The retained façades of Slingsby Place held by full-height scaffold on every floor, around the cleared site, with Covent Garden chimneys behind
Led by Martin Hickey, our Preconstruction Director

Slingsby Place, Covent Garden

Façade retention in Covent Garden: the building taken out, its faces kept, a new base laid

Project Director

50+ years in construction:
Martin Hickey led this job

The Yards, Covent Garden

  • 2façades kept standing, street and courtyard
  • 1tower crane, put up inside the footprint

Take the building out, keep its face

Slingsby Place sits in The Yards, the courtyards between Long Acre and St Martin's Lane in Covent Garden.

The job: strip an old building back to its shell, demolish the inside, carry out structural works behind façades that had to stay, and leave a new base for the next building. All on one of the tightest sites in central London.

The works were led by Martin Hickey as Project Director. He is now our Preconstruction Director.

The Slingsby Place WC2 street sign on a brick wall above the site entrance, with crane parts and barriers in the courtyard below

Façade retention in Covent Garden: the project

The Yards, WC2
Covent Garden
Kept standing
Two façades
The works
Strip-out, structure
Project Director
Martin Hickey

Keeping a façade while you rebuild behind it?

Send us your drawings and any surveys. Martin Hickey, our Preconstruction Director, reads them first, free and with no obligation.

Retained façade: keeping the walls standing

Full-height scaffold bracing the retained façade from inside the site, with a blue tower crane mast in front

Surveyed, then held from top to bottom

The street and courtyard walls had to stay exactly where they were. Before any demolition, they were surveyed, and a full-height temporary works and scaffold system was designed and put up to hold them.

That system stayed until the new structure could carry the load.

Demolition behind retained façades at Slingsby Place: an excavator works on the cleared ground floor while full-height scaffold holds the old walls

Taken down one floor at a time

The demolition went floor by floor, so the kept walls were supported at every stage and never stood on their own.

Each level got props, edge protection and access scaffolds as its floor came out.

Planning the works on a live Covent Garden street

A mobile crane set up on its outriggers in a paved Covent Garden street, behind barriers, with a marshal in hi-vis

No room to store anything, neighbours on every wall

Covent Garden leaves a site almost no space: courtyards full of people, narrow streets, strict delivery times, and shops, restaurants and offices open all around.

So planning came first: surveys of the old structure, a demolition order, a temporary works design and a logistics plan agreed with the council.

Blue tower crane sections on a flatbed lorry in a narrow street of Victorian buildings

Deliveries booked to the allowed hours

Every delivery was booked into the allowed hours and called off just in time, so the site never stood waiting.

Dust and noise were controlled every day, and protected routes kept neighbours and the public safe.

A tight site with neighbours all round?

Tell us where it is. We plan deliveries, cranes, road closures and protection before day one.

The tower crane: from the street to inside the building

With no room beside the building, the tower crane went up inside the footprint. A mobile crane working from the street under a planned road closure lifted its mast and jib in, with traffic marshals and pedestrian management in place.

A lorry loaded with blue crane sections on a narrow street, with a pedestrian on the pavement beside it
ArrivingMast sections brought in by road
Two operatives in hard hats guiding a blue mast section onto the one below, scaffold behind them
Going upMast sections bolted together on site

Structural alterations: a new base for the next building

Looking down on the cleared site: the base of a blue tower crane mast on a new concrete slab, with operatives in hi-vis around it

New slabs and foundations

With the floors and inner structure gone, new slabs and foundations were formed at the base of the building, ready for the new structure.

Two operatives on the new ground slab inside the retained walls, with scaffold and a site hoarding behind them

The result: a safe shell, façades intact

The building was taken back to a stable, supported shell, its façades intact and a new base in place for the new building.

Demolition, temporary works, structure and crane work ran as one programme: no gaps between packages, one order of work, one number to call.

On site at Slingsby Place

Demolition behind a retained façade: four problems, four answers

ConstraintHow it was handled
Restricted central-London accessWindow-timed logistics, with materials called off as needed
Façades that had to stayTemporary works first, kept until the new structure took over
Neighbours on every sideFloor-by-floor sequencing, dust and noise control, protected routes
Heavy lifts in a busy streetA planned road closure, traffic marshals and pedestrian management

Already have a scheme or a quote?

Send it to us. Martin checks it against what the build will really cost and how it can be built, and we will aim to beat the price.

Our team

  • in

Certified, insured, compliant

  • ISO 9001 Quality Management
  • ISO 14001 Environmental Management
  • ISO 45001 Health & Safety Management
  • SafeContractor Approved
  • SSIP Safety Schemes in Procurement
  • CDM 2015 Principal Contractor
  • CIS Gross
  • Public Liability £10,000,000
  • Employers' Liability £10,000,000
  • Professional Indemnity available on request
  • Defects liability standard 12 months, extendable
  • Warranty up to 10 years available
  • Collateral warranties from our consultants & design team
  • ISO 9001 certified
  • ISO 14001 certified
  • ISO 45001 certified
  • SafeContractor approved
  • CHAS accredited
  • Constructionline Gold
  • TrustMark
  • RICS, Royal Institution of Chartered Surveyors
  • RIBA, Royal Institute of British Architects

How it was planned

Plan. Build. Hand over.

  1. Pre-construction

    • Structural surveys of the existing building and its façades
    • Temporary works for the façades signed off before demolition
    • Demolition programme set floor by floor
    • Crane lifts, logistics and road closures agreed with the local authority
  2. The works

    • Soft strip, then demolition behind the retained façades
    • Propping and edge protection on each floor
    • Tower crane lifted in from the street
    • New base formed for the next phase
  3. Handover

    • Façades retained and protected throughout
    • Neighbouring shops and restaurants kept open
    • One point of contact, no interface risk
    • A shell ready for the new structure

What our clients say

See all reviews on Google
  • Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.

    Misha Levit

  • Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.

    Rhea Langford

  • I’d like to thank the team at Сraftex for the work they did on our office.
    It was really important for us to get the work done quickly, but without compromising on quality, as we regularly have clients and guests visiting and needed to move into the new office within a month.
    We spent around two weeks discussing and agreeing all the details before the work started. What I really appreciated was that everything we agreed beforehand was actually followed through during the job. The work was also completed on time.
    Thanks to the whole Сraftex team for a great job. I’d definitely use them again if we need any work done in the future.

    IURII PYLYPETS

  • We recently worked with Craftex and honestly couldn’t be happier with the results. From start to finish, the team was professional, reliable, and highly skilled. The quality of workmanship exceeded our expectations, and everything was completed on time and to a very high standard.
    Communication throughout the project was excellent, and they always went above and beyond to make sure we were satisfied. It’s rare to find a construction company that combines professionalism, attention to detail, and great customer service so well.
    Without a doubt, Craftex is one of the best construction companies we have ever worked with. Highly recommended to anyone looking for quality and trustworthy builders.

    Adam Miah

  • Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

    Pascal Hunt

  • Great company to work with as always. Super flexible at dealing with evolving requirements and fast deployment and execution.

    Akshay Khanna

  • Hired Craftex to do the full design and fit out of my gym in Chelsea. Super efficient and fast team. They gave the best price and a proper fast track program. We managed to open in less than 6 weeks with no headaches or surprises during construction. Quality was great, we had zero snags on completion. I’ve worked with a few companies before but these guys really impressed me from project management to how they treat the client. Top GGs.

    Александр Хоменко

  • I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.

    John Smith

  • Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

    Pawel Kamionka

  • Highly recommended!
    Craftex are the kind of fit-out contractors in London you can truly trust. From the very first meeting, they understood our vision and gave practical ideas to make the most of our space. They turned our old storage area into a clean, efficient, and well-organized warehouse. The team was professional, easy to work with, and clearly took pride in their work.

    Monika Kamionka

  • We brought in Craftex to refurb our London office and honestly, they made the whole thing way easier than we expected. They listened, suggested ideas we wouldn’t have thought of, and explained everything clearly. Not the cheapest quote we got, but the end result shows why, the place looks modern, clean, and our team actually enjoys being here now. Communication was spot-on too. No chasing and confusion, deadlines were hit. If you want people who genuinely care and don’t treat your project like “another job,” I’d recommend them.

    A Google User

  • Sviat and his team at Craftex were brilliant to work with on our office redesign. From the first meeting, they took the time to understand how we actually use the space rather than just pitching generic solutions. They came back with clever, practical ideas to maximise use of the space and get more employees and desks inside . Every step was handled professionally, and the process felt surprisingly smooth for a project of this size. They finished one week ahead of schedule, and the transformation is clear — our office feels brighter, more functional, and much more welcoming. I’d happily recommend Craftex to anyone who wants a reliable design team that also makes the journey enjoyable.

    Cucu Iulian

  • We recently worked with Sviat and the Craftex team on a complete warehouse refurbishment, and the results have been outstanding. From the very beginning, their team was professional, organized, and attentive to every detail. The project was completed on time and within budget, without disrupting our day-to-day operations.

    Simone Racaku

  • My experience with Craftex was excellent from beginning to end. They took the time to really listen to what I wanted and then offered practical suggestions that made the design even better. I always felt like they cared about creating a space that worked for me, not just one that looked nice on paper. The end result is an office that feels stylish, welcoming, and very functional for day-to-day work. The process itself was straightforward, well-managed, and never stressful. I’d definitely recommend Craftex if you’re looking for office design and build services in London — they made the whole journey a positive one.

    Ion Bounegru

  • I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.

    Taron Papoyan

  • I had an amazing experience working with Sviat and the Craftex team on our office fit-out in London. They were always professional, responsive, and quick to offer the best advice whenever decisions needed to be made. I really appreciated how they balanced style with practicality — the office doesn’t just look fantastic, it works perfectly for our team. Everything was done with care and attention to detail, and the project never felt overwhelming because they managed it so well. Communication was clear from start to finish, and I always felt involved in the process. I would happily recommend Craftex to anyone looking for a trustworthy contractor.

    Artur Dvorak

  • Craftex carried out a warehouse fit-out for us, and I couldn’t be happier with the outcome. The space has been completely transformed into a highly organized and efficient environment that makes our daily operations much smoother.
    The team was professional but also very approachable — I always felt comfortable asking questions or giving feedback. They came up with smart, practical solutions that worked perfectly for our setup, and everything was explained clearly along the way.
    The best part was how they stuck to the agreed timeline, finishing on schedule without cutting corners. It’s rare to get both quality and reliability, but Craftex delivered both.

    Roma Shchukin

  • We’re extremely happy with Sviat and the Craftex team’s work. They suggested clever ideas, managed the project efficiently, and delivered a functional, modern space. The team was easy to communicate with and very professional throughout the process!

    Polina Lysenko

  • I can honestly say our office has been completely transformed thanks to Craftex. From the very first meeting, the team was approachable, professional, and full of creative ideas that really made sense for our business. They didn’t just focus on how the space would look but also how it would work for the team day-to-day. The new layout is efficient, modern, and welcoming, and you can tell they really thought about the details. The whole process was smooth and surprisingly stress-free. They kept me updated at every stage, which gave me confidence. I’m really happy with the results and wouldn’t hesitate to recommend them to anyone.

    Mykyta Khadzhynov

  • The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!

    Alaa Betar

  • We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.

    Ben Edell

  • These guys actually deliver. They handled our first industrial to residential conversion near Tower Bridge, turned an old warehouse into 4 modern flats. They stuck to the plan, kept the site clean and the timing was on point. No hidden extras, no drama, just a professional construction company in London that gets the job done.

    Богдан Главацкий

  • We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.

    Ardian Beleshi

  • This was a full high-end renovation of my Victorian rental apartment in Westminster, just off Sloane Square and Belgravia. The scope included full fit-out: electrics, plumbing, a new bespoke kitchen, and a luxury bathroom refurbishment. Craftex took care of everything and made the process easy. They weren’t the cheapest, but you can tell they really know what they’re doing when it comes to prime London property renovations.
    The team was professional, organised, and genuinely seemed to care about getting everything right. I was especially impressed with the quality of the finish – the attention to detail really shows in every corner.
    I’m very happy with the results and would definitely recommend Craftex to anyone looking for reliable, high-quality renovation work in Central London.

    Наталия Цимбалюк

  • I was stressed about timing since we had bookings lined up, but they smashed it. Even worked Saturday to finish the floor. My clients love the look — the beauty salon fit-out turned out exactly how I wanted. Couldn’t have pulled it off without their help. Genuinely appreciate the way they communicated throughout the refurbishment. If you need reliable help with beauty salon design or fit-out, especially in a place like Chelsea — these are the guys.

    Rami Jusupova

  • We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍

    Apartify Estates

  • Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.

    Hainro Eybers

  • Holistic therapy space fit-out
    Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.

    Dariia Shvyryda

  • Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody

    Nikita Nigai

  • Amazing experience with these guys. I trusted them my apartment in London and Business. They are always accurate, very professional, responsive and neat. They would always advice me right things for my best interest. I had luxury experience with them and I would definitely recommend Craftex to everyone.

    Motush Motushev

  • Could not be HAPPIER with Sviat and the Craftex team, they certainly showed me that they’re the number one office design company in London that we’ve had the pleasure of working with. They gave us a unique design just like we wanted, and we loved the first initial draft of the concept. Also have to give them props for Construction, I gave them a tight timeline as we needed to move our team in ASAP, so they pulled double shifts and I didn’t see a drop in quality. Will be to talking to the team when we move up to our next bigger office. Highly recommended A+++

    Mikhail Burdoev

  • Very professional company. Craftex did brilliant minimalistic design and completely refurbished my apartment to the highest quality.

    Vlad

  • I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away.
    We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP.
    We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care.
    We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.

    Lia Lavryk

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Façade retention and structural works: your questions

What is façade retention?

Façade retention means keeping the outside walls of an old building, often for planning or heritage reasons, while the inside is taken out and rebuilt. The walls are braced the whole time.

Who led the works at Slingsby Place?

Martin Hickey ran them from start to finish as Project Director. Today he leads pre-construction at Craftex and brings more than 50 years in construction.

Where is Slingsby Place?

Off Long Acre in Covent Garden, central London WC2, in a group of small pedestrian courtyards known as The Yards.

Can neighbouring shops and restaurants stay open during the works?

Yes. Around Slingsby Place they stayed open throughout. That takes daily control of dust, noise and access, and routes that keep the public away from the work.

What does pre-construction cover on a job like this?

Structural surveys, the order of demolition, the temporary works design and the site logistics, all settled before work starts. Our pre-construction services begin with a free cost and buildability review of your drawings.

How is a façade kept standing while the building behind it is demolished?

It is surveyed first, then braced by a temporary works system designed for it before any demolition begins. The building comes out in a set order, and the bracing stays until the new structure carries the wall.

Was Slingsby Place a Craftex project?

No. It is shown as the earlier experience of Martin Hickey, our Preconstruction Director. That experience now goes into every scheme he reviews for our clients.

How do you get a tower crane onto a site with no space around it?

At Slingsby Place it went up inside the building's own footprint. The sections came by lorry, and a mobile crane in the street lifted them in during a planned road closure.

How long does façade retention take?

It depends on the size of the building and how many floors come out. The bracing goes up first and stays until the new frame is in, so plan for it from the start.

Has Craftex delivered commercial projects of its own?

Yes, for example Portsoken House in Aldgate, Beaumont House in Kensington, a warehouse fit-out in Hackney and the Banbury warehouse. We work across central London, including Westminster. See also commercial refurbishment, or contact us.

Speed and proactivity, proven on our projects

We plan ahead: every change is priced and agreed in writing before the work is done.

  • 3 weeks

    to refurbish a 750 m² office for a fast-growing UK tech company, on site within two weeks of the first call.

  • 8 weeks

    to design and build the 2,500 m² Banbury warehouse, with the site kept running.

  • 8 weeks

    on site at Drake's flagship on Savile Row, with the shop open throughout.

Speak to us and you will see how we work.

We reply within one hour, Monday to Saturday, 8am to 6pm. Urgent? Message us on WhatsApp: we reply straight away, any day.

Planning works behind a retained façade in London?

Craftex plans the structure, the logistics and the programme before work starts, as one accountable team.