Ransom Strips: How They Stop a Site
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 4 min read
The short answer
A ransom strip is a piece of land, often very narrow, that someone else owns between your site and the road. Without a right to cross it, the site cannot be developed, so its owner can ask for a payment.
- Planning permission does not give you a right to cross land you do not own.
- You find a ransom strip by comparing title plans with the council's list of public roads.
- It is solved by a deal, another way in, or in some cases compulsory purchase.
- There is no fixed price. The Valuation Office Agency lists tribunal awards from 15% to 50% of the uplift in value.
A ransom strip is a piece of land that sits between a site and the road and belongs to someone else. It can be a metre wide and still stop a whole scheme. This guide is for landowners and developers in England who have found one, or fear they have.
Craftex is a London-based property development and construction company. We buy and develop sites across England. Land with no clear way in is one kind of problem site we look at. Got one? Send us your site.
What a ransom strip is
To build on land, you need a legal right to get from it to a public road. If someone else owns the ground in between, you need their agreement. That ground is the ransom strip.
Ransom strips come about in a few ways:
- Kept back on purpose. A seller sells a field but keeps a thin strip along the road.
- Left over. A verge or old track never passed with the rest of the land.
- A gap in the road. The public road stops short of your boundary.
Land with no way in at all is called landlocked land. The problem is the same, only bigger.
How to find a ransom strip
Do not wait for a buyer's solicitor to find it. You can check now, in three steps.
- Get the title plans. HM Land Registry sells the title plan and title register for your land and for the land next to it.
- Find the edge of the public road. Every council keeps a list of the streets it maintains. You can inspect it free of charge.
- Compare the two. Look for any ground between your boundary and the public road that is in another name, or in no name at all.
Title plans show general boundaries, not exact lines. If the plans leave doubt, ask a solicitor or a land surveyor to check on the ground.
Also read the title register for rights of way. A right written there may already give you the access you need.
How access problems are solved
There are four usual answers. Which one fits depends on who owns the strip and what else is possible.
| Way | How it works | Good to know |
|---|---|---|
| Do a deal | Buy the strip, or buy a right of way across it | The price is negotiated between the two owners |
| Find another way in | Bring the access from a different road or boundary | A real second option makes your position stronger |
| Compulsory purchase | In some cases the council can be asked to acquire the strip | Not simple. Objections can be raised and compensation is still paid. |
| Insurance | Where the owner cannot be traced, cover may be available | Unlikely where the owner is known |
The compulsory purchase and insurance points come from a RICS Land Journal article on ransom strips. Your solicitor can tell you if either applies to you.
How a ransom strip is valued
A ransom strip is not valued by its size. It is valued by what it unlocks. The usual measure is a share of the uplift: the increase in the site's value once access is granted.
Many people quote one third. That figure comes from a 1961 tribunal case, Stokes v Cambridge Corporation. The Valuation Office Agency says the case was decided on its own facts, and that treating one third as a rule is a misconception.
| Point | What it says |
|---|---|
| Starting point | The two sides share the increase in value equally |
| Stokes v Cambridge (1961) | One third, on its own facts |
| Awards where no other access existed | 50% of the uplift |
| Awards where another access was possible | 15%, 30% and 45% of the uplift in three listed cases |
| What decides it in the end | The bargaining power of each side |
These are a government valuation manual's notes on tribunal cases. They are not our terms, and they are not a quote for your land. We do not publish a price.
The lesson for an owner is simple. The more real choices you have for access, the less the strip is worth.
I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.
Selling a site with an access problem
You can sell a site with a ransom strip. Be open about it. A buyer's solicitor will find it, and a late surprise can end a sale.
A buyer who develops sites will look at three things: the planning prospects, the cost of solving the access, and how long it will take. We do that work ourselves.
We work with owners in three ways:
- We buy it. We buy the site as it is and take on the access problem.
- We go into a joint venture with you. You put in the land, and we solve the access and share the result.
- We do it for you. We handle planning, building and sales, and you keep the land.
We take on schemes from about £3M GDV. GDV means the total sale value of the finished homes. We typically take on schemes of £3M to £150M GDV, and larger schemes are welcome.
What to do next
Get the title plans and check the public road before you spend money on design. If there is a gap, find out who owns it.
Then see the three routes on our sell your land page, or read how to sell land to a developer. Ready now? Send us your site. We reply within one hour, Monday to Saturday, 8am to 6pm.
This guide is general information, not legal advice. Ask your solicitor about your own land.
What to send us about a site with an access problem
- The address or postcode and the title number
- The title plan, with the strip or gap marked if you know where it is
- Who owns the strip, if you know
- Any planning history on the site
- Any talks you have already had with the owner of the strip