Section 18 Valuation: Diminution in Value and the Claim Cap

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read

Office floor part-way through refurbishment, with ceilings open and furniture cleared

The short answer

Section 18(1) of the Landlord and Tenant Act 1927 caps damages for disrepair at the diminution in value of the landlord's interest. If the landlord will demolish or structurally alter the premises, repairs made valueless cannot be claimed at all.

  1. The cap applies to repair, not to decoration, removal or reinstatement.
  2. Damages are typically the lower of the cost of works and the diminution in value.
  3. A valuer measures the diminution by valuing the building in and out of repair.
  4. The landlord's plans for the building often decide how big the fall in value is.

Diminution in value is the legal cap on a dilapidations claim for disrepair. Under section 18(1) of the Landlord and Tenant Act 1927, damages cannot exceed the fall in the value of the landlord's interest. A section 18 valuation is how that fall is measured.

For a tenant, this is often the strongest point in the whole negotiation. A landlord can price a long schedule of repairs. It can only recover what it actually lost.

This guide explains the two limbs of section 18 and how diminution in value is measured. It also shows how to use the cap when negotiating your dilapidations claim. We are builders, not valuers: we price the works, which is the other half of the comparison. Facing a claim now? Get your claim reviewed.

Section 18 of the Landlord and Tenant Act 1927

Section 18(1) has two parts, usually called limbs. Both protect tenants against claims bigger than the landlord's real loss.

The two limbs of section 18(1)
LimbWhat it says, in plain termsEffect on the claim
FirstDamages for disrepair cannot exceed the fall in value of the landlord's interestCaps the repair claim at the diminution in value
SecondNo damages for repairs made valueless by demolition or structural alteration at or shortly after the lease endsRemoves those repair items entirely

The cap only reaches repair. RICS guidance is clear that section 18(1) does not apply to decoration, removal and reinstatement. Those obligations are assessed under different rules.

So split the landlord's schedule into its categories before you argue the cap. The Dilapidations Protocol already asks the landlord to list repair, reinstatement and redecoration separately.

Diminution in value explained

Diminution in value means the fall in the value of the landlord's reversion. That is its interest in the building once your lease ends.

A valuer prepares two valuations of the same property on the same date:

  1. In compliance. The building as it would be if you had kept every covenant.
  2. Out of compliance. The building as it actually is, with your breaches.

The difference is the diminution. RICS guidance says market value is the starting point, generally taken to mean open market value. The valuer works out who would buy or rent the building in each state.

Cost of works and diminution in value compared
Cost of worksDiminution in value
What it measuresThe reasonable cost of putting the breaches rightThe fall in value caused by the breaches
Who usually prepares itA building surveyor, quantity surveyor or contractorA valuer
When it matters mostThe landlord has done, or will do, the worksThe landlord will not do the works, or will redevelop

When the landlord will redevelop

The landlord's plans for the building often decide the claim. If it will strip the floor to shell, the repairs you skipped may be worth very little to it.

The second limb goes further. Some premises will be pulled down, or altered so your repairs become valueless, at or shortly after the lease ends. Then no damages are due for those repairs.

RICS calls a related idea supersession. A landlord should only claim for what it lost. Where its own works sweep away an item, there is usually no loss on that item.

The Protocol builds this in. The landlord's quantified demand should leave out items its plans will supersede. The tenant's response should flag any it missed, with the evidence.

Ask early about the landlord's plans. Look for planning applications, marketing particulars and refurbishment tenders. They are often the best evidence you will find.

Supersession: when the landlord's plans cancel the claim

Supersession is the idea that some schedule items are overtaken by what the landlord does next. If those works would sweep the item away anyway, the landlord has lost nothing on it.

RICS guidance says there is no universally accepted test for supersession. It sets out the situations where it most often arises:

  1. Demolition or structural alteration. The landlord should not claim for repairs to parts it will pull down. This overlaps with the second limb of section 18.
  2. Grander works. The landlord carries out wider or more expensive works than the lease required. The claim may then be superseded, or limited to the basic works.
  3. Market demands. If the market would require the grander works anyway, such as an upgrade to meet energy rules, the landlord may struggle to show a loss.
Typical items tenants argue are superseded
Schedule itemLandlord's planTenant's argument
Repair ceiling grid and tilesStrip floor to shellCeiling is coming out anyway
Redecorate officesFull refurbishmentNew finishes will replace it
Overhaul air conditioningReplace plant to meet energy rulesOld plant is being replaced
Reinstate tenant partitionsNew tenant wants themPartitions stay in use

The Protocol asks the tenant to state supersession in its response, with the evidence and the items it affects.

Cost of works versus diminution

RICS guidance says damages after the lease ends are typically the lower of two figures. One is the reasonable cost of the works; the other is the diminution in value. That makes both figures matter.

A landlord who has done the works will lead with its invoices. A landlord who has not will usually need a diminution valuation. The Protocol says that before issuing proceedings it should provide one, prepared by a valuer, unless that would be unreasonable.

The tenant's side needs both figures too:

  1. A real cost of works. A builder's line-by-line price for what the lease actually requires.
  2. A view on diminution. From a valuer, where the landlord's plans or the market suggest a small fall in value.

Our own RICS-qualified quantity surveyor prices the first figure from current builders' rates. Because our own crews do the work, it is a price we will build for. We do not value the reversion: that is a valuer's job.

The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!

Alaa Betar, Google reviewSee all reviews on Google

Using the cap in negotiation

Most claims settle without a trial. The section 18 cap is a negotiating tool long before it is a legal argument.

Use it in this order:

  1. Split the schedule. Separate repair from decoration and reinstatement, because the cap only reaches repair.
  2. Price the repair items. Get a real cost of works for each line.
  3. Test the landlord's plans. Evidence of refurbishment, re-letting as shell or redevelopment can cut the repair claim sharply.
  4. Take valuation advice. Where the fall in value looks small, a valuer's view strengthens your hand.
  5. Make a reasoned offer. Base it on the lower of the two measures, item by item.

The Scott schedule is where this happens, line by line. One team, one point of contact: we price the works, negotiate with your landlord's surveyor and, if it costs less, do the works ourselves.

What this means at your lease end

Section 18 does not make a dilapidations claim go away. It keeps it honest. A landlord can still recover its real loss on repair, and the reinstatement and decoration items sit outside the cap.

Three things keep the bill down for most tenants:

  • a schedule of condition from the start of the lease;
  • reinstatement and decoration done before you leave, where the lease clearly requires them;
  • a priced, evidence-backed response to every line the landlord claims.

If you are leaving early, the cap also shapes a surrender premium or a break. Our guide to surrender of a commercial lease covers how the dilapidations fit into that deal. Want the works priced before you negotiate? Get your claim reviewed.

Using the section 18 cap

  • Split the schedule into repair, decoration and reinstatement.
  • Price every repair line as a builder would.
  • Ask about the landlord's plans for the building.
  • Collect evidence: planning, marketing, tenders.
  • Get a valuer's view where the fall in value looks small.
  • Offer on the lower of cost of works and diminution.

Frequently asked questions

What is section 18 of the Landlord and Tenant Act 1927?

Section 18(1) limits damages for breach of a repairing covenant. They cannot exceed the amount by which the value of the landlord's reversion is diminished by the breach. A second limb removes damages for repairs made valueless by demolition or structural alteration.

What does diminution in value mean in dilapidations?

It is the fall in the value of the landlord's interest caused by the tenant's breaches. A valuer compares the property as it is with the property as it would be if the covenants had been kept.

Does section 18 apply to reinstatement?

No. RICS guidance says section 18(1) does not apply to non-repair obligations such as decoration, removal and reinstatement. Those are assessed under different rules.

Who prepares a section 18 valuation?

A valuer. The Dilapidations Protocol says a formal diminution valuation should be prepared by a valuer. A building surveyor or contractor prices the works, which is the other figure in the comparison.

What if the landlord plans to redevelop the building?

If the premises will be pulled down, or structurally altered so the repairs become valueless, at or shortly after the lease ends, the second limb of section 18(1) means no damages are due for those repairs.

When does a tenant need a diminution valuation?

The Protocol says a tenant relying on a diminution defence must state its case and provide a diminution valuation, generally within 56 days after the landlord's detailed breakdown of losses.

Facing a large dilapidations claim?

Send the schedule, the lease or just the address. One team prices the works, negotiates with your landlord and can do the works if that costs less.