RIBA Stage 5: Manufacturing and Construction on Site

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read

Concrete-frame building under construction with a red tower crane against a blue sky

The short answer

RIBA Stage 5 is Manufacturing and Construction, the sixth of the eight stages in the RIBA Plan of Work 2020. It starts when the contractor takes possession of the site and ends at Practical Completion.

  1. The building is manufactured, built and commissioned.
  2. There is no design work, other than answers to site queries.
  3. Someone must be named to inspect the quality of the work.
  4. You receive a building manual and a Practical Completion certificate.

RIBA Stage 5 is Manufacturing and Construction. It is the stage where the drawings turn into a building. Parts are made, the site is run and the finished systems are tested.

This guide shows who does what on site and what you hold at the end. Craftex works as design and build architects and builders in one team. About to build? Discuss your project with us.

What RIBA Stage 5 is

The RIBA Plan of Work 2020 splits a project into eight stages, numbered 0 to 7. Stage 5 follows Stage 4, Technical Design. Our guide to all the RIBA stages shows the full sequence.

The RIBA gives Stage 5 one outcome: "Manufacturing, construction and Commissioning completed."

Commissioning means adjusting systems such as heating and ventilation until they work as specified.

The stage has a clear start and end. It commences when the contractor takes possession of the site. It finishes at Practical Completion, when the work is certified as practically complete under the building contract.

The RIBA's core tasks at Stage 5
Core taskIn plain words
Finalise site logisticsPlan deliveries, access, storage and the site set-up
Manufacture and constructMake the parts and build the building
Monitor progressCheck the work against the construction programme
Inspect construction qualityCheck workmanship against the contract
Resolve site queriesAnswer the builder's questions about the drawings
Commission the buildingTest and adjust the systems
Prepare the building manualGather the information you need to run the building

The RIBA is strict on one point. There is no design work in Stage 5, other than answers to site queries. Design left until the site is running is late Stage 4 work.

The architect's role on site

The Plan of Work does not fix the architect's site role. It says the roles must be clear from the outset. Four jobs need a name beside them.

  1. Answering site queries. A site query is a question from the builder to the design team about the contract information.
  2. Reporting on quality. Regular reports on whether the work meets the contract.
  3. Inspecting the works. Visits to check what has been built and to monitor progress.
  4. Producing the defects list. A list of items that do not meet the contract when Practical Completion is certified.

These jobs may sit with the design team that drew the building. The RIBA says they may also sit with a separate role or a client team.

Changes on site are a separate matter. Our guide to variations in construction contracts explains how a change is priced and agreed.

Design and build vs traditional at Stage 5

The route you chose decides who the designers work for during the build.

Who does what on site under each route
QuestionTraditionalDesign and build
Who employs the builderYouYou
Who the design team works forYouThe RIBA notes the team may be novated, so its contract moves to the builder
Who answers site queriesYour design teamThe design team, which may now work for the builder
Who inspects for youSet in your appointmentsSet in your appointments; the RIBA notes a shadow design team may be appointed to monitor

The RIBA makes a plain point about newer routes. They "do not necessarily provide clarity on who is to inspect the ongoing construction works". It says the client needs to consider how much inspection the project requires.

Our guides compare design and build vs traditional procurement and explain the JCT Design and Build contract.

Safety on site runs under its own law. The RIBA lists carrying out the construction phase plan as a Stage 5 task. Our guide to the CDM Regulations 2015 explains that plan.

Happy with the end result. Tight timeline but they pulled it off. The team worked late shifts and even weekends to help us open the doors on schedule. Site was always left tidy at the end of the day and no surprise charges either. Good communication throughout. Would definitely use Craftex again.

Pawel Kamionka, Google reviewSee all reviews on Google

What is handed over at the end of Stage 5

Stage 5 ends with a certificate and a set of information. The RIBA lists what should change hands.

What you receive at the end of RIBA Stage 5
RIBA itemWhat it is
Practical Completion certificateConfirms the work is practically complete under the contract
Defects listItems still to be put right, attached to the certificate
Building manualA summary of the key information about the building
Health and safety fileSafety information for future work on the building, inside the manual
Fire safety informationDesign and construction details that help manage fire safety, inside the manual
Asset informationInformation used to manage and maintain the building

The RIBA says even the simplest project requires a building manual. Decide early what you need in it, so it can be collected at each stage.

One example from our own work. On Medusa, a salon and spa in Knightsbridge, we managed building control and obtained all the certificates. We handed over as-built drawings and the operation and maintenance manuals. Read the Medusa case study.

After Practical Completion comes Stage 6, Handover. It runs to the end of the defects liability period.

What one team that designs and builds changes

On site, time is lost in the gap between a question and its answer. A builder asks. A separate designer may take days to reply. The work waits.

At Craftex the question and the answer sit in one team. Craftex is a team of architects with 50 years of experience, interior designers, engineers and builders.

One team draws the building, takes it through planning, prices it while it is drawn and builds it under one contract. The people who drew a detail work in the same team as the people who build it. You have one firm to hold to the result.

Our people bring combined team experience of 561 major construction projects. We take on projects from £100,000 to £10M and above in construction value. Have drawings ready to build? Discuss your project and send us what you have.

Frequently asked questions

What is RIBA Stage 5?

RIBA Stage 5 is Manufacturing and Construction. The RIBA Plan of Work 2020 gives its outcome as manufacturing, construction and commissioning completed.

When does RIBA Stage 5 start and end?

The RIBA says it commences when the contractor takes possession of the site and finishes at Practical Completion. Practical Completion is the point when the work is certified as practically complete under the building contract.

Is there design work in RIBA Stage 5?

The RIBA says there is no design work in Stage 5 other than responding to site queries. Design by specialist subcontractors belongs to Stage 4, even where the two stages overlap.

What does the architect do during construction?

It depends on the appointment. The design team may answer site queries, inspect quality and help prepare the defects list. The RIBA says a separate person or a client team may do this instead.

What is a site query?

The RIBA defines it as a question from the contractor to the design team. It clarifies information in the contract documents, or asks for information that was not complete when the contract was agreed.

What comes after RIBA Stage 5?

Stage 6, Handover. It starts straight after Practical Completion and finishes at the end of the defects liability period.

Refer a project

Earn 5–10% lifetime commission

from the revenue we generate from your introduction.

Architects, agents, developers, business owners: anyone can refer. Introduce a client and we pay you on their first project and every project after it, for as long as they work with us. The rate depends on the project and is agreed in writing before work starts.

Rates and conditions apply. See the referral terms.

Want the designers and the builders to be one team on site?

Our architects stay with the project while our construction team builds it under one contract. Send us your drawings. We reply within one hour, Monday to Saturday, 8am to 6pm.

Reply within 1 hour, Mon–Sat 8am–6pm. Urgent? WhatsApp us for a reply straight away, any day.

WhatsApp us