How Much Does a Shop Fit-Out Cost? 2026 Prices per m² for UK and London Stores

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 7 min read

Boutique interior with timber display tables, clothing rails, track lighting and large plants

The short answer

A shop fit-out in the UK costs about £452 to £532 per m² for a refresh, £802 to £944 for a full fit-out and £1,335 to £1,570 for a flagship with bespoke joinery at our 2026 rates, ex VAT (about £42 to £146 per sq ft).

  1. The unit you inherit sets the band: shell, Cat A or a previous retailer's fit-out.
  2. The shopfront, bespoke joinery and trading through the works move the figure most.
  3. Consents, landlord's fees and VAT sit outside the rate: budget them as separate lines.

A shop fit-out in the UK costs about £452 to £532 per m² for a refresh and £802 to £944 for a full fit-out. A flagship with bespoke joinery costs £1,335 to £1,570 per m². Those are our 2026 rates, ex VAT, or roughly £42 to £146 per sq ft.

The unit you take on sets the band. The shopfront, the joinery and your trading hours move the figure within it. Consents, landlord's fees and VAT sit outside the rate.

This guide is for brands opening or refitting a store, retailers budgeting a roll-out and landlords readying a unit. It shows where the money goes, one real London flagship that sits above the bands, and the costs outside the build. For the process and choosing a contractor, read our retail fit-out guide.

Our retail fit out and shopfitting team prices from your plan and the landlord's pack. Want a figure for your unit? Discuss your project.

Shop fit-out cost per m² and per sq ft in 2026

Our 2026 rates split a shop fit-out into three typical scopes. Each band is construction only, ex VAT and fees; your fixed figure comes after a survey.

Shop fit-out cost per m² and per sq ft by scope, our 2026 rates, construction only, ex VAT and fees
Scope£ per m²£ per sq ftTypical work
Store refresh£452 to £532£42 to £49New layout, floors, decoration, LED lighting, off-the-shelf fixtures, essential services
Full fit-out£802 to £944£75 to £88Shell or Cat A to trading: ceilings, full M&E, fire alarm, designed lighting, brand finishes, bespoke counters
Flagship£1,335 to £1,570£124 to £146Bespoke joinery and display, feature lighting, complex ceilings, premium floors, full services
New shopfrontPer frontagePer frontagePriced after survey: width, glazing and any conservation-area design

For comparison, Laxton's 2026 price book puts shop refurbishment at £750 to £1,400 per m² and new shops at £1,050 to £2,200. Laxton's adds about 9 % for London. Our bands sit below those published ranges. A shopfront, bespoke joinery and trading through the works push a London store towards the top of its band.

An independent benchmark sits higher. The City of Edinburgh Council publishes a building cost guide based on BCIS rates from mid-2025 to early 2026. It puts an average shop fit-out at about £1,683 per m², above the top of our flagship band.

What a shop fit-out price includes

A fit-out rate covers the build from the unit as handed over to the day you trade. Ask every contractor to price the same list, or the quotes will not compare.

Freestanding black clothing rail and timber bench against a concrete wall, with plants
Freestanding rails and benches are loose fixtures, often bought direct and outside the fit-out rate.

What the rate usually covers:

  • Strip-out of the previous tenant's fit-out
  • Partitions, stockroom and fitting rooms
  • Ceilings, floors and decoration
  • Lighting, power, data and fire alarm
  • Heating, cooling and ventilation
  • Counters, shelving and fixed display joinery

What sits outside it, as separate lines in your budget:

  • VAT at 20 % on the works
  • Loose fixtures and mannequins bought direct
  • Tills, EPOS and security tagging
  • Design fees, if the designer is appointed separately
  • Planning, advertisement and building control fees
  • The landlord's surveyor and legal fees

Display lighting is the line most often cut and most often missed. Our calculator adds about £72 per m² for display and accent lighting on top of the build rate. Light the stock well and it sells; light it badly and the fit-out looks cheap.

Need the scope and the programme as well as the price? Our shopfitting and retail fit-out page shows how we run a store from drawings to keys.

What pushes shop fit-out cost up or down

Two shops of the same size can differ by half in cost. Six things explain most of the gap.

  1. The unit you inherit. A shell needs everything. A Cat A unit has ceilings, lighting and services. A previous retailer's fit-out may be reusable, or may need stripping first.
  2. The shopfront. New glazing, doors and a fascia are priced per frontage. A listed building or conservation area adds design time and often costlier materials.
  3. Bespoke joinery. Made-to-measure counters, shelving and fitting rooms cost more than system fixtures. They also take longer to make, so order them early.
  4. Lighting and air. Track and display lighting, and cooling for a busy floor, add to the mechanical and electrical line.
  5. Trading through the works. Keeping the shop open means night and weekend shifts, phasing and protection. That costs more than a closed site, and less than lost sales.
  6. Access and centre rules. Upper floors, tight delivery windows on busy streets and a shopping centre's fit-out guide all add time, and time costs money.

The landlord can change the net cost too. Ask early about a landlord contribution towards the works. Agree a licence for alterations before you order anything.

The same drivers apply at a larger scale to a car or furniture showroom fit-out.

A real London flagship: Drake's, Savile Row

Drake's flagship at 9 Savile Row shows what the top of the market costs. We refitted the 120 sq m store in 12 weeks, and it traded every day of the works.

£410Kproject value
120 sq mSavile Row flagship
12 weeksstore open throughout

That is about £3,400 per m², by our calculation. It sits well above our flagship band of £1,335 to £1,570 in the table above. We say so plainly, because the reasons are the lesson.

  1. Bespoke timber fixturing. Curved rails, shelving and a shoe wall, each drawn for the stock it holds.
  2. A reworked made-to-order area. Fitting rooms with a pull-out mirror and rails that move garments between rooms.
  3. A new shopfront and lighting. A shopfront in keeping with the street, gallery-grade track lighting and floors for heavy footfall.
  4. Live trading on Savile Row. Deliveries and noisy work were booked around opening hours and the neighbours.

A small flagship also spreads a shopfront and a design team over fewer square metres. Per m², that alone lifts the rate.

Medusa on Beauchamp Place, Knightsbridge, tells the same story. Its 180 sq m of salon and spa over four floors was valued at £460K, design included: about £2,550 per m².

Drake's came back to us for their 500 sq m railway-arch HQ in Bethnal Green, designed and built in 8 weeks. Read the Drake's Savile Row refit in full.

We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍

Apartify Estates, Google reviewSee all reviews on Google

Consents and landlord costs outside the build

The build rate excludes the approvals around it. Budget for them separately and start them early, because they set the programme.

  1. Shopfront: planning permission. Under the Town and Country Planning Act 1990, works that materially affect a building's external appearance are development. A new shopfront usually needs planning permission.
  2. Signs: advertisement consent. No sign may be displayed without express or deemed consent. In a conservation area, an illuminated fascia or projecting sign needs express consent, because the deemed class excludes it.
  3. Listed buildings. Altering a listed building's character needs listed building consent. Works without it are a criminal offence.
  4. Building regulations. Fire safety and access follow Approved Documents B and M for buildings other than dwellings. Building control fees sit outside the rate.
  5. Access for disabled customers. The Equality Act 2010 expects reasonable steps where a physical feature puts disabled people at a substantial disadvantage. A fit-out is the cheapest time to fix steps and doors.
  6. The landlord's approval. A licence for alterations, with the landlord's surveyor and solicitor reviewing your drawings. Leases often pass those costs to the tenant. The licence also records what comes out at lease end, which drives any shop dilapidations claim.

Letting the unit after the fit-out? Since 1 April 2023, a landlord must not continue to let a non-domestic property below EPC band E without a valid exemption. Fixing it during the works costs less than after. Our guide to minimum energy efficiency standards covers the rest.

Budgeting a shop fit-out in five steps

A budget you can defend to a board or a lender takes five lines. Build it in this order.

  1. Measure the area. Sales floor, stockroom and back-of-house, in m².
  2. Pick the band. Refresh, full fit-out or flagship, from the unit's condition and your brand's finish.
  3. Add the shopfront and signs. A separate line, priced per frontage after a survey.
  4. Add consents and landlord costs. Planning, advertisement and building control fees, and the landlord's surveyor.
  5. Hold a contingency. Keep a contingency for what the survey cannot see. Then ask for a fixed figure after a site survey.

Before you sign the lease, check the six points below. Each one moves the figure.

Already have a quote? Send us your quote. We price the same scope, show you where the difference is, and give you a fixed figure after a survey.

We take on construction from £100,000, from a single boutique to a multi-site roll-out.

Before you sign the lease on a shop

  • The landlord's pack: what the unit is handed over with
  • Shopfront and signage rules for the street and any conservation area
  • The shopping centre's fit-out guide, if there is one
  • Power supply, drainage and air-conditioning capacity
  • The EPC rating, if you will sublet
  • Your launch date, and whether you trade during the works

Frequently asked questions

How much does a shop fit-out cost?

At our 2026 rates, about £452 to £532 per m² for a refresh, £802 to £944 for a full fit-out and £1,335 to £1,570 for a flagship with bespoke joinery, ex VAT. A 150 m² shop with a full fit-out comes to about £120,400 to £141,600 before VAT. Prime London flagships can sit higher.

What do shop fitting costs per square metre look like in the UK?

Laxton's 2026 price book gives £750 to £1,400 per m² for shop refurbishment and £1,050 to £2,200 for new shops. A BCIS-based guide from the City of Edinburgh Council puts an average shop fit-out at about £1,683 per m². In London, expect the upper half of each band.

What is the average cost of a shop fit-out?

There is no single average, because the starting unit varies so much. A full fit-out of a typical high-street unit sits at about £802 to £944 per m², or £75 to £88 per sq ft at our 2026 rates, ex VAT. The shopfront, consents, landlord's fees and VAT come on top.

How much does a coffee shop fit-out cost?

More per m² than a plain shop, because a café needs water, drainage, extra power for the machines and often ventilation. The same BCIS-based guide puts restaurant fit-out at about £1,984 per m², against £1,683 for shops. Cooking on site adds extract and gas, which moves the budget again.

Do I need planning permission for a new shopfront?

Usually. Works that materially affect a building's external appearance count as development and need planning permission. Illuminated signs need advertisement consent unless a deemed class covers them, and that class excludes conservation areas. A listed building also needs listed building consent.

Know the figure before you sign the lease.

Send us the plan, the landlord's pack and your launch date. We survey the unit and come back with a programme and a fixed figure.