RIBA Stage 5: Manufacturing and Construction on Site
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
RIBA Stage 5 is Manufacturing and Construction, the sixth of the eight stages in the RIBA Plan of Work 2020. It starts when the contractor takes possession of the site and ends at Practical Completion.
- The building is manufactured, built and commissioned.
- There is no design work, other than answers to site queries.
- Someone must be named to inspect the quality of the work.
- You receive a building manual and a Practical Completion certificate.
RIBA Stage 5 is Manufacturing and Construction. It is the stage where the drawings turn into a building. Parts are made, the site is run and the finished systems are tested.
This guide shows who does what on site and what you hold at the end. Craftex works as design and build architects and builders in one team. About to build? Discuss your project with us.
What RIBA Stage 5 is
The RIBA Plan of Work 2020 splits a project into eight stages, numbered 0 to 7. Stage 5 follows Stage 4, Technical Design. Our guide to all the RIBA stages shows the full sequence.
The RIBA gives Stage 5 one outcome: "Manufacturing, construction and Commissioning completed."
Commissioning means adjusting systems such as heating and ventilation until they work as specified.
The stage has a clear start and end. It commences when the contractor takes possession of the site. It finishes at Practical Completion, when the work is certified as practically complete under the building contract.
| Core task | In plain words |
|---|---|
| Finalise site logistics | Plan deliveries, access, storage and the site set-up |
| Manufacture and construct | Make the parts and build the building |
| Monitor progress | Check the work against the construction programme |
| Inspect construction quality | Check workmanship against the contract |
| Resolve site queries | Answer the builder's questions about the drawings |
| Commission the building | Test and adjust the systems |
| Prepare the building manual | Gather the information you need to run the building |
The RIBA is strict on one point. There is no design work in Stage 5, other than answers to site queries. Design left until the site is running is late Stage 4 work.
The architect's role on site
The Plan of Work does not fix the architect's site role. It says the roles must be clear from the outset. Four jobs need a name beside them.
- Answering site queries. A site query is a question from the builder to the design team about the contract information.
- Reporting on quality. Regular reports on whether the work meets the contract.
- Inspecting the works. Visits to check what has been built and to monitor progress.
- Producing the defects list. A list of items that do not meet the contract when Practical Completion is certified.
These jobs may sit with the design team that drew the building. The RIBA says they may also sit with a separate role or a client team.
Changes on site are a separate matter. Our guide to variations in construction contracts explains how a change is priced and agreed.
Design and build vs traditional at Stage 5
The route you chose decides who the designers work for during the build.
| Question | Traditional | Design and build |
|---|---|---|
| Who employs the builder | You | You |
| Who the design team works for | You | The RIBA notes the team may be novated, so its contract moves to the builder |
| Who answers site queries | Your design team | The design team, which may now work for the builder |
| Who inspects for you | Set in your appointments | Set in your appointments; the RIBA notes a shadow design team may be appointed to monitor |
The RIBA makes a plain point about newer routes. They "do not necessarily provide clarity on who is to inspect the ongoing construction works". It says the client needs to consider how much inspection the project requires.
Our guides compare design and build vs traditional procurement and explain the JCT Design and Build contract.
Safety on site runs under its own law. The RIBA lists carrying out the construction phase plan as a Stage 5 task. Our guide to the CDM Regulations 2015 explains that plan.
Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.
What is handed over at the end of Stage 5
Stage 5 ends with a certificate and a set of information. The RIBA lists what should change hands.
| RIBA item | What it is |
|---|---|
| Practical Completion certificate | Confirms the work is practically complete under the contract |
| Defects list | Items still to be put right, attached to the certificate |
| Building manual | A summary of the key information about the building |
| Health and safety file | Safety information for future work on the building, inside the manual |
| Fire safety information | Design and construction details that help manage fire safety, inside the manual |
| Asset information | Information used to manage and maintain the building |
The RIBA says even the simplest project requires a building manual. Decide early what you need in it, so it can be collected at each stage.
One example from our own work. On Medusa, a salon and spa in Knightsbridge, we managed building control and obtained all the certificates. We handed over as-built drawings and the operation and maintenance manuals. Read the Medusa case study.
After Practical Completion comes Stage 6, Handover. It runs to the end of the defects liability period.
What one team that designs and builds changes
On site, time is lost in the gap between a question and its answer. A builder asks. A separate designer may take days to reply. The work waits.
At Craftex the question and the answer sit in one team. Craftex is a team of architects with 50 years of experience, interior designers, engineers and builders.
One team draws the building, takes it through planning, prices it while it is drawn and builds it under one contract. The people who drew a detail work in the same team as the people who build it. You have one firm to hold to the result.
Our people bring combined team experience of 561 major construction projects. We take on projects from £100,000 to £10M and above in construction value. Have drawings ready to build? Discuss your project and send us what you have.