The short answer
Gateway 2 is the Building Safety Regulator's approval that must come before any work starts on a higher-risk building. Since 30 September 2026, new blocks of flats with a storey at 18 m or more also need a second staircase.
- Higher-risk means at least 18 m or 7 storeys, with at least 2 homes.
- The legal deadline is 12 weeks; the regulator's median was 23 weeks.
- Old stair rules only apply if work is sufficiently progressed by 30 March 2028.
- The Building Safety Levy applies to 10 or more homes from 1 October 2026.
On a tall residential scheme, two rules now decide when you can start and what you can build. The first is Gateway 2. The second is the second staircase.
Gateway 2 is the point where the Building Safety Regulator must approve your building control application. No work may start before it does. The second staircase rule took effect on 30 September 2026. Together they shape the design, the appraisal and the lender's timetable. Planning a scheme near 18 metres? Book a site visit and we'll check it with you.
We are a design and build construction company, and this guide is how we read the rules for a tall scheme.
Which buildings Gateway 2 catches
A building is a higher-risk building (HRB) during design and construction if it is at least 18 metres high or has at least 7 storeys. It must also contain at least 2 homes. Hospitals and care homes of that height count too.
That catches more London schemes than people expect:
- a new block of flats of seven storeys, even under 18 m;
- an office-to-residential conversion of a tall building;
- an upward extension that takes a residential building over the line;
- work to an existing HRB, including many internal refurbishments.
If your appraisal adds storeys, check the height first. Our airspace schemes appraisals start there for that reason.
The three gateways in plain terms
The Building Safety Act 2022 set up three checkpoints for a higher-risk building: at planning, before work starts and before anyone moves in. Each one has to be passed in order.
| Gateway | When | What happens | Who decides |
|---|---|---|---|
| Gateway 1 | Planning application | A fire statement goes in; the fire safety consultee is asked | Local planning authority |
| Gateway 2 | Before building work starts | Full building control application: design, fire and structure strategy, competence, construction control plan | Building Safety Regulator |
| Gateway 3 | Before occupation | Completion certificate with the as-built information; building registered | Building Safety Regulator |
Starting work on an HRB without approval is a criminal offence. Residents can't move into a new HRB until the completion certificate is issued and the building is registered.
Gateway 2 timescales: the law and the reality
The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 set the regulator's deadlines. They can be extended if the applicant agrees.
| Application | Statutory period |
|---|---|
| New HRB, or a stage of one | 12 weeks |
| Work to an existing HRB | 8 weeks |
| Change control (major changes during the build) | 6 weeks |
| Completion certificate | 8 weeks |
The regulator also publishes what actually happens. Its July to September 2026 release used data as of 5 October 2026.
Approval rates have climbed sharply. In November 2025 the regulator reported 32% approvals and 44-week decisions. But September 2026 brought 64 new-build submissions, against 34 in August. That rush came just before the Building Safety Levy started. The regulator says it must now triage its workload to limit delays.
What a Gateway 2 application needs under the Building Safety Act
Under the Building Safety Act regime, a Gateway 2 application is a full technical package, not a form. The regulations list what must go in, and a complete, consistent set is the best defence against a rejection.
Regulation 4 of the Higher-Risk Buildings Procedures Regulations 2023 sets the contents. With the plans and particulars of the building, the application must include:
- Plans to show compliance. Enough drawings to show the work meets every applicable building regulation.
- A competence declaration. That the principal designer and principal contractor are competent for their roles.
- A construction control plan. How compliance will be planned, managed and monitored during the build.
- A change control plan. How changes to the approved design will be recorded and approved.
- A mandatory occurrence reporting plan. How safety occurrences will be reported to the regulator.
- A Building Regulations compliance statement. The design principles and standards the scheme follows.
- A fire and emergency file. The fire safety design and the emergency strategy.
- A partial completion strategy. Only if part of the building will be occupied before the work finishes.
Where an agent applies, the client also signs a statement agreeing to the application. A staged scheme can apply stage by stage, with a statement describing every stage.
Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.
Why Gateway 2 applications fail
The regulator rejects applications with big gaps in compliance. An incomplete one costs months. The weak points are usually the same:
- A design that isn't developed enough. Gateway 2 expects technical design, not planning drawings.
- Documents that don't match. Fire strategy, structure and architecture must agree.
- No proof of competence. For the principal designer and principal contractor.
- Vague construction control. How changes, records and reportable incidents will be managed.
- Products without evidence. How each specified system performs.
Each of these is a design-management problem, not a form-filling one. You solve it by finishing the technical design before you submit. Involve the builder while it's being finished. A pre-construction services agreement is one way to do that.
The golden thread of information under the Building Safety Act
The golden thread is the digital record of a higher-risk building. It holds the information that lets someone understand the building and keep it safe. It starts at design, takes in the Gateway 2 approval and passes to the people who run the building.
The Building Safety Act regime puts the duty on the client. Regulation 31 of the Higher-Risk Buildings Procedures Regulations 2023 says the client must set up an electronic facility to hold it. Designers and contractors must be able to reach it and keep it updated.
| Requirement | What it means on site |
|---|---|
| Kept in an electronic format | One digital system, not paper files in a site cabin |
| Accurate and up to date | Every approved change is in it before the work it covers |
| Changes recorded | Who changed what, and on which date |
| Secure from unauthorised access | Controlled log-ins for each consultant and trade |
| Readable and consistent | Plain filing, one set of terms, a key where data needs one |
| Transferable without loss | It can move to the building owner without breaking |
What goes in during the build
Before the construction phase starts, the facility must hold the pre-application designs and the fire statement. It must also hold the approved Gateway 2 plans and documents, with the evidence of compliance. After that, every agreed document and every approved major change goes in as the job runs.
What is handed over at completion
Regulation 38 sets the handover. By the date the work is completed, the client gives the golden thread to the accountable person. It must keep its filing structure and indexes. The receiver confirms in writing that they can open it and run the building from it.
That handover sits beside the Gateway 3 completion certificate. In occupation, the accountable person keeps the thread digitally. It holds the health and safety file, the safety case report, the residents' engagement strategy and the occurrence reporting system.
The second staircase rule from 30 September 2026
Amendments to Approved Document B (fire safety) took effect on 30 September 2026. They expect blocks of flats with a storey at 18 m or more to have a second staircase. They also add guidance on evacuation lifts and shafts.
The transition, exactly
The old guidance still applies only if both of these are true:
- A building notice, initial notice or full plans application was made before 30 September 2026.
- The work is "sufficiently progressed" before 30 March 2028.
"Sufficiently progressed" has a precise meaning:
- New building: concrete is being poured for the permanent foundations, or permanent piling has started.
- Work to an existing building: that work has started.
- Material change of use: work to make the change has started.
Miss that date and the scheme falls under the new guidance. It may need redesigning around a second stair.
What a second stair does to a scheme
A second stair brings a second protected route, lobbies and more corridor. It often moves the core and changes the structural grid. On a tight London plot, that can mean fewer homes per floor or a different mix. It hits hardest on:
- small-footprint towers, where one core was the only way to make the floor work;
- schemes consented with one stair and not started, which may need a new planning application;
- conversions, where a new stair means cutting through existing slabs.
The Building Safety Levy from 1 October 2026
The Building Safety Levy applies to building control applications made from 1 October 2026. It covers developments of 10 or more homes, or 30 or more student bedspaces. It is charged per square metre, at a rate set for each local authority. Previously developed land pays a lower rate.
Social and affordable housing is exempt. The levy is paid before occupation or completion, whichever comes first. It sits alongside CIL and Section 106, not instead of them. See CIL and Section 106 explained.
Seven steps to plan a tall scheme around the gateways
- Test height and storeys at appraisal. Seven storeys or 18 m changes the route, the stairs and the programme. A site appraisal should say which side of the line you are.
- Design the stairs before planning. A one-stair scheme started after March 2028 is a redesign waiting to happen.
- Bring in the fire engineer and contractor early. Fire, structure and buildability must agree before Gateway 2.
- Programme Gateway 2 realistically. Use real approval times, and promise no start dates until approval.
- Plan change control. Major changes after approval need the regulator's consent. Lock decisions before you submit.
- Budget the levies. The Building Safety Levy, CIL and Section 106 all hit at different stages.
- Plan for Gateway 3 from day one. Keep the golden thread up to date as you build, so the as-built information is ready at handover.
How Craftex works on tall residential schemes
We run feasibility, design, Pre-Construction (RIBA Stage 4 technical design) and construction as one team. So the design that goes to the regulator is the design we price and build. On a design and build route, that closes the gap that causes most mismatched submissions.
We also work inside occupied residential buildings. At Kensington Olympia, we designed and refurbished a 400 sq m penthouse in 12 weeks while every other flat in the building was lived in.
For conversions, see our commercial to residential conversion service. Our view on the future of commercial to residential conversions in London covers the wider market. Got a site that could go tall? Book a site visit and we'll tell you how the height rules affect it.