Skip to content
Request a callbackCallback

For developers building on tight London sites

The Party Wall Act for Developers: Notices, Awards and Programme

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read

Row of brick terraced houses sharing walls and chimney stacks

The short answer

The Party Wall etc. Act 1996 lets a developer build on the boundary, work on a shared wall and dig near a neighbour's foundations, but only after written notice.

  1. Two months' notice for work to a party wall or party structure.
  2. One month for a new boundary wall or a dig within 3 or 6 metres.
  3. No written consent within 14 days means a dispute, settled by a surveyors' award.
  4. Serve notices early: the Act can't stop your scheme, but it can delay it.

Party wall problems rarely kill a London scheme. They delay it. The notices go out when the contractor is ready to start, and the awards take months.

The Party Wall etc. Act 1996 gives a developer clear rights. You can build on the boundary, work on a shared wall and dig near a neighbour's foundations. But first you must serve written notice.

This guide covers the notices, the awards, who pays and how to protect your programme. Planning a basement or a new build? Book a site visit and we'll map the neighbours with you.

The three kinds of party wall notice

Party wall notices and their minimum periods
NoticeSectionTypical workNotice before work
Party structure notice2Cutting in beams, raising or thickening a wall, underpinning, removing chimney breasts, rebuilding, work to a floor between flats2 months
Line of junction notice1A new wall on or astride the boundary1 month
Adjacent excavation notice6Digging or foundations near a neighbour's building1 month

A notice is only valid for a year, so don't serve it too far ahead. The neighbour can agree to an earlier start, but doesn't have to.

The 3 metre and 6 metre rules

Section 6 catches two situations:

  1. within 3 metres of a neighbour's building, where your dig goes deeper than their foundations;
  2. within 6 metres, where your dig cuts a line drawn down at 45 degrees from the bottom of their foundations.

On a London terrace or a tight infill plot, a basement, a piled wall or even a lift pit usually triggers one or both. You often won't know the neighbour's foundation depth. Assume the notice is needed unless trial pits prove otherwise.

Who counts as an adjoining owner

"Owner" under the Act is broader than people expect. It includes:

  • the freeholder;
  • any leaseholder with a lease of more than one year;
  • anyone under contract to buy either of those.

A converted Victorian house next door might have a freeholder and four long leaseholders. Each is an adjoining owner, and each can appoint a surveyor. With neighbours on three sides, that can mean a dozen owners or more. So title searches at HM Land Registry are the first job, not the last.

The Act applies to Crown, government and local authority property too.

What happens after you serve notice

  1. The neighbour consents in writing. Work can go ahead after the notice period. Agree a schedule of condition anyway; it protects both sides.
  2. The neighbour dissents, or says nothing for 14 days. A dispute is deemed to have arisen.
  3. Surveyors are appointed. Either one agreed surveyor, or one for each owner. Those two pick a third surveyor, used only if they can't agree. If a neighbour refuses to appoint, the Act lets you appoint one for them after a further notice.
  4. The award. It sets what work is done, how and when, the protection, access and who pays. It usually attaches a schedule of condition.
  5. The appeal window. Either owner can appeal to the county court within 14 days of the award being served.

A neighbour can also serve a counter-notice within one month. It asks for extra work for their own benefit, such as deeper foundations. They pay for what benefits them.

Who pays for party wall surveyors and works

The building owner, usually the developer, normally pays for the works and both surveyors. The work is for their benefit. The neighbour may contribute where the work is needed because of their own defects or lack of repair.

Brick buildings of different heights built tight against each other in London

Neighbours can also ask for security for expenses before notified work starts. That is money held, or a bond, in case the developer stops halfway. It is usually asked for on intrusive or complex works, such as basements. Put it in the cash flow.

I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away. We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP. We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care. We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.

Lia Lavryk, Google reviewSee all reviews on Google

What the Party Wall Act doesn't cover

These sit outside party wall procedure. They catch developers out because they feel similar.

Issues outside the Party Wall Act
IssueWhy it's separate
Crane oversailingNeeds the owner's permission, usually by licence and fee. A jib over land without consent is trespass
Scaffolding on a neighbour's landThe Act only gives access for notified party wall work; otherwise you need a licence
Rights of lightA private legal right with its own rules; see our guide to right to light for London developers
Planning and Building RegulationsParty wall consent replaces neither, and neither replaces party wall notice
Noise and working hoursSet by the council and your construction management plan

How party walls affect the build programme

The Act's timescales look short on paper. The real time goes on title searches, appointments, schedules of condition and awards with several owners. These are the risks we plan for:

  1. Notices served too late. Two months is a legal minimum, not a realistic time to agree several awards on a basement scheme.
  2. Design not ready. Surveyors need drawings, calculations, method statements and temporary works details. A notice for unfinished design invites dissent.
  3. Slow or absent neighbours. Absentee owners and properties in probate stretch the process. Start early on those.
  4. Late requests for security. These can delay the start.
  5. Changes after the award. A new structural design may need an addendum to the award.

Two projects show the right order of work

At Slingsby Place in Covent Garden, a building was taken back to its shell behind retained façades. The work was led by Martin Hickey, now our Preconstruction Director, as Project Director. Neighbours, shops and restaurants surrounded the site on every side.

Structural surveys of the building and façades came first. The temporary works design for the façade retention was signed off before any demolition. Survey, design, agree, then start: party wall work needs the same order.

At the Kensington Olympia penthouse, we refurbished 400 sq m in 12 weeks while every other flat in the building was lived in. We coordinated every delivery and managed noise and waste, and the building managers were happy with how it was handled. In buildings like that, the managing agent becomes part of the project team.

A developer's party wall checklist

That last point matters most. On our design and build projects, party wall procedure is planned with the structural design and the programme. The same applies where we run construction project management for a client. For a scheme still at land stage, our development management team puts it in the risk register from the first appraisal.

Planning a basement, an extension or a new building on a tight site? Book a site visit and we'll plan the party wall route with you.

Party wall checklist for developers

  • Search the title of every adjoining property, including leaseholders over one year.
  • Dig trial pits or find records of neighbours' foundation depths.
  • Draft notices from the structural design, with drawings and method statements.
  • Serve notices early enough for several awards, and within a year of the start.
  • Put surveyor fees, security for expenses and neighbour works in the cost plan.
  • Record schedules of condition before any work starts.
  • Get separate licences for crane oversail and scaffolding.
  • Make one person accountable from notice to final inspection.

Frequently asked questions

Does a developer need a party wall agreement?

If the work falls under the Act, you must serve notice. That covers work to a party wall or structure, a new wall on the boundary, or a dig within 3 or 6 metres of a neighbour's building. You then need the neighbour's written consent or a surveyors' award before that work starts.

How much notice do I have to give?

Two months for work to an existing party wall or party structure. One month for a new wall on the line of junction or for excavation within 3 or 6 metres. A notice lapses if the work doesn't start within a year.

What happens if a neighbour doesn't respond?

If there is no written response within 14 days, a dispute is deemed to have arisen and surveyors must be appointed. If the neighbour won't appoint one, the Act lets you appoint a surveyor for them after a further notice.

Who pays the neighbour's party wall surveyor?

Usually the building owner, because the work is for their benefit. The neighbour may contribute where the work is needed because of their own defects or lack of repair, or where they asked for extra work.

Can a neighbour stop my development with the Party Wall Act?

No. The Act can't stop lawful work, but it controls how and when notified work is done. Starting without notice can lead to a court injunction.

Does the Party Wall Act cover crane oversailing or scaffolding?

Crane oversailing isn't covered: you need the owner's permission, usually by licence. Scaffolding on a neighbour's land is only covered where it's needed for notified party wall work.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Building on a tight London site?

Our team visits the site, maps the adjoining owners and builds party wall procedure into the programme from day one. Book a site visit.

WhatsApp us