CDM 2015 Client Duties on a Fit-Out: A Plain Guide for Business Owners

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read

Office workplace with acoustic ceiling baffles, a focus table by the window, lounge chairs on a round rug and a glazed meeting room

The short answer

If your business pays for a fit-out, CDM 2015 makes you the client. The client duties stay with you, even when a contractor does most of the work.

  1. Make suitable arrangements, with enough time and resources, and share the information you hold.
  2. With more than one contractor, appoint a principal designer and principal contractor in writing.
  3. Make sure a construction phase plan exists before work starts.
  4. Keep the health and safety file after handover.

Most business owners do not know they have taken on legal duties. Then someone asks for the asbestos survey.

That is understandable. You are opening a restaurant or moving 150 people onto a new floor, not running a building site. But CDM 2015 applies to fitting out, alteration, renovation and redecoration. It also covers installing or removing building services.

So almost every commercial fit-out is construction work under the regulations. The business paying for it carries the CDM 2015 client duties. This guide explains them in plain English, and which parts a competent contractor does for you. Planning works now? Book a site visit and we will walk you through it on site.

Who counts as the client under CDM 2015

Under CDM 2015, a client is anyone for whom a construction project is carried out. A commercial client has the work done as part of a business, whether or not for profit. That includes:

  • a company fitting out its new office or warehouse;
  • a restaurant or pub operator refitting its premises;
  • a landlord refurbishing common parts or a vacant floor;
  • a clinic, school, hotel or charity doing building work.

Sometimes a landlord and a tenant both fund the works. They can agree in writing which one is treated as the only client. People having work done on their own home are treated differently. That is outside this guide.

The CDM 2015 client duties in plain English

Regulation 4 sets out the core client duties. Here is what each one means on a fit-out.

CDM 2015 client duties and what they mean on a fit-out
What the regulations sayWhat it means on your fit-out
Make suitable arrangements for managing the project, with enough time and resourcesDo not squeeze the programme or budget so hard that work cannot be done safely
Keep risks as low as reasonably practicable and provide welfare facilitiesToilets, washing, drinking water and a place to rest and change
Maintain and review the arrangements throughoutIf the scope or sequence changes, the arrangements change too
Provide pre-construction information to every designer and contractorHand over the asbestos survey, drawings, services information and building rules
Ensure a construction phase plan exists before work startsNo plan, no start; the contractor writes it, you check it exists
Ensure the principal designer prepares a health and safety fileThe record of the building as left; you keep it
Take reasonable steps so the principal designer and contractor do their jobsAsk questions, read the reports and act on them

When to appoint a principal designer and principal contractor

Regulation 5 is the one that catches people out. It applies when there is more than one contractor. It also applies when more than one contractor is reasonably foreseeable. You must then appoint, in writing:

  • a principal designer, a designer with control over the pre-construction phase; and
  • a principal contractor.

Make the appointments as soon as practicable, and before the construction phase begins. If you do not, you take on their duties yourself.

On a typical fit-out, more than one contractor is almost certain. Shopfitters, electricians, mechanical engineers, flooring teams and decorators are often separate firms. Furniture installers and IT cabling teams count too if they work on site.

Notifying HSE with form F10

Regulation 6 makes a project notifiable if the construction work is scheduled to:

  • last longer than 30 working days and have more than 20 workers on site at the same time; or
  • exceed 500 person days.

If it is notifiable, the client must notify HSE in writing before the construction phase begins. The notice must also be displayed on site. Often the principal contractor submits the form for you. But the duty is yours, so ask to see the confirmation.

Many small fit-outs are not notifiable. The client duties still apply in full either way.

Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.

Pascal Hunt, Google reviewSee all reviews on Google

Pre-construction information matters most

Most incidents and delays on fit-outs trace back to something nobody knew about the building. The pre-construction information prevents that. Gather these items early.

  1. Asbestos. HSE says to assume asbestos in any building built or refurbished before 2000. Works that disturb the fabric need a more intrusive survey before they start.
  2. Existing drawings and any earlier health and safety file.
  3. Services. Live electrical, gas, water and data routes, fire alarm zones and sprinklers.
  4. Structure. Floor loadings, known defects and limits on drilling or fixing.
  5. Building rules. Working hours, noise limits, lift bookings, permits and hot works rules.
  6. Occupied areas. Where staff, customers or other tenants will be, and when.
  7. Your own needs. Phasing, security and IT cut-over dates.

If you are a tenant, much of this sits with the landlord or managing agent. Ask for it as early as the licence for alterations.

What a good construction phase plan looks like

The plan should fit your building and your programme. It should not be a generic document with your address pasted in. In a working building, look for:

Office building lift lobby with a dark metal lift surround, rectangular ceiling lights and lit stair nosings
Portsoken House, Aldgate: the reception and lift surrounds rebuilt at nights and weekends.
  • how the site is separated from occupied areas, with hoardings, locked doors and dust screens;
  • deliveries and waste: routes, times, lift protection and loading bay bookings;
  • fire safety during the works: clear escape routes, alarm isolation and hot works permits;
  • when noisy and dusty work happens, and how it is controlled;
  • what asbestos was found, and what is being done about it;
  • emergency contacts and first aid.

At Beaumont House in Kensington, we had three weeks to refurbish 750 sq m of offices. Other businesses in the building kept working. The building's management team were particularly happy with how we organised noise, waste and deliveries. That is the part of the plan an occupied building lives with every day.

Sometimes the plan has to move the work itself out of hours. At the Portsoken House reception in Aldgate, the rest of the building was let and in use. We rebuilt the 70 sq m reception in 12 weeks, working only at nights and weekends, so no tenant was interrupted.

The health and safety file at handover

At the end, the principal designer prepares the health and safety file. You keep it available for anyone who needs it later. If you sell or hand over your interest in the building, the file goes with it.

On a tenant fit-out, your next contractor or your landlord will ask for it. Typical contents:

  • as-built drawings of what was installed;
  • remaining hazards the next team must know, such as asbestos left in place;
  • key structural and services information;
  • materials and products that affect future work.

CDM 2015 and the building regulations dutyholders

Since 1 October 2023, the Building Regulations 2010 have their own dutyholder roles. They include a client, a principal designer and a principal contractor for building regulations compliance. These are separate from the CDM roles, even though the names match.

On many fit-outs, the same firms hold both roles. The appointments should say so. Our guide to building regulations for office fit-outs covers that side.

What happens if the duties are not met

Breaching CDM 2015 is a criminal offence under health and safety law. HSE inspectors can stop work. More often, gaps show up as delays. A contractor cannot start without a plan. An asbestos find halts the strip-out. A missing file holds up a sale. The duties cost less at the start than half way through.

A client checklist for your fit-out

For help picking a team, see our tips on choosing a commercial contractor. Our comparison of design and build vs traditional procurement explains who carries what under each route. For offices, see our office fit-out in London service.

We take on construction projects from £100,000. Want one team to carry the coordination? Book a site visit and we will set up the CDM paperwork with you from day one.

CDM 2015 client checklist

  • Confirm you are the client, or agree in writing who is.
  • Appoint competent designers and contractors, and check their competence.
  • With more than one contractor, appoint a principal designer and principal contractor in writing.
  • Commission the asbestos survey and gather building information early.
  • Allow realistic time for design, approvals and mobilisation.
  • Check whether the project is notifiable and that HSE has been told.
  • Do not let work start until the construction phase plan exists.
  • Agree welfare facilities for the workforce.
  • Stay involved: read the reports and act on them.
  • Keep the health and safety file after handover.

Frequently asked questions

Does CDM 2015 apply to a fit-out?

Yes. CDM 2015 defines construction work to include fitting out, alteration, renovation, redecoration and the installation or removal of building services. Almost every commercial fit-out or refurbishment is covered.

Who is the client under CDM 2015 on a tenant fit-out?

The organisation the project is carried out for, normally the tenant paying for the fit-out. If the landlord and tenant both commission works, they can agree in writing that one of them is treated as the only client.

When do I need to appoint a principal designer and principal contractor?

When there is more than one contractor, or it is reasonably foreseeable that more than one will work on the project. The appointments must be in writing and made before the construction phase begins.

Do I need to notify HSE about my fit-out?

Only if the work is scheduled to last longer than 30 working days with more than 20 workers on site at the same time, or to exceed 500 person days. The client duties apply either way.

Can my contractor take on my CDM client duties?

No. You can appoint competent people to help, and they will do most of the practical work. But the client duties stay with the client. Make sure the appointments are in writing and check the key documents exist.

Do I need an asbestos survey before an office fit-out?

If the building was built or refurbished before 2000, assume it contains asbestos. Works that disturb the fabric need a more intrusive survey before they start. It forms part of the pre-construction information.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Commissioning a fit-out and want the paperwork right from day one?

Our design and build team surveys the building, sets up the plan for the works and takes on the principal contractor role. Book a site visit.

WhatsApp us