Skip to content
Request a callbackCallback

For developers and landowners

CIL and Section 106 Explained: What London Developers Pay and When

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read

Residential blocks under construction behind trees, with tower cranes above

The short answer

CIL is a fixed charge per square metre of new floorspace, set by the council and not negotiable. A Section 106 is a negotiated legal agreement that makes one scheme acceptable, such as affordable housing or local works.

  1. Most London residential schemes pay the Mayor's CIL, the borough's CIL and Section 106.
  2. CIL is due from commencement, so the paperwork before you start matters.
  3. Section 106 money falls due at triggers written into the deed.
  4. A 2026 London route lets schemes with 20% affordable homes skip viability tests.

Two charges sit on almost every London housing scheme. One is fixed and one is negotiated. Get either wrong in the appraisal and the land price is wrong too.

The Community Infrastructure Levy (CIL) is a fixed charge per square metre of new floorspace. A Section 106 agreement is a negotiated deed that makes one scheme acceptable. In London most residential schemes pay both, and two CILs at that. Weighing up a site? Book a site visit and we will test it with the levies built in.

CIL and Section 106 side by side

The two work very differently. This table shows where they differ in practice.

CIL and Section 106 compared
Community Infrastructure LevySection 106 agreement
What it isA charge on new floorspaceA planning obligation under section 106 of the 1990 Act
Who sets itThe borough's charging schedule, plus the Mayor's London-wide levyNegotiated for each scheme
How it is worked outRate per m² × net new chargeable floorspace, indexed yearlyWhat makes the scheme acceptable, within the legal tests
Negotiable?No, only statutory reliefs applyYes, within policy and viability
Typical contentArea-wide infrastructureAffordable housing, local works, carbon offset, monitoring
When it is paidFrom commencement, in full or by instalmentsAt triggers in the deed
Who is liableThe landowner, unless someone assumes liabilityEveryone who signs; it runs with the land

How CIL is calculated

The basic sum is simple: rate × chargeable area × index. The detail is in the chargeable area.

  1. New floorspace. The gross internal area of the new floorspace is the starting point.
  2. In-use buildings. Existing floorspace can be deducted if it was lawfully used for six continuous months in the three years before permission. A long-empty building often loses this deduction.
  3. Rates by use and zone. Boroughs charge different rates for homes, offices and retail, and for different areas. Check the schedule for the exact address.
  4. Indexation. Rates rise each year from the date the schedule took effect.

In London the borough levy is added to the Mayoral CIL, which funds strategic transport. In central London and the Isle of Dogs, office, retail and hotel schemes can also face a Crossrail contribution under Section 106. That is offset against the Mayoral CIL.

Who does not pay CIL

Most development creating 100 m² or more of new floorspace, or any new home, is potentially liable. The main exemptions and reliefs are:

  • development under 100 m² that does not create a new home
  • residential annexes and extensions, and self-build homes
  • social housing that meets the relief criteria
  • charitable development that meets the relief criteria

Every exemption and relief must be claimed and granted before commencement. Start work without serving a Commencement Notice and the council must add a surcharge.

The CIL process, step by step

Six steps run from permission to payment. The costly mistakes sit in steps 2, 3 and 4, missed in the rush to start on site.

  1. Liability Notice. Issued by the council with or soon after the planning permission.
  2. Assumption of Liability. Whoever will pay, usually the developer, takes on liability before starting.
  3. Claim reliefs or exemptions. Before commencement, never after.
  4. Commencement Notice. Served before work starts, including demolition that is part of the scheme.
  5. Demand Notice. The council sets out what is due and when.
  6. Payment. In full or by instalments. Late payment brings interest and surcharges.

Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.

Misha Levit, Google reviewSee all reviews on Google

How Section 106 works

A Section 106 obligation must meet three legal tests in regulation 122 of the CIL Regulations 2010. It must be:

  1. necessary to make the development acceptable in planning terms
  2. directly related to the development
  3. fairly and reasonably related in scale and kind to the development

Within those limits, a London Section 106 typically covers:

  • affordable housing: how many homes, which tenures, and review mechanisms
  • highways and transport, often with a separate highways agreement
  • carbon offset payments where a scheme misses on-site targets
  • employment, training and local procurement
  • car-free or permit-free restrictions for new residents
  • biodiversity commitments that must be secured for 30 years
  • monitoring fees for the council's compliance checks

National policy now asks councils to use conditions instead of obligations where a condition will do. Our guide to biodiversity net gain for small sites covers when habitat must be secured by obligation.

Affordable housing in London: the October 2026 position

Nationally, affordable housing is sought on major development: 10 or more homes, or a site of 0.5 hectares or more. London adds a threshold approach through the London Plan.

The government announced emergency measures for London housebuilding in October 2025. The final package was published in March 2026 and added a third, time-limited route.

London affordable housing routes, October 2026
RouteAffordable housing (by habitable room)Viability evidenceReviews
Fast TrackAt least 35% (50% on public and some industrial land)Not neededEarly review if not implemented in time
Viability TestedBelow the thresholdFull viability assessmentEarly, mid and late reviews
Time-limited routeAt least 20%, with at least 60% of it Social Rent (35% on public and some industrial land)Not neededEarly review if the first-floor slab is not reached in 30 months

The time-limited route is open to applications validated before 31 March 2028. It does not apply to Green Belt sites, student housing or large-scale shared living. Build to rent has its own test, covered in our build to rent London guide.

Changing a Section 106 later

Obligations can be changed by agreement at any time through a deed of variation. After five years you can also apply formally to change one that no longer serves a purpose. Under the time-limited route, a deed of variation and a section 73 application can move a stalled consent onto the 20% terms.

London CIL relief: what is proposed

As part of the same London package, the government has proposed a temporary relief from borough CIL. The consultation ran from 16 July to 18 September 2026. As proposed:

  • relief applies to homes, not student housing or co-living, in schemes with at least 20% social and affordable housing
  • it starts at 50% of borough CIL at 20% affordable, rising in a straight line to 80% at 35%
  • only schemes with a borough CIL bill over £500,000 qualify
  • works must start before 31 March 2030, with completion expected within five years, or the relief is clawed back
  • evidence is a summary appraisal showing the scheme is unviable, backed by a statutory declaration

Building both into the appraisal

From the builder's side of the table, CIL and Section 106 behave differently in cash flow. A good appraisal shows that.

  1. CIL arrives early. It is due from commencement, before most sales income.
  2. Section 106 money arrives at triggers. Many payments fall due on occupation of a set share of homes.
  3. Floorspace moves. Every m² added in design adds CIL. Every m² of proven in-use floorspace takes it away.
  4. Other charges sit on top. The Building Safety Levy applies to new residential buildings from 1 October 2026, with exemptions such as affordable homes.

For the wider building safety picture, read our guide to Gateway 2 and the second staircase rule.

At Allitsen Road in St John's Wood, the four design options ran from four flats to seven. A swing like that moves the CIL bill, the affordable housing position and the land value together. That is why our free site appraisal carries CIL and Section 106 as lines from the first option.

Our land value uplift and planning gain team works through the same numbers for landowners. Our planning consultancy team negotiates the obligations on the application.

Want to see what a site can carry after CIL and Section 106? Book a site visit and we will build the levies into the numbers from day one.

Frequently asked questions

What is the difference between CIL and Section 106?

CIL is a fixed, non-negotiable charge per square metre of new floorspace, set in the council's charging schedule. Section 106 is a negotiated legal agreement covering what one scheme needs to be acceptable, such as affordable housing or local transport works.

Do I pay both CIL and Section 106?

Often, yes. In London a residential scheme can pay the Mayoral CIL, the borough CIL and Section 106 obligations. Councils should not charge twice for the same infrastructure.

When is CIL paid?

From commencement of development. The council issues a Demand Notice after it receives the Commencement Notice. Payment is due in full or by instalments under its instalment policy.

Is CIL charged on conversions?

It can be. A change of use that creates new homes is potentially liable, but floorspace in an in-use building, lawfully used for six continuous months in the last three years, can be deducted. Long-vacant buildings often lose that deduction.

Do small developments pay Section 106 affordable housing?

Nationally, affordable housing is sought on major development: 10 or more homes, or 0.5 hectares or more. Smaller schemes can still have Section 106 obligations for other things, such as car-free restrictions.

Can a Section 106 agreement be renegotiated?

Yes, by agreement through a deed of variation at any time, or by formal application after five years. In London, the 2026 time-limited route lets stalled consents move to its terms with a deed of variation and a section 73 application.

Buying or appraising a London site?

Send us the address. We visit, test what can be built and show you the scheme after CIL, Section 106 and build cost, before you commit. Book a site visit.

WhatsApp us