How to Brief a Contractor for a Commercial Project (With a One-Page Template)
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
A good contractor brief says what the project is for, what must be built, where, by when, for roughly how much, and what could get in the way.
- Cover ten things: objective, scope, site, budget, programme, quality, constraints, route, decision-makers, comparison.
- Send the drawings, asbestos survey, lease and services information with it.
- State your budget, so the contractor can tell you early if the scope fits.
- As a commercial client you have legal duties under CDM 2015 from day one.
A good contractor brief tells the contractor five things. What the project is for, what must be built, where, by when and for roughly how much. It also says what could get in the way.
The brief is the cheapest point in a project to get things right. Every gap becomes an assumption in the price. Every assumption becomes a risk allowance you pay for, or an extra you argue about later. Have a project to brief? Book a site visit and we will go through it with you on site.
Three contractors given a vague brief will price three different projects. This guide is written by a contractor. It explains what we need to price a commercial project properly, what the law asks of you, and how to fit it on one page.
How to brief a contractor: the 10 parts of a good brief
A good brief covers ten things. The first seven describe the project. The last three describe how you will buy it.
1. The objective
Say why the project exists, in one or two sentences. "Re-let floors three to five to one occupier by September" leads to different choices from "a showcase head office". The objective tells the contractor what wins when two things compete.
2. The scope
Say what is in and what is out. Strip-out, structure, mechanical and electrical services, finishes, furniture, IT and AV, signage, external works. If you do not know yet, say so and ask for a proposal. A list of exclusions is as useful as a list of inclusions.
3. The site
Give the address, the floor area, the floors involved and whatever information you hold.
- Existing drawings and any measured survey.
- The asbestos survey. Refurbishment needs a refurbishment and demolition survey first in buildings that may contain asbestos.
- The health and safety file from earlier works, if there is one.
- Services information: age, condition and capacity of power, heating and cooling.
- The lease and any landlord's fit-out guide or rules.
4. The budget
Contractors price better when they know the budget. It is not a ceiling to fill. A stated budget lets a contractor tell you early if the scope does not fit, and where to save. Say whether it includes fees, furniture, IT and VAT.
5. The programme
Give the date you need the space, and why. A lease end, an opening date or a funding deadline. Add any fixed points, such as landlord approvals or board meetings.
At Beaumont House in High Street Kensington, the client had five weeks before its lease expired. More than 150 staff had to move. The lease date fixed the programme, and we delivered the 750 sq m refurbishment in three weeks.
6. Quality and specification
How good does it need to be? Share reference projects, photos of finishes you like, a brand guide or a landlord's specification. For offices, say whether you need Category A, Category B or both. Our guide to Cat A, Cat A+ and Cat B fit-out explains the difference.
Our office fit out London team starts every office brief with that question.
7. Constraints
List the things that shape how the work is done.
- Will the building be occupied during the works, and by whom?
- Working hours, noise limits and access restrictions.
- Deliveries, loading bays and lifts.
- Neighbours, party walls and other tenants.
- Planning, listed building or conservation area consents.
- The landlord's licence for alterations.
8. The procurement route
Do you want the contractor to design and build, or to build to your designer's drawings? Design and build gives one party responsibility for both, usually at a fixed price. A traditional route gives you more control of the design, but the design risk stays with you.
Say which you prefer, or ask for a recommendation. See design and build and turnkey contracting.
9. Decision-makers
Who approves the design, the price and changes? Who signs the contract? A contractor needs one person on your side with authority to decide, and to know who else must be consulted.
10. How you will compare prices
Tell contractors what you will judge them on: price, programme, approach, team and track record. Ask them to price the same scope and list their exclusions and assumptions. Then the comparison is fair, and the lowest price is easier to understand.
Your legal duties as a commercial client
Commissioning construction work makes you a client under the Construction (Design and Management) Regulations 2015. The duties apply to commercial clients whatever the size of the project. In summary, you must:
- Make suitable arrangements for managing the project, with enough time and resources.
- Provide pre-construction information to designers and contractors. That is what you know, or could reasonably find out, about hazards such as asbestos, services and structure.
- Appoint a principal designer and principal contractor in writing where more than one contractor will work on the project.
- Make sure a construction phase plan exists before work starts, and that welfare facilities are provided.
- Notify HSE if the work will last longer than 30 working days with more than 20 workers at any one time, or exceed 500 person-days.
The Building Regulations add similar duties for building work. Since October 2023, clients, designers and contractors must plan, manage and monitor work so it complies. The same firm often fills both the CDM and the Building Regulations roles.
A design and build contractor can take on the principal designer and principal contractor roles. Your own duties as client stay with you.
Documents to send with the brief
Send these with the brief. If you do not have something, say so. A contractor can arrange surveys, but needs to know they are missing to plan and price them.
| Document | Why the contractor needs it |
|---|---|
| Floor plans and any measured survey | To measure and price the work |
| Asbestos survey | Required before refurbishment; affects programme and cost |
| Lease and landlord's fit-out guide | Sets what you may do and how |
| Building services information | Decides whether services can be reused |
| Photos of the space | Speeds up the first assessment |
| Planning history, if relevant | Shows what is consented and what is not |
| Any design work done so far | Avoids paying twice for the same work |
A one-page brief template
Copy this list into a document and fill in one or two lines for each item.
Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.
Mistakes we see most often in commercial briefs
These six mistakes cost clients the most time and money.
- No budget. Everyone's time is wasted when scope and budget do not match.
- A date with no reason. If the deadline is fixed, say why. If it is not, say that too.
- Design and build without a brief. A contractor can only design what it has been told.
- No asbestos survey. On refurbishments it often decides the programme.
- Comparing totals only. The lowest price usually has the longest list of exclusions. Read them.
- Changing the brief after pricing. Every change after prices are in costs time on both sides.
For the next steps, see our guides on how to choose a commercial contractor and construction project planning.
Brief us on your commercial project
We take on commercial projects from £100,000 through our commercial fit-out and refurbishment team. That includes offices, warehouses, hospitality and refurbishment, in London and across the UK.
Bring your brief, even a rough one. Book a site visit and we will go through it with you in the space itself.
One-page contractor brief
- Project: address, floors and approximate area.
- Objective: one or two sentences on why the project exists.
- Scope: what is included and what is excluded.
- Site information: drawings, asbestos survey, services information, lease.
- Budget: the figure, and whether it includes fees, furniture, IT and VAT.
- Programme: the date you need the space, and why.
- Quality: Cat A, Cat B or both; reference projects or brand guide.
- Constraints: occupied building, working hours, access, consents, landlord's licence.
- Procurement: design and build, traditional, or contractor to recommend.
- Decision-maker: name and role, and who else must be consulted.
- Comparison: price, programme, approach, team and track record.