Best Clinic Fit-Out Companies in London: How to Choose One That Gets You Open and Registered

Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read

Blue glass chandelier and mirrored walls in the finished Medusa spa and beauty clinic, Knightsbridge, fitted out by Craftex

The short answer

The best clinic fit-out company designs for what CQC and the council will check, not just for looks. It then hands over on the date your lease and staff plan assume.

  1. Ask which healthcare guidance it designs your rooms to.
  2. Check infection control is built into finishes and layout.
  3. Agree who handles landlord consent, building control and licences.
  4. Get a programme built backwards from your opening date.

Most clinic owners judge a fit-out company by its photos. Then the trouble starts after the build. The treatment room has no clinical basin. The laser room has the wrong ventilation. Or the borough wants a licence nobody applied for. Rent is running, staff are hired, and the opening date slips.

This guide compares the types of clinic fit-out company in London. It sets out the seven criteria that matter for registration and opening day, and where we fit as a clinic fit out in London contractor. For the regulatory detail, read our guide to clinic fit-out CQC requirements.

Have premises in mind? Book a site visit and bring your treatment list.

Seven things the best clinic fit-out companies get right

Good-looking rooms are the easy part. These seven decide whether you open on time and pass registration.

1. They design for registration, not just for looks

CQC must be satisfied your premises meet Regulation 15. That means clean, secure, suitable for purpose and properly maintained. CQC guidance says premises should take account of national best practice.

For clinical rooms, the NHS Health Building Notes and Health Technical Memoranda are the usual design benchmarks. Ask which ones the company will design your rooms to.

2. Infection control is built into the finishes

Wipe-clean sealed surfaces, coved flooring and clinical hand-wash basins are design decisions. So is the split between clean and dirty routes. They are cheap to get right on paper and costly to change later.

3. Ventilation and services suit the treatments

Treatment, laser, procedure and decontamination rooms each need different air, power and water. A general fit-out contractor may not know this. A healthcare-experienced one asks for your treatment list before it draws.

4. Patients can get in, wait and talk in private

Step-free access, accessible toilets and a calm waiting area shape the layout. So does privacy at reception. CQC guidance also covers seating, waiting space, privacy and dignity.

5. They manage the consents around the build

Most leased units need the landlord's written consent first. Our guide to licences for alterations covers that side. Building control comes next.

In London, many boroughs also license treatments such as massage, laser and acupuncture. That is a special treatment licence, with exemptions for some health professionals. Ask who manages each consent, and when.

6. The programme starts from your opening date

Rent, staff and marketing usually start before the first patient. So the programme should run backwards from your opening and registration dates. Long-lead equipment and finishes must be ordered early.

7. Aftercare is written down

Clinics run hard from day one. Ask what aftercare period is included. Ask how fast defects are fixed once you're seeing patients.

Clinic fit-out company types compared

Each type suits a different clinic. Pick the type first, then compare firms of that type.

Types of clinic fit-out company and when each fits
Type of companyBest forWatch for
Specialist healthcare or dental fit-out firmDental and specialist clinical premisesLess design freedom outside clinical rooms
Equipment supplier's fit-out packageSingle-discipline clinics where equipment sets the layoutFit-out quality outside the surgery
Interior designer plus a separate builderAesthetic and wellness clinics where brand comes firstGaps between design intent and compliance
General commercial fit-out contractorClinics with a finished, compliant designHealthcare detail
Design and build team with healthcare workMulti-floor or design-led clinics needing compliance and finish togetherCheck its projects match your clinic type

What our clinic work shows

One project shows how the clinical services and the finish come together in a treatment clinic.

Treatment room with lilac walls, two velvet armchairs, a round mirror and lit shelving at Medusa, Knightsbridge
Medusa, Knightsbridge: 180 sq m over four floors in 17 weeks.

Medusa, Knightsbridge: a four-floor clinic in 17 weeks

Medusa is a spa and beauty clinic on four floors, 180 sq m in total. It was a £460K turnkey design and build fit-out, delivered in 17 weeks.

The client came to us at RIBA Stage 2 with a concept. Our team finished the design and stripped out all four floors. We fitted new partitions, ceilings, electrics, fire and intruder alarms, CCTV, air conditioning and ventilation. Designing and pricing together kept the concept within budget.

Holistic therapy space fit-out Super impressed. I had a very specific vision for the studio. calm tones, soft lighting, hidden storage etc. the craftex team just got it. build was done quicker than I expected and the guys were polite, tidy and actually listened. we had 2 snags on day one but they fixed it before the week was out. worth it for the peace of mind.

Dariia Shvyryda, Google reviewSee all reviews on Google

The team behind a clinic fit-out

The people who run the job matter more than the brochure. Earlier projects below are from their careers before Craftex.

  1. Joe Crawford, Operations Director: 37 years in construction, on projects of up to £135M, including the Dior flagship on Bond Street.
  2. Martin Hickey, Preconstruction Director: more than 50 years in construction.
  3. Konstantin Jegorovs, Projects Director: 16 years, an Oxford Brookes construction management graduate.

Craftex has traded since 2016. We hold ISO and CHAS accreditation and carry £10M public and employers' liability cover. Around 60% of our labour is in-house.

Speed matters too. At Beaumont House we refurbished 750 sq m of offices in three weeks, with zero snags.

Where Craftex is not the right fit

We would rather tell you now than after a survey.

  1. Projects under £100,000. A single room refresh suits a local fit-out firm. Our construction work starts at £100,000.
  2. A dental surgery where the supplier package covers everything. One contract for chairs, equipment and a standard layout is simpler.
  3. You need a CQC registration consultant. We design and build premises that support registration. The application is yours or your adviser's.

Five steps to choose a clinic fit-out company in London

  1. List your regulated activities and treatments, and check the registration and licences they need.
  2. Shortlist two or three companies of different types from the table.
  3. Ask each which healthcare guidance it will design to, and to show a similar project.
  4. Get a programme built backwards from your opening date, with long-lead items named.
  5. Compare scope and exclusions, not just the headline price.

See our clinic fit-out and refurbishment service for how we deliver clinics in London. If you have a unit in mind, book a site visit before you sign the lease.

Frequently asked questions

What does a clinic fit-out company do?

It designs and builds the inside of a clinic: layout, partitions, ceilings, flooring, treatment rooms, plumbing, ventilation, power, lighting, fire and security systems and finishes. It then hands over premises ready for equipment, registration and patients.

Does a clinic need CQC registration before it opens?

If you carry out regulated activities, yes. CQC registers the provider and must be satisfied the premises meet Regulation 15: clean, secure, suitable, properly used and properly maintained. Design the fit-out with that in mind from day one.

What guidance should a clinic fit-out follow?

CQC guidance says premises should take account of national best practice. For clinical rooms, ventilation, water and decontamination, the NHS Health Building Notes and Health Technical Memoranda are the usual design benchmarks.

How long does a clinic fit-out take?

It depends on size, condition and services. Our Medusa spa and beauty clinic, 180 sq m over four floors, took 17 weeks. A larger clinic with heavier clinical services takes longer. A survey and a fixed design set the real programme.

Do I need a special treatment licence in London?

Possibly. Most London boroughs license treatments such as massage, laser, acupuncture and electrolysis under the London Local Authorities Act 1991, with exemptions for some registered health professionals. Ask the borough early.

What is the minimum project size for Craftex?

Our construction projects start from £100,000.

Signed the lease, but not sure the unit works as a clinic?

Our design and build team checks the rooms, ventilation, water and access against your treatments, then plans the fit-out around your opening date. Book a site visit.

WhatsApp us