Best Shopfitters in London: How to Choose (2026)

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read

Luxury menswear boutique with timber-panelled walls, lit display shelves of shoes and leather armchairs

The short answer

The best shopfitters for a London store have already solved your hard part: trading during works, landlord approvals, shopfront consent and joinery lead times. Compare them on finished stores of your size, not on photos.

  1. Ask each firm how its last two stores kept trading during the works.
  2. Check who makes the joinery, and how long it takes to make.
  3. Agree who prepares the landlord's pack and the shopfront and sign consents.
  4. Visit a finished store and call the owner before you sign.

A beautiful store is the easy part of a shop fit out. What delays London openings is the trading plan, the landlord, the shopfront consent and the joinery. So when you compare shopfitters in London, look past the photos.

This guide is written by a London team that designs and builds stores. Our retail fit out and shopfitting service covers the whole job, and below we also say when another kind of firm will suit you better. Got a unit in mind? Book a site visit before you sign the lease.

What decides which shopfitters you need

Every shopfitting team shows beautiful finished stores. Fewer can show how they handled the four things below. Use them as your interview.

1. Trading while the work goes on

Most brands cannot close a store for weeks. The work has to be split into areas, with noisy jobs at night and a clean, safe shop floor every morning. Ask each firm how its last two stores stayed open.

2. The joinery and its lead time

Counters, shelving, rails and display units are often the longest item to make. Ask who designs them, who makes them and how long making takes. A firm that buys in all its joinery depends on someone else's diary.

3. The landlord, the shopfront and the signs

In a leased unit the landlord will want drawings and a licence for alterations before work starts. A new shopfront usually needs planning permission. An illuminated sign may need advertisement consent. Our guide to retail fit-out in London: consents and process sets out the steps.

4. The budget and what is left out

Ask every firm the same question: what is not in your price? For a guide to our own 2026 rates, read our shop fit-out cost guide. A full fit-out with us usually starts from about £802 per m², ex VAT.

The main types of shopfitters compared

Shop fitting companies in London come in five main types. These are typical patterns, not judgements on any one firm. Every type has strong and weak firms in it.

Types of shopfitters and retail fit out contractors compared
Type of firmBest forWatch out forWho holds the contract
Joinery-led shopfittersCounters, shelving and display units made in their own workshopBuilding work, services and consents left to othersOften you, with a separate builder
Design-and-build fit-out teams (Craftex)One store designed and built by one team, from survey to openingNot set up for 50-store roll-outsThe fit-out team, for the whole job
Main contractors for retail constructionNew units, structural work and shell-and-coreSmaller fit-outs may not be their focusThe main contractor
Roll-out specialistsThe same store format across many townsOne-off flagship detailsThe roll-out firm
Retail design studiosConcept, brand and the look of the storeThe build is tendered to others laterYou, with the builder chosen at tender

When you compare retail fit out contractors or retail construction companies, ask who holds the contract for the whole job. If nobody does, the gaps between firms become your problem.

Seven checks before you sign

Use these seven checks on every shortlist. They take an afternoon and can save weeks.

  1. Finished stores of your size. Ask for two London stores like yours and visit one.
  2. A call with a past client. Ask what went wrong, and how the firm put it right.
  3. Who makes the joinery. Name the workshop and the lead time in writing.
  4. The programme. It should show the landlord's approval, consents and long-lead items.
  5. Trading plan. If you stay open, ask for the phasing in writing.
  6. Exclusions. Every item not in the price should be listed.
  7. Insurance and accreditations. Ask for the certificates, not just the logos.

Want a second view on firms you are already talking to? See commercial fit-out contractors compared, or book a site visit and we will walk the unit with you.

Where Craftex fits and where it does not

We are a London design-and-build team for whole stores. We design the space, make the joinery, run the services and handle the landlord and the consents, under one contract.

We are a good fit for flagship and boutique stores, brand refits and stores that must keep trading. We take on construction projects from £100,000 to £10M and more. Around 60% of our labour on site is our own, and every job carries £10M of insurance cover.

Where Craftex is not the right fit

  1. Kiosks and pop-ups. A short-term unit is better value with a specialist in temporary stands.
  2. Low-budget refreshes. New paint and a few shelves suit a local builder.
  3. Supply-only shop fittings. If you only need racks or shelving delivered, go to a fittings supplier.
  4. Large national roll-outs. Opening the same format in 30 towns suits a roll-out specialist with regional teams.

For the look and the layout before you choose a builder, read our guide to retail design.

Store projects that stayed open

Two of our retail-facing projects show what a good shopfitter protects: the trading days and the finish.

Timber shoe wall and knitwear shelving made for the Drake's shop on Savile Row
Drake's, Savile Row: bespoke joinery designed, made and installed by Craftex.
8 weeksDrake's, Savile Row: on site, after 4 weeks of design
120 sq mDrake's flagship, open throughout
17 weeksMedusa, Knightsbridge: four levels
2Drake's projects delivered

Drake's, Savile Row: a flagship refit while the shop kept trading

The Drake's Savile Row flagship is a 120 sq m shop. We designed it in 4 weeks and built it in 8 weeks on site, for £410K. The shop stayed open throughout. We fitted a new shopfront, commercial-grade lighting and bespoke joinery that we designed, made and installed, including a 5 m clothing rail.

Medusa, Knightsbridge: four levels designed and built in 17 weeks

Medusa is a salon and spa on Beauchamp Place: 180 sq m over four levels, built for £460K in 17 weeks from concept to handover. We also handled the planning applications for the signs and the outside ventilation units. A store on a busy street needs the same care with its shopfront and signs.

Highly recommended! Craftex are the kind of fit-out contractors in London you can truly trust. From the very first meeting, they understood our vision and gave practical ideas to make the most of our space. They turned our old storage area into a clean, efficient, and well-organized warehouse. The team was professional, easy to work with, and clearly took pride in their work.

Monika Kamionka, Google reviewSee all reviews on Google

The team behind a store fit out

Earlier projects named here are from each person's career before Craftex.

  1. Joe Crawford, Operations Director. 37 years in construction, on projects from £100K to £135M, including the fit-out of Dior's flagship on Bond Street.
  2. Konstantin Jegorovs, Projects Director. 16 years in retail and commercial work.

The same directors run your job from the first visit to the last snag, so the people who priced it are the people you call.

Questions to ask every shopfitter

Take these to each meeting. A firm that answers them clearly, in writing, deserves a place on your shortlist.

Our retail fit-out and shopfitting team is happy to answer every one of these. If you are comparing shopfitters now, book a site visit and put the questions to us.

Ten questions to ask every shopfitter

  • Which two London stores like ours can we visit, and can we call the owners?
  • How did those stores keep trading during the works?
  • Who designs and who makes the joinery, and how many weeks does making take?
  • Who prepares the landlord's pack and the licence for alterations?
  • Does the shopfront or the sign need planning or advertisement consent here?
  • What does your programme assume for each approval?
  • What share of the site labour is your own?
  • What is excluded from your price?
  • What insurance and accreditations do you hold, and can we see the certificates?
  • Who do we call if something fails in the first month of trading?

Frequently asked questions

How do I choose shopfitters in London?

Shortlist firms that have finished stores of your size and type in London. Ask how their last two jobs kept trading, who made the joinery and who handled the landlord. Visit a finished store and call the owner.

What is the difference between shopfitting and a retail fit out?

Shopfitting is the fixtures: counters, shelving, rails and displays. A retail fit out is the whole store: walls, ceilings, floors, lighting, power, the shopfront and the fixtures, under one programme.

Can a shop stay open during a refit?

Yes, with careful phasing. Drake's on Savile Row stayed open throughout its refit: noisy work went out of hours and each area was finished before the next was opened up.

How long does a shop fit out take?

It depends on the size and the scope. Drake's 120 sq m flagship took 4 weeks of design and 8 weeks on site. Your programme is set after a survey of your unit.

Do I need consent for a new shopfront or sign?

Often, yes. A new shopfront usually needs planning permission, and an illuminated sign or a large advert may need advertisement consent. Your landlord's consent is needed as well.

What size of retail project does Craftex take on?

We take on construction projects from £100,000 to £10M and more. We don't take on kiosks, pop-ups or low-budget refreshes.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Got a store to fit out, and a date to open?

We survey the unit, check the consents and the joinery lead times, and give you a programme and a price before you commit. Book a site visit.