Retail Fit-Out in London: A Practical Guide for Shops and Flagship Stores

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read

Clothing shop interior with hanging rails, pendant lights and a timber ceiling

The short answer

A retail fit-out in London is decided by consents and sequencing more than by the build. The landlord's licence, shopfront and signage consents and, often, a shop that must keep trading set the programme.

  1. Start the landlord's licence for alterations as soon as you have a layout.
  2. Check whether the shopfront or signs need planning or advertisement consent.
  3. Survey the unit's power, ventilation and fire alarm before you design.
  4. Phase the works by zone if the store must stay open.

A retail fit-out in London is rarely just a design job. The landlord, the planning authority, building control and the neighbours all have a say. Very often the shop also has to keep trading. So the real work is in the planning and the sequencing.

This guide sets out what a shop or flagship fit-out involves in London. It covers the consents you need, how a live-trading refit runs and what drives the cost. The worked example is our refit of Drake's on Savile Row. Have a unit in mind? Book a site visit and we'll check it with you.

For one team to design and build the whole store, see our shopfitting in London service.

What a retail fit-out in London includes

A fit-out covers everything that turns a unit into a working shop. On a typical London retail project, the scope includes:

  1. Shopfront and entrance: glazing, doors, fascia, signs and security.
  2. Layout: sales floor, fitting rooms, tills, stock room and staff areas.
  3. Joinery and fixtures: display units, rails, shelving, counters and cash desks.
  4. Floors, walls and ceilings: finishes that cope with heavy footfall.
  5. Lighting: display and accent lighting, plus emergency lighting.
  6. Services: power and data for tills, heating, cooling, ventilation, fire alarm and security.
  7. Access and safety: step-free entry where possible, door widths and escape routes.

Retail sits alongside office, hospitality and warehouse work in our commercial fit-out and refurbishment service.

The unit you take on sets the budget

Your budget and programme depend on what you start from. For rates per m² and per sq ft, see shop fit-out cost per m².

Starting points for a London retail fit-out
Starting pointWhat you getWhat you pay for
Shell and coreBare floor, walls, capped servicesAlmost everything, incl. services, ceilings and shopfront
Landlord's Cat A or white boxBasic finishes and servicesThe customer-facing fit-out
Existing store to refitA working shopLess on paper, but phasing around trading

Check what the landlord's specification really includes before you design around it. Our guide to Cat A, Cat A+ and Cat B fit-outs explains the categories.

Before any design is fixed, survey the unit. Check power capacity, ventilation, drainage and the fire alarm. Surprises found then are cheap. Surprises found during the strip-out are not.

London consents decide the programme

Most delays on London retail projects come from consents, not construction. Allow for these early.

The landlord's licence for alterations

Almost every retail lease needs the landlord's written consent for alterations. That licence also lists what you strip out at lease end, the core of retail dilapidations. Landlords usually want drawings, method statements, insurance and the contractor's details. Managed estates may also set rules on hours, deliveries and noisy work. Build this approval time into the programme.

Planning permission and advertisement consent

Works that only affect the inside of a shop are not development. But works that materially change its outside are. A new shopfront therefore often needs planning permission.

Signs follow their own rules. Many plain, non-illuminated fascia and hanging signs have deemed consent. An illuminated sign of any size may need advertisement consent. In a listed building, you also need listed building consent.

Building Regulations, access and fire

New partitions, altered escape routes and new services are building work. They need building control approval. The fire strategy, escape routes and emergency lighting must work for the new layout.

Shops also have a duty under the Equality Act 2010. Where a physical feature puts disabled customers at a substantial disadvantage, you must take reasonable steps to avoid it. Design it in from the start: level access, door widths and counter heights.

CDM 2015: duties for you as the client

As a commercial client, you have duties under the Construction (Design and Management) Regulations 2015. With more than one contractor, you appoint a principal designer and a principal contractor. A construction phase plan must be in place before work starts.

Larger jobs must also be notified to HSE. That applies when work lasts more than 30 working days with more than 20 workers at once, or exceeds 500 person days. A design and build contractor manages this with you.

Refitting a store while it keeps trading

For established brands, closing a shop means lost sales and lost visibility. A live-trading refit avoids that, but it changes how the job runs:

  1. Phasing: the store is split into zones, and each is handed back before the next closes.
  2. Hoarding and dust control: clean hoardings and sealed work areas keep stock and customers safe.
  3. Out-of-hours work: noisy tasks happen before opening or after closing, within permitted hours.
  4. Deliveries: timed around loading rules and neighbours, with materials brought in just in time.
  5. Daily handback: the shop is left clean, safe and ready to trade every morning.

We recently worked with Craftex and honestly couldn’t be happier with the results. From start to finish, the team was professional, reliable, and highly skilled. The quality of workmanship exceeded our expectations, and everything was completed on time and to a very high standard. Communication throughout the project was excellent, and they always went above and beyond to make sure we were satisfied. It’s rare to find a construction company that combines professionalism, attention to detail, and great customer service so well. Without a doubt, Craftex is one of the best construction companies we have ever worked with. Highly recommended to anyone looking for quality and trustworthy builders.

Adam Miah, Google reviewSee all reviews on Google

Drake's, Savile Row: a flagship refitted while trading

We refitted Drake's flagship on Savile Row in Mayfair with the store fully open throughout.

Drake's, Savile Row: the refitted menswear floor with bespoke timber shelving
Drake's, Savile Row: the reworked made-to-order area.
£187KProject value
120 sq mStore size
8 weeksOn site, after 4 weeks of design
0 daysStore closed

The work included a new shopfront, bespoke timber fixtures and gallery-grade lighting. We laid flooring for heavy footfall and built custom desks and joinery for the staff. New rails, extra power and data points and a reworked made-to-order area followed.

Every delivery and work shift was planned so the store could trade and the neighbours were not affected. Working on Savile Row leaves no room for mistakes.

The stages of a retail fit-out

  1. Brief and survey: what the store must do, the budget, the opening date and a survey of the unit.
  2. Design and costing: layout, finishes, joinery and services, priced so you can decide before ordering.
  3. Consents: the landlord's licence, planning and advertisement consent where needed, building control.
  4. Procurement: bespoke joinery, shopfront glazing and special lighting are ordered once the design is fixed.
  5. Construction: strip-out, first fix, partitions and ceilings, second fix, finishes and joinery.
  6. Testing and handover: fire alarm, lighting and services commissioned, certificates issued, store ready for stock.

With one design and build contract, design and pricing run together. You get one point of responsibility and fewer gaps.

What drives the cost of a retail fit-out

There is no honest single price per square foot for London retail. The gap between a simple refresh and a flagship is too wide. These are the main cost drivers.

Main cost drivers for a London retail fit-out
Cost driverWhy it matters
Starting conditionA shell needs services, ceilings and a shopfront; a Cat A unit needs far less
ShopfrontNew glazing, doors and signs are a large item, more so in a conservation area
Bespoke joineryUsually the biggest package in a premium store
Lighting and servicesDisplay lighting, power and data, heating, cooling and ventilation
Live tradingPhasing and night work add cost but protect sales
Access and logisticsBusy streets, upper floors and delivery limits affect labour and time

As a reference, the Drake's flagship was £187K for 120 sq m. It was premium, joinery-led and delivered while trading. A standard high-street unit with ready-made fixtures would cost far less. The only reliable figure is one priced against your drawings and your unit.

Landlords should also check the energy rating. Let commercial units must have an EPC rating of E or better, including existing tenancies since April 2023. A fit-out is a good moment to fix a low rating with lighting and heating upgrades.

How to choose a retail fit-out contractor in London

  1. Relevant work you can check: retail projects of a similar size and finish, ideally delivered while trading.
  2. Design and build under one contract: one party responsible for design, cost and programme.
  3. Accreditations and insurance: landlords will ask. We are ISO and CHAS accredited.
  4. Who does the work: about 60% of our labour is in-house, which keeps quality and programme under control.
  5. A clear, itemised price: with exclusions and provisional sums spelled out, so quotes compare like for like.

Serving food or drink too? Kitchens, extraction and licensing change the job. See our restaurant and hospitality fit-out service.

We take on construction projects from £100,000. Planning a shop or flagship store in London? Book a site visit and we'll check the unit, the consents and the programme with you.

Frequently asked questions

How long does a retail fit-out take in London?

It depends on the size of the unit, the scope and whether the shop is trading. Our live-trading refit of Drake's 120 sq m flagship on Savile Row took 8 weeks on site after a 4-week design stage. Allow time before that for design, the landlord's licence and any planning or advertisement consent.

Do I need planning permission for a new shopfront?

Often, yes. Works that materially change the outside of a building are development under planning law, and a new shopfront usually does. Illuminated signs of any size may need advertisement consent. A listed building also needs listed building consent.

Can my shop stay open during a refit?

Yes, in many cases. The works are phased by zone, noisy tasks are done out of hours, and the store is handed back clean at the end of each shift. Drake's on Savile Row stayed open throughout its refit.

What is the difference between a retail fit-out and a refurbishment?

A fit-out turns a unit into a working shop for one occupier: layout, joinery, lighting and services. A refurbishment updates an existing space, from a light refresh to a full refit of a trading store.

How much does a retail fit-out cost in London?

There is no honest single rate, because a simple refresh and a flagship are very different jobs. As a reference, the Drake's Savile Row refit was £187K for 120 sq m, joinery-led and delivered while trading. We take on construction projects from £100,000 and price after a site survey.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Planning a shop or flagship store in London?

Our design and build team checks the unit, the consents and the services on site, then gives you a programme and a price before you commit. Book a site visit.

Reply within 1 hour, Mon–Sat 8am–6pm. Urgent? WhatsApp us for a reply straight away, any day.

WhatsApp us