CDM 2015 Client Duties on a Fit-Out: A Plain Guide for Business Owners
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
If your business pays for a fit-out, CDM 2015 makes you the client. The client duties stay with you, even when a contractor does most of the work.
- Make suitable arrangements, with enough time and resources, and share the information you hold.
- With more than one contractor, appoint a principal designer and principal contractor in writing.
- Make sure a construction phase plan exists before work starts.
- Keep the health and safety file after handover.
Most business owners do not know they have taken on legal duties. Then someone asks for the asbestos survey.
That is understandable. You are opening a restaurant or moving 150 people onto a new floor, not running a building site. But CDM 2015 applies to fitting out, alteration, renovation and redecoration. It also covers installing or removing building services.
So almost every commercial fit-out is construction work under the regulations. The business paying for it carries the CDM 2015 client duties. This guide explains them in plain English, and which parts a competent contractor does for you. Planning works now? Book a site visit and we will walk you through it on site.
Who counts as the client under CDM 2015
Under CDM 2015, a client is anyone for whom a construction project is carried out. A commercial client has the work done as part of a business, whether or not for profit. That includes:
- a company fitting out its new office or warehouse;
- a restaurant or pub operator refitting its premises;
- a landlord refurbishing common parts or a vacant floor;
- a clinic, school, hotel or charity doing building work.
Sometimes a landlord and a tenant both fund the works. They can agree in writing which one is treated as the only client. People having work done on their own home are treated differently. That is outside this guide.
The CDM 2015 client duties in plain English
Regulation 4 sets out the core client duties. Here is what each one means on a fit-out.
| What the regulations say | What it means on your fit-out |
|---|---|
| Make suitable arrangements for managing the project, with enough time and resources | Do not squeeze the programme or budget so hard that work cannot be done safely |
| Keep risks as low as reasonably practicable and provide welfare facilities | Toilets, washing, drinking water and a place to rest and change |
| Maintain and review the arrangements throughout | If the scope or sequence changes, the arrangements change too |
| Provide pre-construction information to every designer and contractor | Hand over the asbestos survey, drawings, services information and building rules |
| Ensure a construction phase plan exists before work starts | No plan, no start; the contractor writes it, you check it exists |
| Ensure the principal designer prepares a health and safety file | The record of the building as left; you keep it |
| Take reasonable steps so the principal designer and contractor do their jobs | Ask questions, read the reports and act on them |
When to appoint a principal designer and principal contractor
Regulation 5 is the one that catches people out. It applies when there is more than one contractor. It also applies when more than one contractor is reasonably foreseeable. You must then appoint, in writing:
- a principal designer, a designer with control over the pre-construction phase; and
- a principal contractor.
Make the appointments as soon as practicable, and before the construction phase begins. If you do not, you take on their duties yourself.
On a typical fit-out, more than one contractor is almost certain. Shopfitters, electricians, mechanical engineers, flooring teams and decorators are often separate firms. Furniture installers and IT cabling teams count too if they work on site.
Notifying HSE with form F10
Regulation 6 makes a project notifiable if the construction work is scheduled to:
- last longer than 30 working days and have more than 20 workers on site at the same time; or
- exceed 500 person days.
If it is notifiable, the client must notify HSE in writing before the construction phase begins. The notice must also be displayed on site. Often the principal contractor submits the form for you. But the duty is yours, so ask to see the confirmation.
Many small fit-outs are not notifiable. The client duties still apply in full either way.
Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.
Pre-construction information matters most
Most incidents and delays on fit-outs trace back to something nobody knew about the building. The pre-construction information prevents that. Gather these items early.
- Asbestos. HSE says to assume asbestos in any building built or refurbished before 2000. Works that disturb the fabric need a more intrusive survey before they start.
- Existing drawings and any earlier health and safety file.
- Services. Live electrical, gas, water and data routes, fire alarm zones and sprinklers.
- Structure. Floor loadings, known defects and limits on drilling or fixing.
- Building rules. Working hours, noise limits, lift bookings, permits and hot works rules.
- Occupied areas. Where staff, customers or other tenants will be, and when.
- Your own needs. Phasing, security and IT cut-over dates.
If you are a tenant, much of this sits with the landlord or managing agent. Ask for it as early as the licence for alterations.
What a good construction phase plan looks like
The plan should fit your building and your programme. It should not be a generic document with your address pasted in. In a working building, look for:
- how the site is separated from occupied areas, with hoardings, locked doors and dust screens;
- deliveries and waste: routes, times, lift protection and loading bay bookings;
- fire safety during the works: clear escape routes, alarm isolation and hot works permits;
- when noisy and dusty work happens, and how it is controlled;
- what asbestos was found, and what is being done about it;
- emergency contacts and first aid.
At Beaumont House in Kensington, we had three weeks to refurbish 750 sq m of offices. Other businesses in the building kept working. The building's management team were particularly happy with how we organised noise, waste and deliveries. That is the part of the plan an occupied building lives with every day.
Sometimes the plan has to move the work itself out of hours. At the Portsoken House reception in Aldgate, the rest of the building was let and in use. We rebuilt the 70 sq m reception in 12 weeks, working only at nights and weekends, so no tenant was interrupted.
The health and safety file at handover
At the end, the principal designer prepares the health and safety file. You keep it available for anyone who needs it later. If you sell or hand over your interest in the building, the file goes with it.
On a tenant fit-out, your next contractor or your landlord will ask for it. Typical contents:
- as-built drawings of what was installed;
- remaining hazards the next team must know, such as asbestos left in place;
- key structural and services information;
- materials and products that affect future work.
CDM 2015 and the building regulations dutyholders
Since 1 October 2023, the Building Regulations 2010 have their own dutyholder roles. They include a client, a principal designer and a principal contractor for building regulations compliance. These are separate from the CDM roles, even though the names match.
On many fit-outs, the same firms hold both roles. The appointments should say so. Our guide to building regulations for office fit-outs covers that side.
What happens if the duties are not met
Breaching CDM 2015 is a criminal offence under health and safety law. HSE inspectors can stop work. More often, gaps show up as delays. A contractor cannot start without a plan. An asbestos find halts the strip-out. A missing file holds up a sale. The duties cost less at the start than half way through.
A client checklist for your fit-out
For help picking a team, see our tips on choosing a commercial contractor. Our comparison of design and build vs traditional procurement explains who carries what under each route. For offices, see our office fit-out in London service.
We take on construction projects from £100,000. Want one team to carry the coordination? Book a site visit and we will set up the CDM paperwork with you from day one.
CDM 2015 client checklist
- Confirm you are the client, or agree in writing who is.
- Appoint competent designers and contractors, and check their competence.
- With more than one contractor, appoint a principal designer and principal contractor in writing.
- Commission the asbestos survey and gather building information early.
- Allow realistic time for design, approvals and mobilisation.
- Check whether the project is notifiable and that HSE has been told.
- Do not let work start until the construction phase plan exists.
- Agree welfare facilities for the workforce.
- Stay involved: read the reports and act on them.
- Keep the health and safety file after handover.