Collingwood House, Islington
Rooftop extension on an occupied building: one- and two-storey options tested at pre-application
Appraisal target, not a result
£3.9M target GDV for fivenew apartments
Live project: pre-application stage
- 2options drawn: one storey and two
- 5apartments in the one-storey scheme
- 9apartments in the two-storey option
- 18 mheight line that changes the fire rules
Can this roof carry new homes? Find out before the full application
The freeholder of Collingwood House, a property investment company, owns a four-storey block on Mercers Road in Islington: a gym below, 13 flats above and a wide flat roof. The question was simple. Could a rooftop extension of one or two storeys add new homes?
The answer was not simple. The council had advised against a two-storey rooftop scheme here in 2016 and again in 2017. The building is in a conservation area and dates from 1938 to 1939, so there is no permitted development shortcut: it needs full planning permission.
So we did not start with a full application. Craftex assembled and manages the whole consultant team as the owner’s single point of contact, and split the work in two: first prove there is a scheme, then draw it and ask the council. This is a live project. Nothing on this page is a planning result.
The building as found
- Built
- 1938 to 1939
- Height today
- Four storeys
- Planning context
- Conservation area
- In use throughout
- Gym, 13 flats
Own a building with an unused roof?
Send us the address. A director looks at the planning route, the height and the likely structure, and tells you whether a rooftop scheme is worth testing. Free, and we come back to you the same working day.
Rooftop extension drawings: one storey and two, tested side by side
Concept drawings for both options, prepared for the pre-application. They show volume and layout, not final architecture. Our goal for the owner is at least five two-bedroom apartments; the appraisal puts the value of five new apartments at about £3.9M. That figure is a target, not a result.
Tap to enlarge
Section: one new storey
One new floor on the existing roof slab, set back from the parapets. The existing stair is carried up to serve it.
Tap to enlarge
Section: two new storeys
A second, smaller floor above the first. This is the option that takes the building across the 18 m line.
Tap to enlarge
Fourth-floor plan: five apartments
The one-storey scheme: five apartments around the two existing cores, with terraces and a green roof on the set-backs.
Tap to enlarge
Front elevation: two storeys
The two-storey option from Mercers Road: about nine apartments and roughly 575 sq m of new floor space.
Upward extension on Mercers Road: existing and proposed
Our planning review found seven upward extensions approved within about 300 m. The pattern is consistent: set-back, recessive additions are approved; dominant ones are refused. So the design sits behind the existing parapet and reads as a new crown to the building, and the heritage case is written around that.
Tap to enlarge
Tap to enlarge
Want to see what your roof could hold?
We draw the options, count the homes and show you what each one triggers in planning, fire safety and structure, before you commit to an application.
The building and its history: a 1938 warehouse, altered for eighty years
Tap to enlarge
Built as a tobacco warehouse
Collingwood House was built in 1938 to 1939 as a tobacco company’s headquarters: a warehouse and loading bay on the ground floor, offices and a boardroom above. Even then the floors stepped back at different levels.
The section shows it today. No two parts of the roof are quite the same height, which is why nobody could trust a single desktop figure for this building.
Extended again and again
The building has been added to in almost every decade: at the rear in the 1950s and 1960s, at third-floor level around 1989, and at first floor around 2020. A warehouse became offices, then a health club, then flats.
From the roof you can read it: older brick wings, a later clad storey, and lower roofs between them.
Tap to enlarge
Old frame, new steel
Past surveyors did not even agree on what holds it up. One record calls the frame steel; a later engineer called it concrete. Our structural engineer walked the building, read the 1938 drawings in the archive and marked up each floor: original structure in blue, later additions in red.
What this means for you: on an old, much-altered building, the history is the first survey.
Extensions, changes of use and earlier rooftop attempts
From the Historic Building Report (December 2018), the structural engineer’s report (November 2026) and the planning record.
| When | What changed |
|---|---|
| 1938 to 1939 | Built as a tobacco company’s headquarters: warehouse on the ground floor, offices above |
| 1946 | Single-storey extension permitted to the south (since demolished) |
| 1950 to 1966 | Rear extensions at first and second floor; third floor turned into a canteen |
| 1953 | Roof assessed for staff recreation use; the slab and framing were judged adequate for it |
| 1982 to 1986 | Warehouse closed; two applications to convert the whole building to flats refused at appeal |
| 1988 to 1990 | Refurbished for business use: third-floor extension, rear extension, parts demolished |
| 1998 | Ground, first and part of the second floor converted to a health club |
| 2014 to 2015 | Parts of the second and third floors converted to flats |
| 2016 and 2017 | Council gave adverse pre-application advice on a two-storey rooftop scheme |
| Around 2020 | Single-storey extension at first floor for the gym and its plant |
| 2026 | Rooftop extension taken to pre-application by Craftex (this project) |
Craftex is also delivering a separate project in the same building: the former gym space on the second floor is being converted into four flats.
Airspace development risks: what decides a scheme like this
Six questions decide whether this roof gets built on. Planning is only one of them.
| Question | Why it matters here | What we do about it |
|---|---|---|
| Planning route | Conservation area, built before 1 July 1948: no permitted development route. Two adverse pre-application responses on record. | Policy and precedent review first; both options tested at pre-application before a full application. |
| Height and fire safety | On desktop data the building is about 12.4 m: about 15.5 m with one storey, about 18.6 m with two. Over 18 m it becomes a higher-risk building. | Measured survey of the real heights before the storeys are fixed. We are still working through the fire constraints of a building above 18 m. |
| Scale | At around ten homes a scheme becomes major development: planning committee, a full Section 106 agreement and 45% on-site affordable housing. | Unit numbers, Section 106 and the Community Infrastructure Levy (CIL) assessed for each option, so the owner sees the cost of each threshold. |
| Structure | A 1938 frame with decades of additions. Nobody had established what the frame and foundations could take. | Structural feasibility for one storey and two, assessed separately. |
| A building in use | Works above an operating gym and 13 occupied flats, on a tight site with restricted crane access. | Buildability reviewed with the engineer from the first stage: lightweight construction, access and sequence. |
| Legal title | Many registered interests in one building. Airspace and Landlord and Tenant Act 1987 rights, lease terms, restrictive covenants, rights of light, party walls, crane and access. | A risk list handed to the owner’s solicitors at the start, so legal work runs alongside planning. |
The pattern: every one of these can stop the scheme, and each can be answered at modest cost before the expensive work starts.
Which of these could stop your scheme?
Tell us about the building. We go through the same six questions with you and say plainly where the risk sits.
Pre-application advice done in the right order: de-risk first
Tap to enlarge
Spend a little to find out, before a lot
Stage 1 answers three questions. A measured survey fixes the real heights. A structural feasibility study asks whether the frame and foundations can carry the load. A planning review tests policy and precedent. Each stage is paid in advance, and if Stage 1 shows the scheme does not stand up, the commission stops and no further fees are due.
The engineer’s feasibility report came back in November 2026. On its assumptions, one lightweight storey can be carried by the original frame without strengthening, subject to site investigation. A second storey is a bigger structural step: the report sets out the extra support and testing it would need. Areas already extended upwards are treated with caution, as the overlay shows.
What this means for you: you know whether you have a scheme before you pay for one. Our development feasibility study works the same way.
Where the project stands: pre-application in progress
An honest status, as of November 2026. We will update it as the project moves.
| Step | Status |
|---|---|
| Stage 1: survey, structural feasibility, planning review | Done; structural feasibility report issued November 2026 |
| Stage 2: concept design for one and two storeys | Drawn (the drawings on this page) |
| Pre-application documents | Ready to submit, with a request for a meeting with the council |
| Meeting with the council | Not yet held; we expect it two to three weeks after submission |
| Written advice from the council | Not yet received; we expect it four to six weeks after the meeting |
| Five-apartment, one-storey scheme | Being prepared in parallel and assessed financially: CIL, Section 106, value and build cost |
| Viability assessment and full planning application | Next stage; not started |
There is no statutory timeframe for pre-application responses, so the dates above are expectations, not promises.
Start with the stage that can say no
A staged proposal with a clear scope for each consultant, a list of what is not included, and a stop point after the first stage. One team and one point of contact from the first survey to the planning decision: that is our development management service.
Our team
- in
Sviatoslav is a self-made entrepreneur with a degree in mechanical engineering and over 10 years of hands-on experience in the UK construction industry. Starting as a demolition labourer and carpenter on London job sites, he personally worked through every stage of the building process — from groundwork and fit-out to project planning, estimating, procurement, and full-scale management.
This unique, bottom-up experience allows him to run projects with maximum efficiency, clear communication, and minimal friction — both on site and with clients.
Under his leadership, Craftex has delivered high-end residential and commercial projects across London, known for their snag-free finishes, smooth execution, and strong pre-construction planning.
Today, Sviatoslav oversees the company's operations and delivery teams while spearheading its expansion into design & build and high-value commercial sectors, including office fit-outs, data centres, and property development ventures.
Clients value his deep technical insight, clear leadership, and relentless focus on delivering clean results — on time, on budget, and to the highest standard.
-
Rob leads Craftex's development partnerships with landowners, investors and family offices.
Over 20 years he has held Managing Director and Land Director roles at plc housebuilders, including Berkeley Homes, Countryside and St Modwen, and has been directly responsible for delivering more than 3,000 private homes, 1,000 affordable homes and 750 build-to-rent homes. His schemes include Acton Gardens (2,340 homes), St Andrew's Park, Uxbridge (1,340 homes) and the Old Vinyl Factory, Hayes.
Rob has served as a non-executive director of three housing associations and two private housebuilders. He holds a first-class engineering degree, a postgraduate diploma in financial strategy from Oxford, an MBA from London Business School and a Master of Studies from Cambridge, where his research focused on AI in construction.
-
Joe has 37 years of experience working on both the commercial and operational side of construction. His previous works cover multiple sectors, including high-end residential refurbishments, new build construction, and commercial property renovations. Examples include the fit-out of Dior’s flagship store on Bond Street and residential developments in Belgravia. Budgets have also varied, with projects ranging from £100K to £135M. This experience and the transferrable skills gained enable Joe to successfully manage any project, regardless of type, style, or value.
At Craftex, Joe is responsible for ensuring the smooth operation of all designs and builds. With a collaborative approach and strategic thinking, he ensures our high standards and happy customers are maintained. He is heavily involved in developing and implementing innovative procurement solutions, as well as envisaging any potential problems along the way for proactive and preventative project management. Joe also takes on the role of influencing the design process and supporting development in others, passing on his wealth of skills and knowledge to the team.
-
Martin has over 50 years of experience in construction having started in the industry as a labourer at the age of 16. Since then, he progressed to site manager before running his own company from 1987 to 1996. Turning to contracts management shortly after, Martin now has 18 years of experience in the role. During this time, he has led multiple high-quality building projects, with a particular passion for sustainable methods and technological advancements in construction.
At Craftex, Martin is responsible for preconstruction and project management, offering innovative solutions and ensuring all aspects of the projects run smoothly. He is also pivotal in the implementation of digital solutions and SaaS tools, enabling more efficient project management and process analysis, besides pushing us closer to our 100% paper-free pledge.
-
With a unique set of skills honed over the past 16 years in the retail and commercial sector both in the UK and overseas, Konstantin Jegorovs brings a wealth of experience, insights and knowledge to his role as Craftex’s Projects Director.
A graduate of construction management from Oxford Brookes university, Konstantin has led flagship projects of up to £5 million in value for commercial banks, complex fit outs of occupied commercial office premises, innovative and challenging aparthotels and high-end residential projects for the UAE Royal Family.
Overseeing every single element of each project from the initial consultation to delivery phase, Konstantin is intrinsic to Craftex’s customer service and collaboration offering, thanks to a proactive and forward-thinking approach. He deploys his experience in the development and improvement of policies, processes and strict adherence to ISO business management systems to ensure the flawless delivery of Craftex projects, with an unwavering commitment to quality that ensures each client gets the maximum return for their investment.
Fluent in both Russian and English and with a plethora of industry-relevant qualifications, Konstantin is a valuable asset to the Craftex team and committed to helping our clients see their visions become reality.
What Craftex delivers at pre-application
One appointment instead of five. The owner deals with Craftex; we brief, coordinate and answer for the team. This is how our planning consultants run a difficult site.
| Deliverable | What the owner gets |
|---|---|
| A multi-disciplinary team | Planning consultant, structural engineer, architect and measured surveyor, coordinated by our planning director |
| One staged proposal | A clear scope for each consultant, an exclusions list and a staged payment schedule with a stop point |
| Planning strategy | Policy and precedent review, and the heritage case for a set-back design that re-crowns the building |
| Risk list for the owner’s solicitors | Airspace and leaseholder rights, lease terms, covenants, rights of light, party wall, crane and access |
| Measured survey | Heights and levels of the building and its neighbours |
| Structural feasibility | One-storey and two-storey options assessed separately |
| Pre-application package | Concept massing for both options, schedule of accommodation, white-box 3D images, initial Design and Access and Heritage Statement, and the submission |
| A single point of contact | One director who reports, chases and recommends whether to go on |
Free value: take this with you
Twelve checks before you commission a rooftop extension
-
Before you spend on design
- Check the permitted development route first. A conservation area or a building finished before 1 July 1948 closes it, and full planning is a different budget.
- Pull the planning history. Earlier refusals and pre-application letters on your building tell you what the council has already said no to.
- Read the precedents on your street. Which rooftop schemes nearby were approved, which were refused, and what the decision notices say about set-backs.
- Find the building’s own history. Old extensions and changes of use decide what the structure can take.
-
Before you fix the number of storeys
- Measure the real height. Desktop figures are not enough when 18 m changes the fire-safety regime for the whole building.
- Get a structural feasibility view for each option. One storey and two are rarely the same question.
- Count the homes against the thresholds. Ten homes is major development: committee, Section 106 and on-site affordable housing.
- Plan the build over people. Occupied flats, a trading ground floor and crane access all shape cost and programme.
-
Before you talk to the council or the leaseholders
- Send the title to your solicitors early. Airspace rights, lease terms, covenants and rights of light can stop a scheme that planning would allow.
- Take legal advice before any disposal of the airspace. Leaseholders may have statutory rights, and the notices must be served correctly.
- Go to pre-application with a scheme that has survived its own tests. Survey, structure and policy first; drawings second.
- Stage the fees. Agree in writing that the work stops, with nothing more to pay, if the first stage says no.
Certified, insured, compliant
- ISO 9001 Quality Management
- ISO 14001 Environmental Management
- ISO 45001 Health & Safety Management
- SafeContractor Approved
- SSIP Safety Schemes in Procurement
- CDM 2015 Principal Contractor
- CIS Gross
- Public Liability £10,000,000
- Employers' Liability £10,000,000
- Professional Indemnity £10,000,000
- Defects liability standard 12 months, extendable
- Warranty up to 10 years available
- Collateral warranties from our consultants & design team
What our clients say
See all reviews on Google-
Hired Craftex for our conversion project. We had to convert a 600m2 office into 8 apartments. Guys did an excellent job in terms of program efficiency and quality of the finishes which gave us a big upside to exit the project 2 months faster than other competitors’ timelines.
Misha Levit
-
Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.
Rhea Langford
-
I’d like to thank the team at Сraftex for the work they did on our office.
It was really important for us to get the work done quickly, but without compromising on quality, as we regularly have clients and guests visiting and needed to move into the new office within a month.
We spent around two weeks discussing and agreeing all the details before the work started. What I really appreciated was that everything we agreed beforehand was actually followed through during the job. The work was also completed on time.
Thanks to the whole Сraftex team for a great job. I’d definitely use them again if we need any work done in the future.IURII PYLYPETS
-
We recently worked with Craftex and honestly couldn’t be happier with the results. From start to finish, the team was professional, reliable, and highly skilled. The quality of workmanship exceeded our expectations, and everything was completed on time and to a very high standard.
Communication throughout the project was excellent, and they always went above and beyond to make sure we were satisfied. It’s rare to find a construction company that combines professionalism, attention to detail, and great customer service so well.
Without a doubt, Craftex is one of the best construction companies we have ever worked with. Highly recommended to anyone looking for quality and trustworthy builders.Adam Miah
-
Craftex has completed a range of both small and large-scale projects on our commercial property with exceptional precision and quality. Dmitriy consistently delivers courteous, prompt service and has shown great flexibility in accommodating last-minute changes to plans and timelines. I highly recommend Craftex for their professionalism and outstanding workmanship.
Pascal Hunt
-
Great company to work with as always. Super flexible at dealing with evolving requirements and fast deployment and execution.
Akshay Khanna
-
Hired Craftex to do the full design and fit out of my gym in Chelsea. Super efficient and fast team. They gave the best price and a proper fast track program. We managed to open in less than 6 weeks with no headaches or surprises during construction. Quality was great, we had zero snags on completion. I’ve worked with a few companies before but these guys really impressed me from project management to how they treat the client. Top GGs.
Александр Хоменко
-
I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.
John Smith
-
Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.
Pawel Kamionka
-
Highly recommended!
Craftex are the kind of fit-out contractors in London you can truly trust. From the very first meeting, they understood our vision and gave practical ideas to make the most of our space. They turned our old storage area into a clean, efficient, and well-organized warehouse. The team was professional, easy to work with, and clearly took pride in their work.Monika Kamionka
-
We brought in Craftex to refurb our London office and honestly, they made the whole thing way easier than we expected. They listened, suggested ideas we wouldn’t have thought of, and explained everything clearly. Not the cheapest quote we got, but the end result shows why, the place looks modern, clean, and our team actually enjoys being here now. Communication was spot-on too. No chasing and confusion, deadlines were hit. If you want people who genuinely care and don’t treat your project like “another job,” I’d recommend them.
A Google User
-
Sviat and his team at Craftex were brilliant to work with on our office redesign. From the first meeting, they took the time to understand how we actually use the space rather than just pitching generic solutions. They came back with clever, practical ideas to maximise use of the space and get more employees and desks inside . Every step was handled professionally, and the process felt surprisingly smooth for a project of this size. They finished one week ahead of schedule, and the transformation is clear — our office feels brighter, more functional, and much more welcoming. I’d happily recommend Craftex to anyone who wants a reliable design team that also makes the journey enjoyable.
Cucu Iulian
-
We recently worked with Sviat and the Craftex team on a complete warehouse refurbishment, and the results have been outstanding. From the very beginning, their team was professional, organized, and attentive to every detail. The project was completed on time and within budget, without disrupting our day-to-day operations.
Simone Racaku
-
My experience with Craftex was excellent from beginning to end. They took the time to really listen to what I wanted and then offered practical suggestions that made the design even better. I always felt like they cared about creating a space that worked for me, not just one that looked nice on paper. The end result is an office that feels stylish, welcoming, and very functional for day-to-day work. The process itself was straightforward, well-managed, and never stressful. I’d definitely recommend Craftex if you’re looking for office design and build services in London — they made the whole journey a positive one.
Ion Bounegru
-
I’m really pleased with my experience working with Craftex. As a commercial construction firm, they handled everything from start to finish without any unnecessary stress on my side. What impressed me was how they suggested practical ideas that improved the design while also keeping things realistic. The communication was always clear, so I never felt out of the loop. The project ran smoothly, deadlines were met, and the end result is exactly what I was hoping for — a space that feels both functional and modern. It’s not easy finding contractors who are this reliable, but Craftex definitely proved they can be trusted.
Taron Papoyan
-
I had an amazing experience working with Sviat and the Craftex team on our office fit-out in London. They were always professional, responsive, and quick to offer the best advice whenever decisions needed to be made. I really appreciated how they balanced style with practicality — the office doesn’t just look fantastic, it works perfectly for our team. Everything was done with care and attention to detail, and the project never felt overwhelming because they managed it so well. Communication was clear from start to finish, and I always felt involved in the process. I would happily recommend Craftex to anyone looking for a trustworthy contractor.
Artur Dvorak
-
Craftex carried out a warehouse fit-out for us, and I couldn’t be happier with the outcome. The space has been completely transformed into a highly organized and efficient environment that makes our daily operations much smoother.
The team was professional but also very approachable — I always felt comfortable asking questions or giving feedback. They came up with smart, practical solutions that worked perfectly for our setup, and everything was explained clearly along the way.
The best part was how they stuck to the agreed timeline, finishing on schedule without cutting corners. It’s rare to get both quality and reliability, but Craftex delivered both.Roma Shchukin
-
We’re extremely happy with Sviat and the Craftex team’s work. They suggested clever ideas, managed the project efficiently, and delivered a functional, modern space. The team was easy to communicate with and very professional throughout the process!
Polina Lysenko
-
I can honestly say our office has been completely transformed thanks to Craftex. From the very first meeting, the team was approachable, professional, and full of creative ideas that really made sense for our business. They didn’t just focus on how the space would look but also how it would work for the team day-to-day. The new layout is efficient, modern, and welcoming, and you can tell they really thought about the details. The whole process was smooth and surprisingly stress-free. They kept me updated at every stage, which gave me confidence. I’m really happy with the results and wouldn’t hesitate to recommend them to anyone.
Mykyta Khadzhynov
-
The results from Craftex’s commercial refurbishment in London are fantastic. The team was friendly, clear in communication, and made sure the project stayed on track. The workspace now feels efficient, welcoming, and modern. Definitely a team you can trust!
Alaa Betar
-
We hired Craftex for a commercial ground floor fit-out with 2 flats above. There were some minor co-ordination hiccups with third-party suppliers but the team kept it moving. Finish quality was strong. Kitchens and doors look great. I have already asked them for a quote on the next project.
Ben Edell
-
These guys actually deliver. They handled our first industrial to residential conversion near Tower Bridge, turned an old warehouse into 4 modern flats. They stuck to the plan, kept the site clean and the timing was on point. No hidden extras, no drama, just a professional construction company in London that gets the job done.
Богдан Главацкий
-
We recently hired Craftex for a commercial office fit-out project in Central London, and overall, we’re really happy with the result. There was a delay on our side with a custom glass partition supplier, but the Craftex team managed the construction schedule very professionally and kept everything on track. Their guys worked clean, respected our workspace and IT setup, and kept the site tidy throughout. If you're looking for a reliable office refurbishment company in London, I’d definitely recommend Craftex. Would use them again without hesitation.
Ardian Beleshi
-
This was a full high-end renovation of my Victorian rental apartment in Westminster, just off Sloane Square and Belgravia. The scope included full fit-out: electrics, plumbing, a new bespoke kitchen, and a luxury bathroom refurbishment. Craftex took care of everything and made the process easy. They weren’t the cheapest, but you can tell they really know what they’re doing when it comes to prime London property renovations.
The team was professional, organised, and genuinely seemed to care about getting everything right. I was especially impressed with the quality of the finish – the attention to detail really shows in every corner.
I’m very happy with the results and would definitely recommend Craftex to anyone looking for reliable, high-quality renovation work in Central London.Наталия Цимбалюк
-
I was stressed about timing since we had bookings lined up, but they smashed it. Even worked Saturday to finish the floor. My clients love the look — the beauty salon fit-out turned out exactly how I wanted. Couldn’t have pulled it off without their help. Genuinely appreciate the way they communicated throughout the refurbishment. If you need reliable help with beauty salon design or fit-out, especially in a place like Chelsea — these are the guys.
Rami Jusupova
-
We used Craftex for a shop-to-flat conversion in Chelsea — turning an old retail space into two rental units. Access wasn’t the easiest, but the guys handled it well, no drama. Quote was clear, no hidden extras, and they actually stuck to it, which is rare. Finish came out solid, exactly what we needed for rentals. Joe (PM) kept things ticking and communication was always on point. All in all, smooth job — would use them again for sure.👍
Apartify Estates
-
Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.
Hainro Eybers
-
Holistic therapy space fit-out
Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.Dariia Shvyryda
-
Made a full refurbishment and redesign of our Central London office. Fantastic work, quality service and reliable people. Can recommend it to everybody
Nikita Nigai
-
Amazing experience with these guys. I trusted them my apartment in London and Business. They are always accurate, very professional, responsive and neat. They would always advice me right things for my best interest. I had luxury experience with them and I would definitely recommend Craftex to everyone.
Motush Motushev
-
Could not be HAPPIER with Sviat and the Craftex team, they certainly showed me that they’re the number one office design company in London that we’ve had the pleasure of working with. They gave us a unique design just like we wanted, and we loved the first initial draft of the concept. Also have to give them props for Construction, I gave them a tight timeline as we needed to move our team in ASAP, so they pulled double shifts and I didn’t see a drop in quality. Will be to talking to the team when we move up to our next bigger office. Highly recommended A+++
Mikhail Burdoev
-
Very professional company. Craftex did brilliant minimalistic design and completely refurbished my apartment to the highest quality.
Vlad
-
I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away.
We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP.
We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care.
We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.Lia Lavryk
Refer a project
Earn 5–10% lifetime commission
from the revenue we generate from your introduction.
Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.
Rates and conditions apply. See the referral terms.
Rooftop extension and pre-application: your questions
Do you need planning permission for a rooftop extension?
Usually, yes. Some buildings can add storeys under permitted development with prior approval, but that route is closed to buildings in a conservation area and to buildings completed before 1 July 1948. Collingwood House is both, so it needs full planning permission. We check the route in a free site appraisal before any design money is spent.
What is pre-application advice, and is it worth it?
It is the council’s written view on a scheme before a full application is made. On a site with a difficult history it is worth it: you learn what officers will support for the price of concept drawings, not a full application. At Collingwood House the council had already advised against a two-storey rooftop scheme twice, so we test both options first.
Can you build a rooftop extension in a conservation area?
Yes, with full planning permission and a design that respects the street. Near Collingwood House seven upward extensions have been approved within about 300 m. The ones approved were set back and quiet; the ones refused dominated the building below. A heritage statement explains why the design fits.
Can an existing building carry an extra storey?
It depends on the frame and the foundations, and an engineer has to check both. Here the structural feasibility report found that one lightweight storey can sit on the original frame without strengthening, provided site investigation confirms the assumptions. Parts of the building that were already extended upwards are treated more cautiously.
How many flats can a rooftop extension add?
It depends on the roof area the structure can carry and the height the street will accept. At Collingwood House the one-storey scheme is five apartments and the two-storey option is nine. From ten homes a scheme becomes major development, with on-site affordable housing and a Section 106 agreement.
What is airspace development?
Building new homes on top of an existing building, using the unused space above its roof. The owner keeps the building and gains new flats to sell or let. It depends on four things being true at once: planning, the structure, fire safety and the legal rights over the roof.
How long does pre-application advice take?
There is no statutory timeframe. On this project we expect a meeting about two to three weeks after the request is lodged, and written feedback four to six weeks after the meeting. Councils differ, so treat these as working assumptions.
What happens when a building goes over 18 metres?
A residential building of 18 m or more, or seven storeys or more, is a higher-risk building. It falls under the Building Safety Regulator, with stricter fire-safety design and approval gateways before and after construction. That adds time and cost, so the real height is measured before the number of storeys is fixed.
Do leaseholders have a say in an airspace development?
They can. Under the Landlord and Tenant Act 1987, qualifying leaseholders may have a right of first refusal when a freeholder disposes of the airspace. Lease terms, restrictive covenants, rights of light and party wall matters also apply. We list these risks for the owner’s solicitors at the start; the legal advice itself is theirs.
Has the Collingwood House rooftop extension got planning permission?
No. This is a live project at pre-application stage. The pre-application documents are ready to submit and the council has not yet given its view. We will update this page as the project moves; nothing here is a planning result.