For clients, developers and building owners in England
Principal Designer: Duties Under CDM and Building Regulations
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 6 min read
The short answer
A principal designer is the designer a client appoints in writing to take control of the design work on a building project. In England there are two such roles: one for health and safety under CDM 2015, and one for the Building Regulations.
- CDM 2015 role: plans and coordinates health and safety before work starts on site.
- Building Regulations role: coordinates the design so that, if built, it meets the regulations.
- The client appoints both in writing when more than one contractor will work on the project.
- One designer can hold both roles if the client confirms it in writing.
A principal designer is the designer who takes control of the design work on a building project. The client appoints them in writing. In England the name covers two legal roles, and many clients only know one of them.
This guide sets the two roles side by side for a client with a real project. Craftex has architects who coordinate the design team and builders under one contract. Planning a project? Discuss your project with us.
What a principal designer does
A building is drawn by several designers: an architect, a structural engineer, a services engineer and specialists. A principal designer leads them on two things the law cares about.
- Safety of the work. Under CDM 2015 they plan, manage and monitor health and safety before construction starts.
- Compliance of the building. Under the Building Regulations they coordinate the design so the finished work would meet the regulations.
They do not replace the other designers. Each designer still answers for their own drawings. The principal designer makes sure the parts fit together and that nobody leaves a gap.
GOV.UK guidance on the Building Regulations role is direct. It says the principal designer should be "part of the design team and not a third party without any influence over design decisions".
CDM principal designer vs Building Regulations principal designer
The two roles share a name. They come from different laws and protect different things.
| Point | CDM 2015 principal designer | Building Regulations principal designer |
|---|---|---|
| Law | Construction (Design and Management) Regulations 2015 | Building Regulations 2010, Part 2A, in force from 1 October 2023 |
| Where | Great Britain | England |
| Protects | Health and safety of people who build, use and maintain the building | Compliance of the design with the Building Regulations |
| Main duty | Plan, manage and monitor the pre-construction phase | Plan, manage and monitor the design work |
| Key paper | The health and safety file, a record for future work on the building | A document for the client within 28 days of the end of the appointment |
The CDM role comes first in time. Our guide to the CDM Regulations 2015 explains all five duty holders.
The Building Regulations role is newer. The rules that added it were made using powers from the Building Safety Act 2022. It applies to building work in England in general, with extra rules for higher-risk buildings.
The duties in plain words
Under CDM 2015 the principal designer must find the risks that can be foreseen. They must remove them, or control them, as far as is reasonably practicable. They help the client collect pre-construction information. That is what is known about the site and the building before work starts.
Under the Building Regulations the principal designer must take all reasonable steps to make the designers cooperate. They must also keep in touch with the principal contractor, the builder in control of the site.
Who appoints the principal designer and when
The client appoints the principal designer. The client is the person or business the project is carried out for. A developer or a building owner is a client.
The trigger is the same in both laws. You must appoint when more than one contractor will work on the project, or when that is reasonably foreseeable. For example, a builder and a separately appointed electrician are two contractors.
The timing differs slightly.
- CDM 2015. As soon as is practicable, and in any event before the construction phase begins.
- Building Regulations. Before the construction phase begins.
- Higher-risk building work. Before the building control approval application goes to the regulator.
HSE guidance says the CDM appointment should be made as early as possible, and where practicable at the concept stage. HSE says design decisions made before work starts have a significant effect on safety. Our guide to the RIBA stages shows where the concept stage sits.
What the client must do in writing
Both laws put the paperwork on the client. This is the list to keep on file. Items 3, 4 and 6 come from the Building Regulations.
- Appoint the principal designer in writing. One appointment for each set of regulations, or one certificate that covers both.
- Appoint the principal contractor in writing. The same rule applies to the builder in control of the work.
- Certify a shared role, if you use one. You can certify in writing that your CDM principal designer is treated as the Building Regulations one.
- Check competence first. Take all reasonable steps to check the designer has the skills, knowledge, experience and behaviours for the role.
- Share building information. Give every designer and contractor what you know about the building and the work.
- Replace a leaver. If the appointment ends early, appoint a new principal designer as soon as reasonably practicable.
If a business client appoints nobody, the duties do not vanish. The client must fulfil them itself until someone is appointed. Our guide to CDM 2015 client duties on a fit-out covers the health and safety side.
Homes are treated differently. If a homeowner makes no appointment, the designer in control of the design phase is the principal designer.
Great experience from start to finish. Communication was clear, the workmanship was excellent, and the whole project was managed professionally.
Whether the architect is the principal designer
The law does not name a profession. It sets a test. The principal designer must be a designer with control over the design work, and competent for the role.
| Rule | CDM 2015 | Building Regulations (England) |
|---|---|---|
| Must be a designer | Yes, as the regulations define it | Yes, with control over the design work |
| Can be a company | Yes | Yes, with a named individual managing the role |
| Must draw the building | No. HSE says they "do not have to carry out actual design work" | Guidance says be part of the design team, not an outside third party |
| What they need | Skills, knowledge and experience | Skills, knowledge, experience and behaviours |
So an architect who leads the design can hold the role. So can another designer who controls the design work. What matters is control and competence, not the job title.
A company can be appointed. It must name a person to manage the role. GOV.UK guidance says the legal responsibility stays with the company.
Higher-risk buildings and Gateway 2
Extra rules apply to higher-risk building work. GOV.UK guidance describes a higher-risk building in two parts. It has at least 7 storeys or is at least 18 metres high. It also has at least 2 residential units, or is a hospital or a care home.
On this work the client must do more.
- Appoint earlier. Both roles must be in place before the building control approval application is submitted to the regulator.
- Keep records. Keep a written record of the steps taken to check each appointee is competent.
- Ask about sanctions. Ask whether a serious sanction has occurred in the last 5 years.
The principal designer also gets extra duties. GOV.UK guidance lists a system for reporting safety occurrences. It also lists storing the record of information about the building, known as the golden thread.
Our guides to the Building Safety Act for building owners and to Gateway 2 and second staircases cover this in more detail.
What one team that designs and builds changes
The principal designer and the principal contractor must share information. The Building Regulations say each must have regard to the other's comments. That is hard when the designers and the builder have never met.
It is simpler when they sit in one business. Craftex is a team of architects with 50 years of experience, interior designers, engineers and builders.
Our architects lead and coordinate the design team, and the people who will build it sit at the same table. One team draws the building, takes it through planning, prices it while it is drawn and builds it under one contract.
Our people bring combined team experience of 834 design projects. We take on projects from £100,000 to £10M and above in construction value.
At the first meeting, ask any team three things. Who will hold each principal designer role? Who is the named person? What will you receive in writing? Discuss your project and ask us the same.