RIBA Stage 4 Technical Design: What You Receive
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
RIBA Stage 4 is Technical Design, the fifth of the eight stages in the RIBA Plan of Work 2020. By its end, all the design information needed to manufacture and construct the project is complete.
- You receive construction information, manufacturing information and final specifications.
- The Building Regulations application is made during Stage 4.
- The design team and the builder's specialist subcontractors both design in this stage.
- The RIBA says Stage 4 overlaps with Stage 5 on most projects.
RIBA Stage 4 is Technical Design. It is the stage where the design becomes a full set of instructions for the builder. By its end, everything needed to manufacture and construct the project is drawn and written down.
This guide shows what you should hold when Stage 4 ends. Craftex offers technical design by our architects, priced by our construction team as it is drawn. Have drawings already? Discuss your project with us.
What RIBA Stage 4 is
The RIBA Plan of Work 2020 splits a project into eight stages, numbered 0 to 7. Stage 4 follows Stage 3, Spatial Coordination. Our guide to all the RIBA stages shows the full sequence.
The RIBA gives Stage 4 one outcome: "All design information required to manufacture and construct the project completed."
Four core tasks sit in the stage.
- Technical design. The architects and engineers develop their design in full detail.
- Design team information. The team prepares and coordinates information for each building system, such as walls, roof and heating.
- Specialist design. Specialist subcontractors design their own systems, and that work is fitted into the whole.
- A design programme. A timetable shows who draws what, and when.
Two legal steps also belong here. The Building Regulations application is made during Stage 4, before work starts on site. Planning conditions that must be cleared before work starts are discharged too.
What drawings and specifications you receive
The RIBA lists the information that changes hands at the end of Stage 4. This table puts each item in plain words.
| RIBA item | What it is | Why you need it |
|---|---|---|
| Construction Information | Drawings and schedules used to build on site | The builder prices and builds from it |
| Manufacturing Information | Details used to make parts off site, mostly by specialists | Factory-made items fit when they arrive |
| Final Specifications | Written rules for products, workmanship and tolerances | They set the quality in the contract |
| Residual Project Strategies | Strategies still running, such as fire safety or sustainability | They carry on into the build |
| Building Regulations Application | The submission to building control | The RIBA says to make it before work starts on site |
The RIBA uses two more terms worth knowing. Prescriptive information is complete and instructive. The builder can build from it. Descriptive information states the design intent, so a specialist can design that system.
Ask which parts of your building will be drawn in full by the design team. Ask which parts a specialist will design later. That split decides what a builder can price firmly today. Our guide to planning and building regulations drawings shows what each drawing set looks like.
Who does the work at Stage 4
The RIBA names two groups. The design team completes its design. The specialist subcontractors employed by the contractor complete theirs.
A lead designer directs the work and checks that the parts fit. On some projects the client also appoints a monitoring team to review what is produced.
The RIBA is firm on one point. Specialist design belongs in Stage 4, not Stage 5. For example, a lift or a kitchen extract system should be designed before it is built, not during.
This is where the choice of route matters. The RIBA says the design team may be novated to the construction team. Novated means their contract moves from you to the builder. Our guide to design and build vs traditional procurement explains what that changes for you.
Stage 4 and the fixed build price
A price is only as firm as the drawings behind it. The RIBA notes that Stage 3 information is "unlikely to contain sufficient detail to allow robust tenders to be prepared".
Stage 4 closes that gap. The specifications are written and the details are drawn. The RIBA says the final cost plan becomes a pre-tender cost estimate. Our guide to the construction cost plan follows that document from first sketch to tender.
When you sign depends on the route.
- Traditional. The design team's work should be substantially complete before the building contract is signed.
- Two-stage design and build. The client may sign after the major packages have been secured.
Our guide to the two-stage tender explains the second route.
Before you sign, check four things.
- Every package is listed. You know which are fully drawn and which a specialist will design.
- The specification is final. Products and finishes are named, not left as "to be confirmed".
- The approvals route is agreed. The Building Regulations application is in or ready.
- Open items are priced. Any unknowns are shown as clear sums, not hidden.
I worked perfectly with Sviat and Joe, with their architect they came up with a very smart design for our office to fit more desks and optimise the space to its maximum capacity. They also did excellent value engineering on the MEP design proposed by others, allowing us to save around £50K. The quality and speed were outstanding we finished two weeks ahead of schedule. Highly recommend these guys.
How long Stage 4 takes
The RIBA Plan of Work does not set a length for any stage. The time depends on your project. Four things drive it.
- Size and type. A clinic or a restaurant kitchen needs more detail than an open office floor.
- Number of specialists. Each specialist system adds a round of design and review.
- The route. The RIBA says the procurement route might require Stage 4 to be done in two parts.
- Approvals. Building control and planning conditions run beside the drawing work.
The RIBA also says Stage 4 will overlap with Stage 5, Manufacturing and Construction on most projects. Work can start on site while later packages are finished.
One example from our own work. Medusa is a 180 sq m salon and spa in Knightsbridge. Our team took it from concept to full technical design, then built it. The whole job, a £460K project, took 17 weeks from concept to handover. Read the Medusa case study.
What one team that designs and builds changes
On a traditional route the designer finishes Stage 4 and a separate builder then prices it. Gaps can show up at that hand-over. The builder may find details that cost more than the cost plan allowed.
At Craftex the work does not change hands. Craftex is a team of architects with 50 years of experience, interior designers, engineers and builders.
One team draws the building, takes it through planning, prices it while it is drawn and builds it under one contract. The people who will build each detail see it before it is fixed. Our pre-construction services page explains how this works.
We take on projects from £100,000 to £10M and above in construction value. Have a Stage 3 design and need it taken to construction drawings? Discuss your project and send us what you have.