For office occupiers and landlords
Building Regulations for an Office Fit-Out: What Applies and When You Need Approval
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read
The short answer
Most office fit-outs in England need building regulations approval. Offices are workplaces under the Fire Safety Order, so you must apply with full plans, not a building notice.
- New partitions, escape route changes and new services count as building work.
- Fire safety, energy (Part L), access (Part M) and toilets (Part T) shape the design.
- Building control inspects during the works and issues a completion certificate.
- New energy standards apply to work notified from 24 March 2027.
Here is the problem for most occupiers. The lease is signed and the furniture is ordered. Nobody has asked who is handling building control.
That matters, because building regulations for an office fit-out are not a formality. Approval is tied to the fire strategy, the escape routes, the energy rules and the toilets you provide. Get it late and you may redesign ceilings after they are built.
This guide covers England. It explains what counts as building work and which parts of the regulations apply to an office fit out and refurbishment. It also covers how approval works and what changes in 2027. Planning a fit-out now? Book a site visit and we will check what your floor needs.
When building regulations apply to an office fit-out
The Building Regulations 2010 apply to "building work". On a fit-out, three parts of that definition usually apply.
- Material alterations. An alteration is material if it would make the building less compliant on certain requirements. These include structure (Part A), fire safety (B1, B3, B4, B5), access (Part M) and toilets (Part T).
- Controlled services and fittings. New or extended heating, cooling, mechanical ventilation, lighting and sanitary installations.
- Material change of use. For example, turning another use into offices.
In practice, new meeting rooms change escape routes and fire separation. A new air conditioning or lighting system is a controlled service. Moving toilets touches Parts M and T. That is why most office fit-outs need approval. Redecoration and new furniture on their own usually do not.
| Typical fit-out item | Building regulations relevance |
|---|---|
| New partitions, meeting rooms, cellular offices | Escape routes, travel distances, fire separation, Part M access |
| Removing or altering walls | Structure (Part A), fire separation |
| New suspended ceilings or raised floors | Fire spread, cavity barriers, linings |
| New or altered lighting | Energy efficiency (Part L) |
| Air conditioning, heating, ventilation changes | Part L, ventilation (Part F) |
| New or relocated toilets and kitchens | Part M, Part T, drainage (Part H), ventilation |
| New doors on escape routes | Fire doors, access control release, door widths |
| Fire alarm and emergency lighting changes | Means of warning and escape (B1) |
Full plans, not a building notice
There are two common routes to approval. A building notice lets you start on notice and be inspected as you go. A full plans application has the drawings checked before work starts.
For offices, you do not get the choice. A building notice cannot be used for work on a building covered by the Regulatory Reform (Fire Safety) Order 2005. That Order applies to workplaces, so offices need a full plans application.
You can apply to the council's building control team. Since April 2024, you can also use a registered building control approver.
Fire safety drives most of the design
Approved Document B Volume 2 is the main guidance for buildings other than homes. On an office fit-out, these points most often change the design.
- Escape routes and travel distances. New rooms lengthen the walk to a stair. An open floor that worked can fail once rooms go in.
- Inner rooms. A room you can only leave through another room has extra conditions.
- Fire separation and cavity barriers. Partitions that stop at a suspended ceiling need the right detailing and fire stopping.
- Fire doors. Doors on protected routes need the right rating and self-closers.
- Alarm and emergency lighting. New rooms change the detector, sounder and lighting layouts.
- Linings. Feature timber, acoustic panels and fabric finishes must meet reaction-to-fire classes.
In a multi-let building, your changes must also fit the landlord's fire strategy. That is why the landlord's surveyor will want to see them. See our guide to the licence for alterations.
Two duties sit outside building control. The responsible person must review the fire risk assessment after the works. And where regulation 38 applies, fire safety information must be handed over at completion. On any fit-out, ask for the updated fire strategy, as-built drawings and the alarm and emergency lighting certificates.
Part L sets the energy rules for new services
Part L covers the "fixed building services" you install or replace. That means heating, hot water, air conditioning, mechanical ventilation and lighting. The new systems must meet minimum efficiencies and have suitable controls. They must be commissioned and handed over with information on how to run them.
Watch for consequential improvements under regulation 28. They can apply in an existing building over 1,000 m². The trigger is new fixed building services, or more installed capacity. Further energy work may then be required where it is technically, functionally and economically feasible. Adding cooling to a large floor can trigger it.
We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.
Part M and Part T: access and toilets
Part M covers access to and use of buildings. On an office fit-out, it affects door widths, level access and accessible toilets. It also covers kitchen points, signage and the height of controls. Your duties under the Equality Act 2010 sit alongside it.
Part T is newer. Since 1 October 2024, it has required single-sex male and female toilets in buildings other than homes. Universal toilets are allowed in addition, or instead where space rules out separate rooms.
Part T is also one of the requirements that make an alteration "material". So a fit-out that moves or adds toilets must plan the layout around it.
The other parts that come up
- Part A, structure. Removing walls, new openings, and heavy items like safes or server racks.
- Part F, ventilation. Fresh air rates for meeting rooms and new enclosed spaces.
- Part H, drainage. New kitchens, tea points and toilets.
- Part K, protection from falling. New stairs, balustrades and mezzanines.
- Electrical safety. In offices, this sits mainly with the Electricity at Work Regulations 1989 and BS 7671. Every new circuit needs a test certificate.
How building regulations approval runs on a fit-out
- Survey and brief. Existing drawings, the landlord's fire strategy and the building's rules.
- Design. Layout, fire strategy for the floor, services design and specification.
- Full plans application. Submitted before work starts. Conditions often cover details still in development.
- Inspections. Building control visits at key stages: fire stopping, cavity barriers, drainage and completion.
- Testing and commissioning. Fire alarm, emergency lighting, electrics, ventilation and air conditioning.
- Completion certificate. Issued once building control is satisfied. Keep it with the health and safety file.
Allow time for the application in the programme. Never close up ceilings before the fire stopping has been inspected. Reopening a finished ceiling for an inspection is an expensive and avoidable delay.
Two Craftex office projects show the approvals in practice
At Beaumont House in Kensington, we turned 750 sq m of run-down offices into an open-plan workplace in three weeks. The client had five weeks before their lease ran out. The scope included demolished walls, frosted glass meeting rooms and new lighting and wiring throughout. It also included underfloor data to every desk, CCTV and access control.
Each item touched the regulations: structure, escape routes, fire separation, Part L lighting and door release on escape routes. On a programme that short, approvals must run alongside the design, not after it.
At Portsoken House in Aldgate, the scope was bigger. We delivered 1,550 sq m over two floors with a full mechanical and electrical package. It also included new ceilings, levelled floors, a new entrance, a kitchen and toilets, all around tenants who stayed in the building.
Six mistakes to avoid
- Assuming "it's only internal". Internal works are often exempt from planning permission, not from building regulations.
- Starting on a building notice. It is not allowed for offices.
- Designing rooms first and escape routes later. Travel distances and inner-room rules can kill a layout.
- Ignoring the landlord's fire strategy. Your floor is part of the building's strategy, and the landlord will check.
- Leaving Part L and Part T to the end. Both shape the layout and the plant from the start.
- No completion certificate. It causes problems at lease end, on assignment and with insurers.
What comes after the drawings
Building control is one of several duties on a fit-out. Our guide to CDM 2015 client duties on a fit-out covers health and safety. If your staff will stay in the building, read about refurbishing an office while it's occupied. For the scope options, see the types of office fit-out.
With design and build, the drawings, the approvals and the build sit with one team. Want building control handled from day one? Book a site visit and we will plan the approvals into your programme.