For occupiers taking on or refitting an industrial unit
Industrial Fit-Out: How to Fit Out an Industrial Unit Without Losing Months
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
An industrial fit-out turns an empty shell unit into a working space for production, assembly, storage or trade. Check use class, landlord consent, power and floor loading before anything is designed.
- The planning use class must allow your process: E(g)(iii), B2 or B8.
- Most leased units need a licence for alterations, including reinstatement terms.
- Power upgrades and floor loads are the items that most often stop a fit-out.
- Welfare, racking and fire safety follow HSE guidance and the Fire Safety Order.
An industrial fit-out turns an empty shell into a working unit. That means offices and welfare, power and lighting, heating where needed, floors, racking, mezzanines, drainage and fire safety.
Before any of that is designed, check three things. The planning use class must allow what you will do. The landlord must consent to the works. The power supply and floor must carry your equipment.
Those three checks decide the programme. Everything else is construction, which we deliver as industrial fit out and refurbishment. Taking on a unit? Book a site visit and we will run those checks with you.
Industrial fit-out compared with warehouse fit-out
The two overlap, and the same contractor often does both. The difference is what happens inside.
| Warehouse or distribution | Industrial or production | |
|---|---|---|
| Main activity | Storing and moving goods | Making, assembling, repairing or processing |
| Typical use class | B8 storage or distribution | B2 general industrial, or E(g)(iii) light industrial |
| Biggest design drivers | Racking, loading, forklift routes | Machinery, power, extraction, process drainage |
| Floor | Flatness and load for racking | Load for machines, chemical resistance |
| Services | Lighting, office heating, charging | Three-phase power, compressed air, extraction, water |
If your unit is mostly storage and distribution, start with our warehouse fit-out and refurbishment service. Our guide to what a warehouse fit-out involves explains the process.
Step 1: check the use class before you sign
Planning use classes decide what you can lawfully do in the unit.
- E(g)(iii) light industrial covers processes that can run in a residential area without harming amenity. It sits inside Class E, so it can share a building with offices.
- B2 general industrial covers industrial processes outside E(g).
- B8 covers storage or distribution, including open-air storage.
Read the unit's planning history, not just the agent's particulars. A permission can carry conditions on hours, deliveries, noise or the exact use. If your process needs another class or breaks a condition, you need permission first. Our guide to Class E explains how the classes fit together.
Step 2: landlord consent and the lease
Most industrial units are leased. So almost every fit-out needs a licence for alterations from the landlord.
Expect the landlord to ask for drawings and structural calculations for anything fixed to the frame or slab. They will also want a method statement, insurance details and often a promise to reinstate at lease end.
Two things to negotiate before you sign:
- What you must strip out at lease end. Offices, mezzanines and racking can help the next tenant, or become a dilapidations claim against you.
- Who pays for what. A landlord may fund shell upgrades, such as roof lights, LED lighting or energy improvements, and leave the process fit-out to you.
The process is covered in our licence for alterations guide.
Step 3: power, floor and structure
These three items most often stop an industrial fit-out after it has started.
Power. Check the incoming supply against your machines, charging and heating loads before you commit. An upgrade from the network operator can take months. It is a long-lead item in its own right.
Floor. Heavy machinery, racking and mezzanine columns put point loads on the slab. Ask for the floor's design loading, or have it tested. Some processes also need a chemical-resistant or anti-static finish.
Structure. Anything hung from the roof, such as cranes, extraction or services, needs the frame checked. At the Drake's railway-arch warehouse, nothing could be drilled into the arch at all. So every partition and service frame was designed to stand on its own. The 500 sq m space was delivered in 8 weeks.
We recently worked with Sviat and the Craftex team on a complete warehouse refurbishment, and the results have been outstanding. From the very beginning, their team was professional, organized, and attentive to every detail. The project was completed on time and within budget, without disrupting our day-to-day operations.
Step 4: offices, welfare and mezzanines
Most industrial occupiers need offices, a canteen and toilets inside the shell. The legal minimum for welfare is set by the Workplace Regulations. HSE guidance gives these minimums for mixed use.
| People at work | Toilets | Washbasins |
|---|---|---|
| 1 to 5 | 1 | 1 |
| 6 to 25 | 2 | 2 |
| 26 to 50 | 3 | 3 |
| 51 to 75 | 4 | 4 |
| 76 to 100 | 5 | 5 |
Add drinking water and somewhere to eat. Provide changing facilities where people wear work clothing, and emergency showers or eyewash where the process needs them.
At the Banbury warehouse, we refitted the whole 2,500 sq m building in eight weeks, including a new 148 sq m welfare and storage area. The warehouse kept running throughout. The work included a storage room with pallet racking and metal safety barriers.
At a 120 m² warehouse in Hackney with 6 m ceilings, we installed electric heating and bespoke lighting. There was no natural outflow, so we fitted pumped drainage for a sink and an emergency safety shower.
A mezzanine is often the quickest way to fit offices into a tall unit. It usually needs Building Regulations approval. Our guide to warehouse mezzanine floor regulations covers escape, fire protection and access.
Step 5: racking and storage
Racking is equipment, not furniture, and it is treated that way. HSE's warehousing guide (HSG76) and the codes of the Storage Equipment Manufacturers' Association (SEMA) set the expected practice.
- Design to a recognised standard, such as EN 15512, with load notices on every bay.
- Install with a competent installer, after checking the floor for point loads.
- Name a person responsible for racking safety.
- Inspect regularly. Trained staff make visual checks, and an expert inspects at least once a year.
Plan racking with the lighting and sprinkler layout. Racks fitted after the lights often leave dark aisles and blocked sprinkler heads.
Step 6: fire, building regulations and CDM
- Fire. The Regulatory Reform (Fire Safety) Order 2005 puts duties on the responsible person, usually the occupier. The fire risk assessment must reflect the new layout, storage and processes.
- Building Regulations. New offices, mezzanines, structural changes, drainage and changes to escape routes usually need approval.
- Energy. Lighting, heating and fabric work affects the energy rating, which matters for letting.
- CDM 2015. As the client, you have legal duties for health and safety on the project. See our guide to CDM client duties.
Keeping the unit running during the works
Most industrial fit-outs happen in buildings that are already working. That changes the job.
- Phase the works so production or dispatch never stops.
- Separate site areas from live areas with hoarding and controlled routes.
- Agree noisy and dusty work windows with the operations manager.
- Plan deliveries around the yard's own lorry movements.
- Keep fire exits and alarms live throughout.
That is how Banbury was delivered: a new area built inside a running warehouse, with operations carrying on next to it.
Industrial fit-out checklist
Our in-house team plans and builds industrial and warehouse fit-outs, from the mechanical and electrical design to the last racking bay. For new-build units, see our warehouse and logistics construction service.
We take on construction projects from £100,000. Ready to check your unit? Book a site visit and we will walk it with you.
Before work starts on site
- Use class and planning conditions checked for your process.
- Licence for alterations agreed, including reinstatement.
- Incoming power capacity confirmed against your loads.
- Floor loading confirmed for machines, racking and mezzanine columns.
- Welfare designed to HSE minimums for peak headcount.
- Racking designed, installed and inspected to SEMA practice.
- Fire risk assessment updated for the new layout.
- Building Regulations approval in place for offices, mezzanines and structure.
- Phasing plan agreed if the unit is already operating.