For families renovating a period house
Victorian and Edwardian House Renovation: Costs, Process and Choosing a Builder
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 13 min read
The short answer
A Victorian or Edwardian house renovation costs about £1,150 to £1,800 per m² with Craftex, depending on how deep the work goes (our 2026 rates, construction only, ex VAT and fees). A 300 m² family house comes to roughly £344,000 to £540,000 before VAT, design fees and contingency.
- Layout kept, with new wiring, plumbing, heating, kitchen and bathrooms: £1,150 to £1,350 per m².
- Back to brick, with new openings and steels: £1,530 to £1,800 per m²; with an extension or loft, about £1,835 to £2,160.
- On top: 20% VAT, design and engineering fees, and a contingency of 5% to 10% of the works.
- Design comes first: a fixed price needs finished drawings, and a change after plastering is the most expensive kind.
A Victorian house renovation with Craftex costs £1,150 to £1,350 per m² when the layout stays. Back to brick, it is £1,530 to £1,800 per m². These are our 2026 rates for construction only, before VAT and fees.
For a 300 m² Edwardian family house in Surrey, that is about £344,000 to £405,000, or £459,000 to £540,000 back to brick. Structure, services, an extension and the kitchen and bathroom specification push it up. Keeping the layout and good original features bring it down.
This guide is for families taking on their first period house, often with a mortgage, to live in for decades. It shows the full budget, why design comes first, the process step by step and plain answers to the worries we hear most.
We are a design and build team for house renovation in London and the home counties. Buying now? Send us the floor plan and we'll price the works before you exchange.
What a Victorian house renovation costs per m²
Builders price a renovation by floor area and by how deep the work goes. The price of the house does not set the cost of the works. Measure the gross internal area, inside the outside walls on every floor, then pick the depth of work.
Our example is a large detached Edwardian family house in Surrey: 300 m² (about 3,200 sq ft) over three floors. Surrey's average house is about 125 m² on EPC data from January 2026, so this is a big home, well over twice the average.
| Depth of work | What it covers | Per m² | 300 m² house |
|---|---|---|---|
| Light refresh | Decoration, flooring, a kitchen or bathroom, services kept | Below £1,150, priced room by room | Under £344,000 |
| Full refurbishment | Layout kept: rewire, replumb, new heating, kitchen, bathrooms, joinery | £1,150 to £1,350 | £344,000 to £405,000 |
| Structural renovation | Back to brick: new openings and steels, all-new services | £1,530 to £1,800 | £459,000 to £540,000 |
| Remodel and extend | Back to brick plus an extension or loft room | £1,835 to £2,160 | £551,000 to £648,000 |
With 20% VAT, the full refurbishment comes to about £413,000 to £486,000. The back-to-brick renovation comes to about £551,000 to £648,000. Fees and contingency sit on top, as the next section shows.
A family planning to stay 30 years or more usually lands in the middle two rows. Old wiring, lead or iron pipes and tired heating are hidden in the walls. Replacing them once, before the finishes go in, is far cheaper than opening the house again later.
Planning a bigger house or a basement? Our guides to house extension cost in London and loft conversion cost in London price the new floor area.
The full budget for a 300 m² family house, with VAT and fees
The build is the biggest line, but not the only one. A mortgage buyer needs every line before exchange, because the deposit, the loan and the works all come from the same pot.
| Line | What it is | Allow |
|---|---|---|
| Works | Construction at our 2026 rates | £459,000 to £540,000 |
| VAT | 20% on the works | £92,000 to £108,000 |
| Design and engineering | Market guide: 3% to 15% of construction for the architect, plus engineer and surveys | £14,000 to £81,000 |
| Contingency | 5% to 10% of the works for what the walls hide | £23,000 to £54,000 |
| Consents | Planning (£548 council fee today) if needed, building control, party wall surveyors | Set by the council and per neighbour |
| Moving out | Rent and storage while the structural work runs | Your own figure |
Together, the first four lines come to about £588,000 to £783,000. Add VAT on the fees, the consents and any rent. An old house belongs at the top of the contingency range, because more is hidden.
Our guide to renovation mortgage and refurbishment loans explains the further advance, the retention and refurbishment bridging. Already own the house? See the wider picture in how much it costs to renovate a house in London.
Why the same renovation costs more in Kensington than in Surrey
The same house, renovated to the same standard, costs a different amount in different places. The Valuation Office Agency publishes BCIS location factors that show it. Each area gets a number against a national average of 100.
| Area | Factor (vs Surrey) | Back to brick, per m² |
|---|---|---|
| Kensington and Chelsea | 132 (+15%) | £1,755 to £2,065 |
| Westminster | 129 (+12%) | £1,715 to £2,020 |
| Wandsworth | 128 (+11%) | £1,705 to £2,005 |
| Lambeth | 126 (+10%) | £1,675 to £1,975 |
| Kingston upon Thames | 124 (+8%) | £1,650 to £1,940 |
| Merton | 123 (+7%) | £1,635 to £1,925 |
| Richmond upon Thames | 120 (+4%) | £1,595 to £1,875 |
| Every Surrey district | 115 (base) | £1,530 to £1,800 |
The last column takes our back-to-brick rate as the Surrey level and scales it by each area's factor. It shows how the market moves, not a separate price list.
What drives the difference
- Labour and access. Inner London trades cost more to employ and to get to site. Narrow streets mean small deliveries, hand-carrying and more labour hours.
- Parking and road charges. Bay suspensions and permits cost money every day. The Congestion Charge rose to £18 a day on 2 January 2026, on top of ULEZ for older vans.
- Conservation areas and Article 4. Much of inner London sits in conservation areas. More work needs consent, often with matching materials and sash windows made to the old pattern.
- Terraces and party walls. A terrace shares two walls, so steels, chimneys and digging mean notices and surveyors on both sides.
- Specification. In prime central London, buyers expect stone, bespoke joinery and smart-home systems. The finish moves the price more than the postcode does.
A detached Surrey house avoids much of this: drive access, room for a skip and often no party wall at all. It brings its own questions, such as green belt rules for extensions and longer travel for trades.
We work across Kensington, Wandsworth, Clapham, Wimbledon, Richmond and Surrey. The team is the same wherever the house is.
Why design comes first, and how it saves money
The value of a house is created in the design. Where the kitchen goes, how the light reaches the hall, whether the loft becomes a bedroom: those choices make the house worth more. The builder then delivers what was drawn.
A design that is finished and agreed protects you in four ways:
- A real fixed price. A builder can only fix a price for what is drawn. Without drawings, every quote is a guess with a margin for risk.
- No delays on site. Trades wait for nobody when every decision is already made. Long-lead joinery and windows are ordered early.
- No budget creep. Most overruns come from decisions made on site. Each one becomes a variation, priced when you have no other builder to ask.
- No disappointment at handover. You see the rooms, finishes and lighting before work starts. What you get at the end is what you approved.
What goes wrong without design
On a house renovated without finished drawings, the same mistakes appear again and again. A radiator lands where the sofa needs to go, so the pipes are rerouted. Sockets end up behind the bed and are moved after plastering. The kitchen is re-ordered because the window is 10 cm narrower than assumed.
Each fix means cutting into new plaster, then making good and redecorating. Nothing like that happens when the electrician, plumber and joiner build from the same coordinated drawings.
| Design stage (RIBA) | What you get | Share of the architect's fee |
|---|---|---|
| Stages 0 to 3 | Measured survey, brief, concept, coordinated layout, planning drawings | About 35% |
| Stage 4 | Technical drawings, specification, building regulations, the fixed price | About 35% |
| Stages 5 to 6 | Site queries, inspections, handover | About 30% |
On the market guide of 3% to 15% of construction, the design phase to Stage 4 is roughly 70% of the fee. For this house that is about £10,000 to £57,000, plus a structural engineer. Our guide to architect fees in the UK explains each fee model.
We saved a lot of money by having professional advice from the start.
That line is from a client couple who bought a house in Hampstead and renovated it with us. The full review sits further down this page.
The renovation process step by step, from survey to handover
A whole-house renovation runs in a fixed order. Each step makes the next one cheaper and more certain.
| Step | What happens | Timing |
|---|---|---|
| 1. Survey of the house | A Level 3 survey for a large, older house; drains and asbestos where flagged | Before you exchange |
| 2. Brief and budget | What the family needs, what it can spend, with contingency | First meetings |
| 3. Measured survey | Exact drawings of the house as it stands | Before design starts |
| 4. Design, RIBA Stages 2 to 4 | Concept, coordinated layout, technical drawings, specification | Agreed in the design programme |
| 5. Planning or conservation consent | Only for extensions, roof or outside changes, or a listed house | 8-week statutory decision period |
| 6. Party wall notices | Shared walls and digging near neighbours | 2 months, or 1 month for digging |
| 7. Fixed price | Priced line by line on the Stage 4 drawings | After Stage 4 |
| 8. Contract | Price, programme, payment stages and change control in writing | Before work starts |
| 9. Build | Strip-out to finishes, inspected by building control | Date in the contract |
| 10. Handover | Snagging, certificates, manuals and the defects period | At completion |
For the contract, the Joint Contracts Tribunal publishes building contracts for a home owner or occupier. One is for a homeowner with no consultant, another for one who has appointed one. Whatever form you use, it should fix the price, the dates, the payment stages and how changes are agreed.
The build, phase by phase
- Strip-out and opening up. Old finishes come off and hidden problems show. An asbestos survey comes first: HSE warns any home built or refurbished before 2000 may contain it.
- Structure. Steels for new openings, repairs to joists, chimneys and the roof, and any extension shell.
- First fix. New wiring, pipes, heating and ventilation run through open walls and floors.
- Plastering. Walls and ceilings are closed, and the house starts to look like rooms again.
- Second fix. Sockets, switches, radiators, sanitaryware, the kitchen and the joinery go in.
- Finishes and snagging. Floors, decoration and a room-by-room check before you move back in.
How long a 300 m² renovation takes
Herbert Crescent, a 450 m² house we refurbished in Knightsbridge, took 32 weeks on site. A 300 m² house that keeps its layout is usually quicker. Back to brick with an extension, it takes longer, and design and consents come before the build. We set your date after the survey and write it into the contract.
I and my husband are very satisfied with Craftex's service and customer support. We bought a house in Hampstead and wanted to redesign and renovate it. On our initial free consultation with Sviat, we found out that we actually can do loft conversion and rear extension and add value to the property straight away. We worked with the Craftex design team to bring our vision to life and deliver planning approvals. At that time guys started stripping out to save time on the construction programme as we wanted to move in ASAP. We worked with very experienced project director Konstantin who was responsible for all aspects of project delivery from design to construction with a very good eye on details and customer care. We saved a lot of money by having professional advice from the start. Project management and quality at Craftex are at the highest level. Many thanks to Craftex Team.
16 worries about renovating a period house, answered
Most families renovating their first period house share the same fears. Here are the honest answers, with what we do on our own projects.
Money and price
- Will the builder disappear with my deposit? A deposit should only cover materials ordered early for your house, such as windows or joinery. After that, pay in stages for work you have seen done on site. Check the company on Companies House: Craftex has been registered there since 2016, number 10210252.
- What if the price goes up halfway? Get a fixed price on finished drawings, with a clear list of what is excluded. Any change should be priced and signed in writing before it is built. That is how we work, and the contingency covers what the walls hide.
- Is it really that expensive? The cost follows the depth of work and the specification, not the postcode. Both are your choices, made at design stage. A full refurbishment that keeps the layout costs much less than a back-to-brick rebuild.
- How do I compare quotes? Give every builder the same drawings and specification, then compare line by line, not total by total. Watch for provisional sums and exclusions. Already have a quote? Send it to us. We'll beat it. Our guide on why builders' quotes vary shows what to look for.
Quality and safety
- How do I know the quality will be good? Agree the specification and see samples before work starts. Building control inspects the structure, fire safety and services and signs off at the end. At handover we give you the certificates, manuals and warranties in one file.
- What insurance should the builder have? Public liability for damage to your house and your neighbours', and employers' liability, which the law requires of any firm with staff. Professional indemnity matters if they design. We carry £10M of each.
- Have you done houses like ours? Our published homes are in central London: a 450 m² house at Herbert Crescent and a 400 sq m penthouse at Kensington Olympia. Outside London, we take on country houses and estate homes in the home counties, with the same directors. We do not show clients' homes without their consent.
- What if something goes wrong after we move in? The contract should name a defects period and who fixes what within it. The law already requires a trader to work with reasonable care and skill. We leave the aftercare dates in writing at handover.
Time and family life
- Do we need to move out? If the layout stays, often not: the work is phased floor by floor and the working area sealed. For a back-to-brick renovation with new services, most families move out for the structural stage. We tell you honestly at the first visit.
- How long will it really take? Longer than the build alone, because design and consents come first. The build date goes into the contract once the house is surveyed. Ask any builder for a written programme before you sign.
- Can we do it in phases? Yes, but design the whole house first. Run the services in one go, so a later phase never cuts open a finished room. Each extra phase repeats the set-up costs.
- Will it add value? A sound structure, new services and a layout that suits family life are what buyers pay for. Ask a local agent for sold prices of renovated houses on your street. Spend on what lasts, not on fashion.
Consents and management
- What about planning, neighbours and party walls? Internal work in an unlisted house rarely needs planning permission. Extensions, roof changes and outside changes in a conservation area usually do. Shared walls and digging near neighbours need party wall notices, two months or one month ahead.
- Do I need a project manager? Not with a design and build team: one contract and one director run the job. Our projects director runs delivery from design to handover. You get one name to call.
- Is design really needed? For a whole house, yes. Without drawings there is no fixed price, and the decisions get made on site at the highest cost. The design section above shows why.
- What if we fall out? A written contract with the price, dates and change procedure prevents most disputes. Raise problems early and in writing. Keep payments in line with work done, so neither side is ever far ahead.
How to choose a builder you can trust
The best protection is to choose well. A builder you can trust shows you their work, their paperwork and their price before you commit.
Look for accreditations you can check. We hold ISO 9001, 14001 and 45001, CHAS, Constructionline Gold, SafeContractor, FMB and TrustMark. TrustMark is the Government Endorsed Quality Scheme for work in and around the home.
The ten checks below take a week, not a month. Use them on every builder you speak to, us included.
How we price and run a family house renovation
Send us the floor plan, the sales particulars and a few photos. We tell you which depth of work the house looks like and the range at our 2026 rates, the same working day.
Then we visit and check the structure, services and what planning will allow. Our design team draws the house to Stage 4, and the team that will build it prices the drawings. You get one fixed price, one contract and one director.
About 60% of our labour is in-house, and every project we have delivered has finished ahead of programme and on budget. We take on renovations from £100,000. Buying a period house now? Send us the floor plan and we'll price the works before you exchange.
How to choose a builder you can trust
- Houses like yours, finished, with owners you can call
- Company checked on Companies House: age, directors and filed accounts
- Public liability, employers' liability and, if they design, professional indemnity certificates seen
- Accreditations you can verify online, such as TrustMark, FMB or CHAS
- A survey of the house before any price
- Quotes compared on the same drawings and specification
- A fixed price with exclusions and provisional sums listed
- A written contract with dates, payment stages and change control
- No large payment before work starts; stages paid for work done
- Building control sign-off, certificates and a defects period at handover