Clinic Fit-Out and CQC Requirements: What Your Premises Must Deliver
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
CQC does not publish a fixed specification for clinic premises. Regulation 15 requires them to be clean, secure, suitable, properly used, properly maintained and appropriately located.
- The rooms must suit the services you will register.
- Finishes and ventilation must support infection control.
- Patients must get in, around and out with privacy and dignity.
- CQC must refuse registration if you cannot show you will meet Regulation 15.
Most clinic owners meet CQC's premises expectations at the worst time. The lease is signed and the layout drawn. Then the registration inspector asks how the decontamination room works.
This guide sets out the CQC requirements a clinic fit-out must meet, from the contractor's side. It is for owners and practice managers opening or refurbishing CQC-registered premises in London. That includes private GP, dental, physiotherapy, diagnostics, outpatient and day-case services, and medical aesthetics.
We deliver private clinic fit out in London. This guide draws on treatment rooms we built, such as the four-floor Medusa clinic in Knightsbridge. It is not regulatory advice: your compliance adviser decides what you register. Found a unit? Book a site visit and we will check it against the rules with you.
First, check whether you need CQC registration
CQC registration depends on the regulated activities you carry out. Calling the premises a clinic does not decide it. Diagnostic and screening procedures, treatment of disease, disorder or injury, and surgical procedures commonly bring private clinics into scope. Many beauty and wellbeing services are not regulated activities.
That line is moving for aesthetics. The government plans a licensing scheme for non-surgical cosmetic procedures, run by local authorities. It also plans to limit the highest-risk procedures to qualified, regulated professionals in CQC-registered settings. In October 2026 the scheme was not yet in force. Check the current position before you fix the scope.
What CQC Regulation 15 asks of your clinic fit-out
| Regulation 15 requirement | What it means for the fit-out |
|---|---|
| Clean | Surfaces that can be cleaned to the standard each room needs; cleaning and clinical waste designed in |
| Secure | Controlled access to clinical, storage and records areas; safe medicines storage |
| Suitable for the purpose | Room sizes that fit the services; enough toilets, storage and waiting space; privacy; accessible |
| Properly used | Rooms used as designed; changes of use risk-assessed |
| Properly maintained | Building and services that can be maintained and recorded |
| Appropriately located | Easy to reach, with linked rooms close together |
CQC's guidance adds points that turn straight into design decisions.
- Premises must meet statutory requirements and should take account of national best practice.
- People's needs must be considered when premises are designed, built, renovated or adapted.
- Alterations must follow current law and guidance. Where guidance cannot be met, the provider needs a plan to manage the risk.
- People should enter, leave and find their way easily. Where they cannot, reasonable adjustments are needed under the Equality Act 2010.
Infection prevention and control sits mainly under Regulation 12. In practice, it drives most of the fit-out specification.
NHS design guidance sets the benchmark
When CQC refers to national best practice, the usual reference points are NHS Health Building Notes (HBNs) and Health Technical Memoranda (HTMs). They are written for NHS buildings. Private clinics widely use them as the benchmark.
| Guidance | Covers | Fit-out decisions it drives |
|---|---|---|
| HBN 00-03 | Clinical and clinical support spaces | Room sizes, couch access, hand-wash positions |
| HBN 00-09 | Infection control in the built environment | Finishes, junctions, storage, hand hygiene |
| HBN 00-10 | Floors, walls, ceilings, sanitaryware, windows | Sheet flooring with coved skirting, cleanable surfaces |
| HTM 03-01 | Specialised ventilation | Air change rates and pressure in treatment rooms |
| HTM 01-05 | Decontamination in dental practices | Separate clean and dirty flow |
| HTM 06 series | Electrical services | Supplies and resilience for medical equipment |
You do not have to follow every clause to the letter. But where you depart from them, know why and be able to explain it. Have that conversation before drawings go to the landlord.
The fit-out decisions that matter most
These six decisions decide whether the premises work for patients, staff and the inspector.
- Layout and flow. Separate patient, staff, clean and dirty routes where the services need them. Size rooms for the couch, the equipment and a wheelchair, not just a desk.
- Finishes. Wipe-clean, hard-wearing and jointless where clinical work happens: sheet vinyl with coved skirtings, sealed ceilings and impervious worktops.
- Ventilation. Clinical rooms often need more air changes, and some procedures need controlled pressure. Plan plant space, ducts and noise early.
- Privacy and dignity. Acoustic separation between consulting rooms, visual privacy and changing space.
- Accessibility. Level access, wide doors, accessible toilets, hearing loops and clear wayfinding.
- Security and storage. Controlled access, secure medicines storage and enough storage that corridors stay clear.
The hard part is keeping a clinical room from feeling institutional. Wipe-clean finishes can still come in warm tones, with soft lighting and natural-looking materials. Patients notice how a room feels long before they notice the flooring.
Holistic therapy space fit-out Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.
London checks to make before you sign the lease
- Use class. Medical and health services sit within Use Class E. Moving into a former office or shop often needs no planning permission for the use. External changes, signage and plant still can.
- Special treatment licence. Most London boroughs need one for treatments such as massage, acupuncture, tattooing, electrolysis or laser. Some registered healthcare professionals are exempt, so ask the borough early.
- The landlord. Clinical ventilation, extra plant, water and drainage need landlord consent. Our guide to the licence for alterations explains how to keep it off the critical path.
- Building control. Clinics are workplaces under the Fire Safety Order, so building work needs a full plans application. See our guide to building regulations for fit-outs.
Refurbishing a clinic that stays open
Many clinics cannot close. A care setting cannot accept the noise, dust and disruption a normal site does.
The site has to run around the people still using the building. At the Portsoken House reception in Aldgate, the rest of the building stayed occupied. We rebuilt the reception only at night and at weekends, so the tenants were never interrupted. Order compliant long-lead materials early too, so standards are never traded away under programme pressure.
The principles for any live clinic:
- phase the works so clinical areas are never next to open demolition;
- seal working areas and control dust, with negative pressure where the risk justifies it;
- keep patient routes, fire escapes and accessible access open and signed;
- schedule noisy work outside clinic hours;
- clean each phase to a clinical standard before patients return.
Our guide to refurbishing occupied premises covers the same approach in offices.
What our treatment and occupied-building projects show
Medusa Spa & Beauty in Knightsbridge was a turnkey beauty clinic of 180 sq m over four floors. We designed and built it in 17 weeks. The work included new electrics, fire and intruder alarms, CCTV, air conditioning and ventilation.
We stripped out all four floors before the new services went in. Treatment businesses outside CQC still face licensing and building control.
A pre-lease checklist for clinic owners
We design and build clinic fit-outs and refurbishments across London, from £100,000. Got a unit in mind? Book a site visit before you sign the lease.
Before you sign the lease
- Confirm which regulated activities you will register and the rooms they need.
- Check the floor-to-ceiling height for ventilation and services.
- Check water, drainage and power capacity for clinical rooms and equipment.
- Confirm the landlord will allow plant, ductwork and extra drainage.
- Check the use class, signage and any special treatment licence.
- Plan patient, staff, clean and dirty flows before the room layout.
- Decide which HBNs and HTMs you are designing to, and where you will depart.
- Allow time in the programme for CQC registration of the location.