn. This project: about £6,430 per sq m (about £597 per sq ft), delivered in 12 weeks of nights and weekends. A reception costs several times more per sq m than an open-plan office floor: structure, glazing, stone and joinery go into a small area, and night work adds to it. The calculator below prices office floors. Enter your floor area or headcount for a first range, based on our 2026 London rates, ex VAT and fees; a reception is priced on its own after a survey.

I know my
Add
Your estimateEnter your spaceex VAT and fees Get a quote for your project

Headcount uses about 100 sq ft per person. Your fixed figure follows a survey of the floor and an agreed layout.

Free value: take this with you

Nine checks before rebuilding a reception in an occupied building

  1. Before the design

    • Decide who the reception is for: tenants, people viewing space to let, or visitors.
    • Get the building’s rules for works: hours, noise, access and deliveries.
    • Find out what sits behind the walls before planning structural changes around the lifts.
  2. Before you choose a contractor

    • Ask for a programme that shows the night and weekend shifts, not only a price.
    • Ask who designs and who builds. One team for both means one price to hold to.
    • Ask how the entrance stays usable every morning while the works go on.
  3. Before handover

    • Walk the reception in daylight and after dark to judge the lighting.
    • Check the finishes up close: stone joints, plaster and joinery edges.
    • Compare it with the floors above, so the building reads as one.

Certified, insured, compliant

  • ISO 9001 Quality Management
  • ISO 14001 Environmental Management
  • ISO 45001 Health & Safety Management
  • SafeContractor Approved
  • SSIP Safety Schemes in Procurement
  • CDM 2015 Principal Contractor
  • CIS Gross
  • Public Liability £10,000,000
  • Employers' Liability £10,000,000
  • Professional Indemnity available on request
  • Defects liability standard 12 months, extendable
  • Warranty up to 10 years available
  • Collateral warranties from our consultants & design team
  • ISO 9001 certified
  • ISO 14001 certified
  • ISO 45001 certified
  • SafeContractor approved
  • CHAS accredited
  • Constructionline Gold
  • TrustMark
  • RICS, Royal Institution of Chartered Surveyors
  • RIBA, Royal Institute of British Architects

What our clients say

See all reviews on Google
  • Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.

    Misha Levit

  • Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.

    Rhea Langford

  • I’d like to thank the team at Сraftex for the work they did on our office.
    It was really important for us to get the work done quickly, but without compromising on quality, as we regularly have clients and guests visiting and needed to move into the new office within a month.
    We spent around two weeks discussing and agreeing all the details before the work started. What I really appreciated was that everything we agreed beforehand was actually followed through during the job. The work was also completed on time.
    Thanks to the whole Сraftex team for a great job. I’d definitely use them again if we need any work done in the future.

    IURII PYLYPETS

  • We recently worked with Craftex and honestly couldn’t be happier with the results. From start to finish, the team was professional, reliable, and highly skilled. The quality of workmanship exceeded our expectations, and everything was completed on time and to a very high standard.
    Communication throughout the project was excellent, and they always went above and beyond to make sure we were satisfied. It’s rare to find a construction company that combines professionalism, attention to detail, and great customer service so well.
    Without a doubt, Craftex is one of the best construction companies we have ever worked with. Highly recommended to anyone looking for quality and trustworthy builders.

    Adam Miah

  • Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

    Pascal Hunt

  • Great company to work with as always. Super flexible at dealing with evolving requirements and fast deployment and execution.

    Akshay Khanna

  • Hired Craftex to do the full design and fit out of my gym in Chelsea. Super efficient and fast team. They gave the best price and a proper fast track program. We managed to open in less than 6 weeks with no headaches or surprises during construction. Quality was great, we had zero snags on completion. I’ve worked with a few companies before but these guys really impressed me from project management to how they treat the client. Top GGs.

    Александр Хоменко

  • I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.

    John Smith

  • Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

    Pawel Kamionka

  • Highly recommended!
    Craftex are the kind of fit-out contractors in London you can truly trust. From the very first meeting, they understood our vision and gave practical ideas to make the most of our space. They turned our old storage area into a clean, efficient, and well-organized warehouse. The team was professional, easy to work with, and clearly took pride in their work.

    Monika Kamionka

  • We brought in Craftex to refurb our London office and honestly, they made the whole thing way easier than we expected. They listened, suggested ideas we wouldn’t have thought of, and explained everything clearly. Not the cheapest quote we got, but the end result shows why, the place looks modern, clean, and our team actually enjoys being here now. Communication was spot-on too. No chasing and confusion, deadlines were hit. If you want people who genuinely care and don’t treat your project like “another job,” I’d recommend them.

    A Google User

  • Sviat and his team at Craftex were brilliant to work with on our office redesign. From the first meeting, they took the time to understand how we actually use the space rather than just pitching generic solutions. They came back with clever, practical ideas to maximise use of the space and get more employees and desks inside . Every step was handled professionally, and the process felt surprisingly smooth for a project of this size. They finished one week ahead of schedule, and the transformation is clear — our office feels brighter, more functional, and much more welcoming. I’d happily recommend Craftex to anyone who wants a reliable design team that also makes the journey enjoyable.

    Cucu Iulian

  • We recently worked with Sviat and the Craftex team on a complete warehouse refurbishment, and the results have been outstanding. From the very beginning, their team was professional, organized, and attentive to every detail. The project was completed on time and within budget, without disrupting our day-to-day operations.

    Simone Racaku

  • My experience with Craftex was excellent from beginning to end. They took the time to really listen to what I wanted and then offered practical suggestions that made the design even better. I always felt like they cared about creating a space that worked for me, not just one that looked nice on paper. The end result is an office that feels stylish, welcoming, and very functional for day-to-day work. The process itself was straightforward, well-managed, and never stressful. I’d definitely recommend Craftex if you’re looking for office design and build services in London — they made the whole journey a positive one.

    Ion Bounegru

  • I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

    Taron Papoyan

  • I had an amazing experience working with Sviat and the Craftex team on our office fit-out in London. They were always professional, responsive, and quick to offer the best advice whenever decisions needed to be made. I really appreciated how they balanced style with practicality — the office doesn’t just look fantastic, it works perfectly for our team. Everything was done with care and attention to detail, and the project never felt overwhelming because they managed it so well. Communication was clear from start to finish, and I always felt involved in the process. I would happily recommend Craftex to anyone looking for a trustworthy contractor.

    Artur Dvorak

  • Craftex carried out a warehouse fit-out for us, and I couldn’t be happier with the outcome. The space has been completely transformed into a highly organized and efficient environment that makes our daily operations much smoother.
    The team was professional but also very approachable — I always felt comfortable asking questions or giving feedback. They came up with smart, practical solutions that worked perfectly for our setup, and everything was explained clearly along the way.
    The best part was how they stuck to the agreed timeline, finishing on schedule without cutting corners. It’s rare to get both quality and reliability, but Craftex delivered both.

    Roma Shchukin

  • We’re extremely happy with Sviat and the Craftex team’s work. They suggested clever ideas, managed the project efficiently, and delivered a functional, modern space. The team was easy to communicate with and very professional throughout the process!

    Polina Lysenko

  • I can honestly say our office has been completely transformed thanks to Craftex. From the very first meeting, the team was approachable, professional, and full of creative ideas that really made sense for our business. They didn’t just focus on how the space would look but also how it would work for the team day-to-day. The new layout is efficient, modern, and welcoming, and you can tell they really thought about the details. The whole process was smooth and surprisingly stress-free. They kept me updated at every stage, which gave me confidence. I’m really happy with the results and wouldn’t hesitate to recommend them to anyone.

    Mykyta Khadzhynov

  • The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!

    Alaa Betar

  • We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.

    Ben Edell

  • These guys actually deliver. They handled our first industrial to residential conversion near Tower Bridge, turned an old warehouse into 4 modern flats. They stuck to the plan, kept the site clean and the timing was on point. No hidden extras, no drama, just a professional construction company in London that gets the job done.

    Богдан Главацкий

  • We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.

    Ardian Beleshi

  • This was a full high-end renovation of my Victorian rental apartment in Westminster, just off Sloane Square and Belgravia. The scope included full fit-out: electrics, plumbing, a new bespoke kitchen, and a luxury bathroom refurbishment. Craftex took care of everything and made the process easy. They weren’t the cheapest, but you can tell they really know what they’re doing when it comes to prime London property renovations.
    The team was professional, organised, and genuinely seemed to care about getting everything right. I was especially impressed with the quality of the finish – the attention to detail really shows in every corner.
    I’m very happy with the results and would definitely recommend Craftex to anyone looking for reliable, high-quality renovation work in Central London.

    Наталия Цимбалюк

  • I was stressed about timing since we had bookings lined up, but they smashed it. Even worked Saturday to finish the floor. My clients love the look — the beauty salon fit-out turned out exactly how I wanted. Couldn’t have pulled it off without their help. Genuinely appreciate the way they communicated throughout the refurbishment. If you need reliable help with beauty salon design or fit-out, especially in a place like Chelsea — these are the guys.

    Rami Jusupova

  • We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍

    Apartify Estates

  • Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.

    Hainro Eybers

  • Holistic therapy space fit-out
    Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.

    Dariia Shvyryda

  • Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody

    Nikita Nigai

  • Amazing experience with these guys. I trusted them my apartment in London and Business. They are always accurate, very professional, responsive and neat. They would always advice me right things for my best interest. I had luxury experience with them and I would definitely recommend Craftex to everyone.

    Motush Motushev

  • Could not be HAPPIER with Sviat and the Craftex team, they certainly showed me that they’re the number one office design company in London that we’ve had the pleasure of working with. They gave us a unique design just like we wanted, and we loved the first initial draft of the concept. Also have to give them props for Construction, I gave them a tight timeline as we needed to move our team in ASAP, so they pulled double shifts and I didn’t see a drop in quality. Will be to talking to the team when we move up to our next bigger office. Highly recommended A+++

    Mikhail Burdoev

  • Very professional company. Craftex did brilliant minimalistic design and completely refurbished my apartment to the highest quality.

    Vlad

  • I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away.
    We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP.
    We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care.
    We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.

    Lia Lavryk

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Office reception fit-out and refurbishment: your questions

How long does an office reception fit-out take?

The Portsoken House reception, 70 sq m, took 12 weeks with the design included, all of it worked at night and at weekends. On your building the time depends on the structural changes, the finishes and the hours the landlord allows for works.

What did the Portsoken House reception cost?

The project value was £450K for 70 sq m, covering the structural changes, the Italian stone and the bespoke joinery. We price your reception after a survey, as a fixed-price proposal.

What is the difference between a reception fit-out and a reception refurbishment?

A fit-out makes a space work for the people who use it: layout, services and finishes. A refurbishment renews a space that is worn or dated. This reception was both: structural changes and new glazing, then new walls, stone, joinery and lighting.

Does a reception fit-out include the reception desk?

It can. Here bespoke joinery was made for the space as part of the same contract, alongside the Italian stone floor. On your reception we can design and build the desk with the rest of the works, so one team answers for how it all fits.

Do you fit out whole office buildings as well?

Yes. At Portsoken House the reception came after a full refurbishment of the second and eighth floors, by the same team, so the entrance and the offices were planned as one building.

Can a reception be refurbished while the building stays open?

Yes. Here the floors above were let and in use, so every shift was planned for nights and weekends and no tenant was interrupted.

What does a reception fit-out include?

On this job: structural work and new glazing, rebuilt lift surrounds, plastered wall panels, a stone floor, bespoke joinery and new lighting. Yours may need less; we survey it and list only what it needs.

What makes a good office reception design?

Daylight first, then a few durable materials, then lighting that ties the entrance to the floors above. Here the new glazing brought the light in, stone and joinery carry the finish, and the fittings match the offices upstairs.

Do you design receptions as well as build them?

Yes. Our in-house team designed this one with the client and our site team built it, as with the offices upstairs. One company answered for the drawings, the price and the finish.

Do you fit out office receptions across London?

Yes, across London, from a single reception to whole office buildings, designed and built by one team. Where the building stays open, we plan the works for nights and weekends, as we did at Portsoken House.

Planning a reception or office fit-out in London?

Craftex designs and rebuilds receptions and offices as one accountable team, around the people already in the building.

Unit 5, 160 Buckingham Palace Road, London SW1W 9TR

info@craftex.co.uk

MESSAGE US ON WHATSAPP

Your details are used only to answer your enquiry (privacy).

WhatsApp us