Skip to content
Request a callback

Construction Logistics Plans in London: What Developers Must Plan For

London street with blue site hoarding, skips and a conveyor outside a live construction site

A Construction Logistics Plan (CLP) sets out how materials, waste, plant and workers will get to and from a construction site, and how the impact on the roads, neighbours and people walking and cycling will be kept down. In London, the London Plan (Policy T7) says CLPs will be required and must follow Transport for London guidance: an outline CLP goes in with the planning application, and a detailed CLP is approved before work starts, usually to discharge a planning condition.

Treat it as paperwork and it becomes the thing that stops your site. Treat it as the first programme document and it saves weeks.

Outline CLP vs detailed CLP

TfL's Construction Logistics Planning guidance (version 1.2, April 2021, adopted nationally through CLOCS) splits the plan in two.

Outline CLPDetailed CLP
WhenWith the planning applicationPre-construction, at discharge of conditions
Who writes itDeveloper and design team, often with a transport consultantDeveloper with the appointed contractor
Level of detailExpected activity, routes, main constraints, likely measuresProgramme by phase, vehicle numbers, booking, holding areas, monitoring
How it bindsCommitments written into the Section 106 agreement or conditionsApproved by the council, then implemented and monitored on site
StatusFixed with the permissionA living document, reviewed before each new phase

Medium and higher impact developments need both. Smaller schemes often cover logistics in the Transport Assessment, but a council can still ask for a detailed CLP where the site has specific problems: a narrow street, a school next door, a bus route or a red route.

What a CLP has to contain

The TfL guidance gives a structure that most London boroughs expect to see:

  1. Introduction. The developer, the site, who wrote and approved the plan, and its objectives.
  2. Context and constraints. Planning policy, local access, community considerations and scaled maps of the site and surroundings.
  3. Programme and method. The construction phases, from demolition and enabling works to fit-out.
  4. Routing and site access. Strategic and local routes, roads to avoid, and site plans showing gates, loading and holding areas.
  5. Measures to reduce impact. Each one labelled as committed, proposed or considered.
  6. Vehicle movements. Estimated trips by phase, with holding and unloading capacity.
  7. Implementation, monitoring and updates. Who checks compliance, what is recorded and how the plan changes.

The measures are where the plan earns its keep: delivery booking systems, consolidation centres, off-peak deliveries, holding areas off the street, shared deliveries with neighbouring sites, and using rail or water where the site allows it. Policy T7 asks development proposals to consider rail and water for materials, and to keep safe access for people walking and cycling at all times during construction.

The London rules your logistics plan must respect

CLOCS and FORS

The CLOCS Standard (Construction Logistics and Community Safety) covers how sites, vehicles and drivers are managed to reduce road risk. CLPs normally commit the developer to require CLOCS compliance through procurement, typically with fleet operators holding FORS Silver accreditation. Write it into the building contract, or it won't happen.

Direct Vision Standard and HGV Safety Permit

Since 28 October 2024, any HGV over 12 tonnes driving in Greater London needs an HGV Safety Permit, which requires a Direct Vision Standard rating of three stars or the fitting of the Progressive Safe System. Operators running a vehicle without a valid permit face a penalty charge of up to £550. Your suppliers' fleets, not just your contractor's, must comply.

Non-Road Mobile Machinery (NRMM)

London has its own emission standards for construction plant with engines between 37 kW and 560 kW. Under the Mayor's NRMM rules:

DateStandard
From 1 January 2025Stage IV throughout Greater London
From 1 January 2030Stage V throughout Greater London
From 1 January 2040Zero-emission machinery only

Constant-speed engines, such as generators, already need to meet Stage V across London. Most sites must register all in-scope machinery on the online NRMM Register, which is also the only route for exemptions. Check the plant list before the site set-up is priced, because hiring compliant machinery late is expensive.

Highways licences

Hoardings, scaffolding, skips, materials on the pavement, crane oversail and parking bay suspensions each need permission from the highway authority or the owner of the airspace. On a borough road that's the council; on a red route it's TfL. Build their lead times into the programme. Crane oversail over a neighbour's land needs their agreement, usually by licence, separately from any party wall procedure.

Looking down into a London basement: tower-crane mast and operatives working on the slab

Why the CLP is a cost and programme document

Every line in a CLP has a price. A delivery window of 9.30 to 3.30 means fewer drops per day. A ban on waiting vehicles means a holding area or a consolidation centre. A narrow gate means smaller loads and more trips. A requirement for a banksman at every movement means labour on the preliminaries.

That's why the outline CLP written for planning should be tested by someone who will actually build the scheme. A plan that promises the council an impossible delivery regime gets written into the Section 106 agreement, and the contractor inherits it. Bringing the builder in at that stage is what a pre-construction services agreement is for.

What good London logistics looks like on site

We've delivered work where the neighbours never stopped trading, and the logistics plan is what made it possible.

  • At Portsoken House in Aldgate the rest of the building stayed let, so the reception was rebuilt at nights and at weekends and the other tenants were never interrupted.
  • On Savile Row, we refitted Drake's flagship store over 12 weeks while it stayed open, with every delivery and work schedule planned around trading.
  • On Herbert Crescent in Knightsbridge, a 450 m² prime residential refurbishment, we controlled noise and access and protected the neighbours and the building throughout the 32-week programme.

The common thread: the access, delivery and noise plan was agreed before work started, and someone on site owned it every day.

Developer's CLP checklist

  • Outline CLP drafted with input from someone who will build the scheme.
  • Delivery hours, holding areas and vehicle sizes tested against the programme.
  • CLOCS compliance and FORS Silver written into the building contract.
  • Every supplier's HGVs checked for the Direct Vision permit.
  • Plant list checked against London NRMM standards, and the site registered.
  • Highways licences and parking suspensions in the programme with their lead times.
  • Crane oversail and scaffold licences agreed with neighbours.
  • Monitoring: who records vehicle movements, complaints and breaches.
  • Detailed CLP updated before each new phase.

On our design and build projects, and where we run construction project management for a client, the logistics plan is written alongside the programme and priced into it. For schemes still at land stage, our development management team tests access and logistics in the first appraisal, before the scheme is fixed.

Planning a development on a tight London site? Send us the address. We'll look at the site, the access and what it will take to build.

Get my free site appraisalDownload the free Investor & Developer guide

Construction logistics plans: questions

What is a construction logistics plan?

A plan showing how construction vehicles, materials, waste and workers will reach and leave a site, and how the impact on roads, neighbours and people walking and cycling will be reduced. In London it follows Transport for London guidance.

When is a construction logistics plan required in London?

The London Plan says CLPs will be required for development proposals, proportionate to the scheme. Medium and larger schemes normally submit an outline CLP with the planning application and a detailed CLP before construction starts, usually under a planning condition.

What is the difference between a CLP and a construction management plan?

A CLP focuses on the supply chain: vehicles, routes, deliveries and their effect on the road network. A construction management plan, or construction environmental management plan, covers wider site issues such as noise, dust and working hours. The CLP is usually prepared first and feeds into it.

Who writes the detailed CLP?

The developer is responsible, but the detailed CLP is normally written with the appointed contractor, because it depends on their programme, method and supply chain.

Do construction lorries in London need a Direct Vision permit?

Yes, if they are over 12 tonnes. Since 28 October 2024 an HGV Safety Permit requires a three-star Direct Vision rating or the Progressive Safe System, and running without one can mean a penalty charge of up to £550.

What NRMM standard applies on London construction sites?

Since 1 January 2025, machinery with engines of 37-560 kW must meet at least Stage IV across Greater London, rising to Stage V from 1 January 2030. Generators already need Stage V, and most sites must register their machinery on the NRMM Register.

Own a site or a building in London?

Send us the address.
The site appraisal is free.

Submit your site for a free appraisal
WhatsApp us