For clients, developers and building owners
RIBA Stage 3 Spatial Coordination: What Gets Fixed
Sviatoslav JerdetchiiCEO & Founder of Craftex. Updated , 5 min read
The short answer
RIBA Stage 3 is Spatial Coordination, the fourth of the eight stages in the RIBA Plan of Work 2020. Its outcome is architectural and engineering information that is spatially coordinated: every space is fixed, so Stage 4 can run without redesign.
- The concept is tested with design studies, engineering analysis and cost exercises.
- Structure, plant rooms and risers get their fixed places.
- You receive a signed-off stage report, an updated cost plan and updated strategies.
- The RIBA says planning applications are generally submitted at the end of Stage 3.
RIBA Stage 3 is Spatial Coordination. It is the stage where a good-looking concept is made to work as a real building. Structure, pipes, ducts and stairs all find their fixed places.
This guide shows what happens in Stage 3 and what to approve before you leave it. Craftex provides architectural design services with the build priced as the design is drawn. Have a concept? Discuss your project with us.
What RIBA Stage 3 is
The RIBA Plan of Work 2020 splits a project into eight stages, numbered 0 to 7. Stage 3 follows Stage 2, Concept Design. Our guide to all the RIBA stages shows the full sequence.
The RIBA gives Stage 3 one outcome: "Architectural and engineering information Spatially Coordinated."
Spatially coordinated has a set meaning. The spaces you asked for are fixed. So are the spaces the building systems need, such as column grids, risers and plant rooms. A riser is a vertical shaft for pipes and cables.
Three core tasks sit in the stage.
- Test the concept. Design studies, engineering analysis and cost exercises check that the concept works.
- Start change control. From now on, a change to the design goes through an agreed procedure.
- Plan the design work. A stage design programme shows who does what, and when.
The team also reviews the design against the Building Regulations. The cost plan is updated as detail is added.
| Point | What the RIBA Plan of Work 2020 says |
|---|---|
| Name | Spatial Coordination |
| Outcome | Architectural and engineering information spatially coordinated |
| Who leads | The lead designer and the design team |
| Your part | Decisions the coordination needs, and sign-off of the stage report |
| Planning | Applications are generally submitted at the end of the stage |
| You receive | Signed-off stage report, project strategies, updated outline specification, updated cost plan, planning application |
What changed from the old Stage 3 Developed Design
Before the 2020 edition, Stage 3 carried the name Developed Design. The RIBA's own comparison chart in the 2020 Overview still shows that earlier name. The RIBA calls the 2020 edition "a clarification of the 2013 structure".
The new name says what the stage is for. Three points in the 2020 guidance matter to a client.
- The concept is not redesigned. The RIBA says Stage 3 "is not about adjusting the Architectural Concept, which should remain substantially unaltered".
- Loose ends stay in Stage 2. A project should not move to Stage 3 while room sizes or room positions are still open.
- Specialist reports land on time. Most project strategies, such as fire safety, should be concluded by the end of Stage 3.
Why this helps you: each designer can then finish their own drawings at Stage 4, Technical Design without undoing someone else's work.
The planning application at Stage 3
The RIBA's planning note is clear. Planning applications are generally submitted at the end of Stage 3. The design is then based on the best information the team has.
Some clients apply earlier. The RIBA says this should only happen when the threshold of information required has been met. It asks for a gateway part-way through the stage, with a list of what must be ready.
There is a reason for the caution. A design that wins consent before the structure and services are fitted may need changes afterwards. Changes after consent may need a further application to the council.
At Stage 3 the RIBA lists these planning tasks.
- Use the advice. Feed pre-application advice from the council into the design.
- Test the effects. Study the effect on neighbours, the local setting and the environment.
- Write the documents. Prepare the design and access statement, if one is required, and the supporting reports.
- Know the conditions. Establish the likely planning conditions and payments to the council.
Our guides explain what a planning application is and how pre-application planning advice works. For help with the application itself, see our planning consultancy service.
Fuse Energy hired Craftex on the fit-out and installation of our engineering and research centre, which included electrical, heating, lighting, plumbing, and ventilation upgrades. They delivered everything to a high standard and were proactive throughout — even working weekends to help speed up the programme, despite not being contracted to. They managed last-minute changes very well, communication was clear and consistent, and the team was professional from start to finish. We’d happily recommend Craftex to anyone needing a reliable construction partner.
What to sign off before Stage 4
Stage 3 ends when you sign off the stage report. The RIBA describes it as a record of the decisions made and the outcome of the design process.
Check these six things before you sign.
- The layout is final. Every room has its size and its place.
- The structure fits. Columns, beams and walls are shown on the plans.
- The services fit. Plant rooms, risers and ceiling space are large enough.
- The cost plan is updated. It matches the design in front of you and your budget.
- The strategies are complete. Fire safety, access and the others are written up.
- Changes are controlled. You know how a change is asked for and approved from here on.
One warning on price. Under some routes, Stage 3 information is used to tender the work. The RIBA says it is "unlikely to contain sufficient detail to allow robust tenders to be prepared". Our guide to the construction cost plan shows how firm the figure is at each stage.
What one team that designs and builds changes
Coordination is a test of whether the drawings can be built. It is strongest when a builder is in the room. The RIBA notes the construction team may be involved at Stage 3 where the route calls for early input.
At Craftex the builders are always in the room. Craftex is a team of architects with 50 years of experience, interior designers, engineers and builders.
One team draws the building, takes it through planning, prices it while it is drawn and builds it under one contract. Our people bring combined team experience of 11,127 homes taken through planning.
We take on projects from £100,000 to £10M and above in construction value. Have a concept that needs coordinating before planning? Discuss your project and send us what you have.