Victorian and Edwardian House Renovation: Costs, Process and Choosing a Builder

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 13 min read

Finished period townhouse living room with a white marble fireplace, built-in shelving and tall black-framed windows

The short answer

A Victorian or Edwardian house renovation costs about £1,150 to £1,800 per m² with Craftex, depending on how deep the work goes (our 2026 rates, construction only, ex VAT and fees). A 300 m² family house comes to roughly £344,000 to £540,000 before VAT, design fees and contingency.

  1. Layout kept, with new wiring, plumbing, heating, kitchen and bathrooms: £1,150 to £1,350 per m².
  2. Back to brick, with new openings and steels: £1,530 to £1,800 per m²; with an extension or loft, about £1,835 to £2,160.
  3. On top: 20% VAT, design and engineering fees, and a contingency of 5% to 10% of the works.
  4. Design comes first: a fixed price needs finished drawings, and a change after plastering is the most expensive kind.

A Victorian house renovation with Craftex costs £1,150 to £1,350 per m² when the layout stays. Back to brick, it is £1,530 to £1,800 per m². These are our 2026 rates for construction only, before VAT and fees.

For a 300 m² Edwardian family house in Surrey, that is about £344,000 to £405,000, or £459,000 to £540,000 back to brick. Structure, services, an extension and the kitchen and bathroom specification push it up. Keeping the layout and good original features bring it down.

This guide is for families taking on their first period house, often with a mortgage, to live in for decades. It shows the full budget, why design comes first, the process step by step and plain answers to the worries we hear most.

We are a design and build team for house renovation in London and the home counties. Buying now? Send us the floor plan and we'll price the works before you exchange.

What a Victorian house renovation costs per m²

Builders price a renovation by floor area and by how deep the work goes. The price of the house does not set the cost of the works. Measure the gross internal area, inside the outside walls on every floor, then pick the depth of work.

Our example is a large detached Edwardian family house in Surrey: 300 m² (about 3,200 sq ft) over three floors. Surrey's average house is about 125 m² on EPC data from January 2026, so this is a big home, well over twice the average.

Our 2026 rates per m² and totals for a 300 m² house, construction only, ex VAT and fees. Your fixed figure comes after a survey.
Depth of workWhat it coversPer m²300 m² house
Light refreshDecoration, flooring, a kitchen or bathroom, services keptBelow £1,150, priced room by roomUnder £344,000
Full refurbishmentLayout kept: rewire, replumb, new heating, kitchen, bathrooms, joinery£1,150 to £1,350£344,000 to £405,000
Structural renovationBack to brick: new openings and steels, all-new services£1,530 to £1,800£459,000 to £540,000
Remodel and extendBack to brick plus an extension or loft room£1,835 to £2,160£551,000 to £648,000

With 20% VAT, the full refurbishment comes to about £413,000 to £486,000. The back-to-brick renovation comes to about £551,000 to £648,000. Fees and contingency sit on top, as the next section shows.

A family planning to stay 30 years or more usually lands in the middle two rows. Old wiring, lead or iron pipes and tired heating are hidden in the walls. Replacing them once, before the finishes go in, is far cheaper than opening the house again later.

Planning a bigger house or a basement? Our guides to house extension cost in London and loft conversion cost in London price the new floor area.

The full budget for a 300 m² family house, with VAT and fees

The build is the biggest line, but not the only one. A mortgage buyer needs every line before exchange, because the deposit, the loan and the works all come from the same pot.

Full budget for the 300 m² Surrey house renovated back to brick (works at our 2026 rates; fee and contingency lines are allowances)
LineWhat it isAllow
WorksConstruction at our 2026 rates£459,000 to £540,000
VAT20% on the works£92,000 to £108,000
Design and engineeringMarket guide: 3% to 15% of construction for the architect, plus engineer and surveys£14,000 to £81,000
Contingency5% to 10% of the works for what the walls hide£23,000 to £54,000
ConsentsPlanning (£548 council fee today) if needed, building control, party wall surveyorsSet by the council and per neighbour
Moving outRent and storage while the structural work runsYour own figure

Together, the first four lines come to about £588,000 to £783,000. Add VAT on the fees, the consents and any rent. An old house belongs at the top of the contingency range, because more is hidden.

Our guide to renovation mortgage and refurbishment loans explains the further advance, the retention and refurbishment bridging. Already own the house? See the wider picture in how much it costs to renovate a house in London.

Why the same renovation costs more in Kensington than in Surrey

The same house, renovated to the same standard, costs a different amount in different places. The Valuation Office Agency publishes BCIS location factors that show it. Each area gets a number against a national average of 100.

Construction price levels by area (Valuation Office Agency, Rating Cost Guide 2026) and our back-to-brick rate scaled by them. Illustration only: your figure follows the survey.
AreaFactor (vs Surrey)Back to brick, per m²
Kensington and Chelsea132 (+15%)£1,755 to £2,065
Westminster129 (+12%)£1,715 to £2,020
Wandsworth128 (+11%)£1,705 to £2,005
Lambeth126 (+10%)£1,675 to £1,975
Kingston upon Thames124 (+8%)£1,650 to £1,940
Merton123 (+7%)£1,635 to £1,925
Richmond upon Thames120 (+4%)£1,595 to £1,875
Every Surrey district115 (base)£1,530 to £1,800

The last column takes our back-to-brick rate as the Surrey level and scales it by each area's factor. It shows how the market moves, not a separate price list.

What drives the difference

  1. Labour and access. Inner London trades cost more to employ and to get to site. Narrow streets mean small deliveries, hand-carrying and more labour hours.
  2. Parking and road charges. Bay suspensions and permits cost money every day. The Congestion Charge rose to £18 a day on 2 January 2026, on top of ULEZ for older vans.
  3. Conservation areas and Article 4. Much of inner London sits in conservation areas. More work needs consent, often with matching materials and sash windows made to the old pattern.
  4. Terraces and party walls. A terrace shares two walls, so steels, chimneys and digging mean notices and surveyors on both sides.
  5. Specification. In prime central London, buyers expect stone, bespoke joinery and smart-home systems. The finish moves the price more than the postcode does.

A detached Surrey house avoids much of this: drive access, room for a skip and often no party wall at all. It brings its own questions, such as green belt rules for extensions and longer travel for trades.

We work across Kensington, Wandsworth, Clapham, Wimbledon, Richmond and Surrey. The team is the same wherever the house is.

Why design comes first, and how it saves money

The value of a house is created in the design. Where the kitchen goes, how the light reaches the hall, whether the loft becomes a bedroom: those choices make the house worth more. The builder then delivers what was drawn.

Tape measure laid across the worn edge of a timber table top
A measured survey: every design decision starts from exact dimensions

A design that is finished and agreed protects you in four ways:

  1. A real fixed price. A builder can only fix a price for what is drawn. Without drawings, every quote is a guess with a margin for risk.
  2. No delays on site. Trades wait for nobody when every decision is already made. Long-lead joinery and windows are ordered early.
  3. No budget creep. Most overruns come from decisions made on site. Each one becomes a variation, priced when you have no other builder to ask.
  4. No disappointment at handover. You see the rooms, finishes and lighting before work starts. What you get at the end is what you approved.

What goes wrong without design

On a house renovated without finished drawings, the same mistakes appear again and again. A radiator lands where the sofa needs to go, so the pipes are rerouted. Sockets end up behind the bed and are moved after plastering. The kitchen is re-ordered because the window is 10 cm narrower than assumed.

Each fix means cutting into new plaster, then making good and redecorating. Nothing like that happens when the electrician, plumber and joiner build from the same coordinated drawings.

How much to allow for design on the 300 m² house renovated back to brick (market guide, not our fee)
Design stage (RIBA)What you getShare of the architect's fee
Stages 0 to 3Measured survey, brief, concept, coordinated layout, planning drawingsAbout 35%
Stage 4Technical drawings, specification, building regulations, the fixed priceAbout 35%
Stages 5 to 6Site queries, inspections, handoverAbout 30%

On the market guide of 3% to 15% of construction, the design phase to Stage 4 is roughly 70% of the fee. For this house that is about £10,000 to £57,000, plus a structural engineer. Our guide to architect fees in the UK explains each fee model.

We saved a lot of money by having professional advice from the start.

That line is from a client couple who bought a house in Hampstead and renovated it with us. The full review sits further down this page.

The renovation process step by step, from survey to handover

A whole-house renovation runs in a fixed order. Each step makes the next one cheaper and more certain.

Interior under refurbishment, with bare plaster walls, ladders, tools and dust sheets
Strip-out shows what the walls have been hiding
The renovation journey for a period family house
StepWhat happensTiming
1. Survey of the houseA Level 3 survey for a large, older house; drains and asbestos where flaggedBefore you exchange
2. Brief and budgetWhat the family needs, what it can spend, with contingencyFirst meetings
3. Measured surveyExact drawings of the house as it standsBefore design starts
4. Design, RIBA Stages 2 to 4Concept, coordinated layout, technical drawings, specificationAgreed in the design programme
5. Planning or conservation consentOnly for extensions, roof or outside changes, or a listed house8-week statutory decision period
6. Party wall noticesShared walls and digging near neighbours2 months, or 1 month for digging
7. Fixed pricePriced line by line on the Stage 4 drawingsAfter Stage 4
8. ContractPrice, programme, payment stages and change control in writingBefore work starts
9. BuildStrip-out to finishes, inspected by building controlDate in the contract
10. HandoverSnagging, certificates, manuals and the defects periodAt completion

For the contract, the Joint Contracts Tribunal publishes building contracts for a home owner or occupier. One is for a homeowner with no consultant, another for one who has appointed one. Whatever form you use, it should fix the price, the dates, the payment stages and how changes are agreed.

The build, phase by phase

  1. Strip-out and opening up. Old finishes come off and hidden problems show. An asbestos survey comes first: HSE warns any home built or refurbished before 2000 may contain it.
  2. Structure. Steels for new openings, repairs to joists, chimneys and the roof, and any extension shell.
  3. First fix. New wiring, pipes, heating and ventilation run through open walls and floors.
  4. Plastering. Walls and ceilings are closed, and the house starts to look like rooms again.
  5. Second fix. Sockets, switches, radiators, sanitaryware, the kitchen and the joinery go in.
  6. Finishes and snagging. Floors, decoration and a room-by-room check before you move back in.

How long a 300 m² renovation takes

Herbert Crescent, a 450 m² house we refurbished in Knightsbridge, took 32 weeks on site. A 300 m² house that keeps its layout is usually quicker. Back to brick with an extension, it takes longer, and design and consents come before the build. We set your date after the survey and write it into the contract.

I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away. We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP. We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care. We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.

Lia Lavryk, Google reviewSee all reviews on Google

16 worries about renovating a period house, answered

Most families renovating their first period house share the same fears. Here are the honest answers, with what we do on our own projects.

Money and price

  1. Will the builder disappear with my deposit? A deposit should only cover materials ordered early for your house, such as windows or joinery. After that, pay in stages for work you have seen done on site. Check the company on Companies House: Craftex has been registered there since 2016, number 10210252.
  2. What if the price goes up halfway? Get a fixed price on finished drawings, with a clear list of what is excluded. Any change should be priced and signed in writing before it is built. That is how we work, and the contingency covers what the walls hide.
  3. Is it really that expensive? The cost follows the depth of work and the specification, not the postcode. Both are your choices, made at design stage. A full refurbishment that keeps the layout costs much less than a back-to-brick rebuild.
  4. How do I compare quotes? Give every builder the same drawings and specification, then compare line by line, not total by total. Watch for provisional sums and exclusions. Already have a quote? Send it to us. We'll beat it. Our guide on why builders' quotes vary shows what to look for.

Quality and safety

  1. How do I know the quality will be good? Agree the specification and see samples before work starts. Building control inspects the structure, fire safety and services and signs off at the end. At handover we give you the certificates, manuals and warranties in one file.
  2. What insurance should the builder have? Public liability for damage to your house and your neighbours', and employers' liability, which the law requires of any firm with staff. Professional indemnity matters if they design. We carry £10M of each.
  3. Have you done houses like ours? Our published homes are in central London: a 450 m² house at Herbert Crescent and a 400 sq m penthouse at Kensington Olympia. Outside London, we take on country houses and estate homes in the home counties, with the same directors. We do not show clients' homes without their consent.
  4. What if something goes wrong after we move in? The contract should name a defects period and who fixes what within it. The law already requires a trader to work with reasonable care and skill. We leave the aftercare dates in writing at handover.

Time and family life

  1. Do we need to move out? If the layout stays, often not: the work is phased floor by floor and the working area sealed. For a back-to-brick renovation with new services, most families move out for the structural stage. We tell you honestly at the first visit.
  2. How long will it really take? Longer than the build alone, because design and consents come first. The build date goes into the contract once the house is surveyed. Ask any builder for a written programme before you sign.
  3. Can we do it in phases? Yes, but design the whole house first. Run the services in one go, so a later phase never cuts open a finished room. Each extra phase repeats the set-up costs.
  4. Will it add value? A sound structure, new services and a layout that suits family life are what buyers pay for. Ask a local agent for sold prices of renovated houses on your street. Spend on what lasts, not on fashion.

Consents and management

  1. What about planning, neighbours and party walls? Internal work in an unlisted house rarely needs planning permission. Extensions, roof changes and outside changes in a conservation area usually do. Shared walls and digging near neighbours need party wall notices, two months or one month ahead.
  2. Do I need a project manager? Not with a design and build team: one contract and one director run the job. Our projects director runs delivery from design to handover. You get one name to call.
  3. Is design really needed? For a whole house, yes. Without drawings there is no fixed price, and the decisions get made on site at the highest cost. The design section above shows why.
  4. What if we fall out? A written contract with the price, dates and change procedure prevents most disputes. Raise problems early and in writing. Keep payments in line with work done, so neither side is ever far ahead.

How to choose a builder you can trust

The best protection is to choose well. A builder you can trust shows you their work, their paperwork and their price before you commit.

Newly renovated period townhouse kitchen with a marble-clad island, oak joinery with brass handles and a marble splashback
A finish you agreed on paper, delivered as drawn

Look for accreditations you can check. We hold ISO 9001, 14001 and 45001, CHAS, Constructionline Gold, SafeContractor, FMB and TrustMark. TrustMark is the Government Endorsed Quality Scheme for work in and around the home.

The ten checks below take a week, not a month. Use them on every builder you speak to, us included.

How we price and run a family house renovation

Send us the floor plan, the sales particulars and a few photos. We tell you which depth of work the house looks like and the range at our 2026 rates, the same working day.

Then we visit and check the structure, services and what planning will allow. Our design team draws the house to Stage 4, and the team that will build it prices the drawings. You get one fixed price, one contract and one director.

About 60% of our labour is in-house, and every project we have delivered has finished ahead of programme and on budget. We take on renovations from £100,000. Buying a period house now? Send us the floor plan and we'll price the works before you exchange.

How to choose a builder you can trust

  • Houses like yours, finished, with owners you can call
  • Company checked on Companies House: age, directors and filed accounts
  • Public liability, employers' liability and, if they design, professional indemnity certificates seen
  • Accreditations you can verify online, such as TrustMark, FMB or CHAS
  • A survey of the house before any price
  • Quotes compared on the same drawings and specification
  • A fixed price with exclusions and provisional sums listed
  • A written contract with dates, payment stages and change control
  • No large payment before work starts; stages paid for work done
  • Building control sign-off, certificates and a defects period at handover

Frequently asked questions

How much does it cost to renovate a Victorian house in the UK?

With Craftex, a full refurbishment that keeps the layout costs about £1,150 to £1,350 per m², and a back-to-brick renovation about £1,530 to £1,800 per m². These are our 2026 rates for construction only, before VAT and fees. Add 20% VAT, design and engineering fees and a contingency of 5% to 10%. Your fixed figure comes after a survey and the drawings.

How much does a full renovation of a four-bedroom house cost?

Measure the gross internal floor area and multiply by the rate for the depth of work. At 200 m², a full refurbishment at our 2026 rates is about £230,000 to £270,000; back to brick, about £306,000 to £360,000. VAT, fees and contingency come on top.

How long does it take to renovate a Victorian house?

Allow for design and consents before the build, then the works. Herbert Crescent, a 450 m² house we refurbished in Knightsbridge, took 32 weeks on site. A smaller house that keeps its layout is usually quicker; structural work, an extension or a basement take longer. The build date is set after the survey and written into the contract.

Can I live in the house while it is being renovated?

If the layout stays, often yes: the work is phased floor by floor and the working area is sealed. For a back-to-brick renovation with new services, most families move out for the structural stage. Plan the rent into the budget from the start.

Do I need planning permission to renovate a Victorian house?

Usually not for internal work in an unlisted house, such as removing an internal wall. You do need it for most extensions, roof changes and changes to the outside in a conservation area or under an Article 4 direction. A listed house needs listed building consent for internal works too. Building regulations approval is separate and covers wiring, plumbing, heating, windows and structure.

Should I hire an architect or a design and build company?

Both work. With an architect, you appoint the designer first, then tender the drawings to builders. With design and build, one team designs, prices and builds the house under one contract, so the people drawing it know what it costs. Either way, get the design finished before you ask for a fixed price.

How do I find a builder I can trust for a whole-house renovation?

Ask for houses like yours and speak to those owners. Check the company on Companies House, its insurance certificates and its trade accreditations. Compare quotes on the same drawings, insist on a written contract, and never pay a large sum before work starts. Pay in stages for work you have seen done.

Can I add renovation costs to my mortgage?

Sometimes. Options include a further advance from your lender, a mortgage with a retention released after the works, or a short-term refurbishment bridging loan repaid by a mortgage later. Every lender asks for the same thing: a costed schedule of works and a programme from the builder.

What should I renovate first in an old house?

Start with what keeps the house standing and dry: structure, roof, damp and drainage. Then the services hidden in the walls: wiring, plumbing and heating. Finishes come last, so nothing new is cut open later.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Send us the floor plan and we'll price the works before you exchange.

Floor plan, a few photos and what you want the house to become. A director comes back to you the same working day with the depth of work, the range at our 2026 rates and the next step.

WhatsApp us